ITB_FAC260128_275-Ton_Air-Cooled_Chiller_Replacement_-_Addendum_1.pdf

PDF 121 KB Posted

Attached to
275-Ton Air-Cooled Chiller Replacement
Solicitation number
ITB# FAC/260128
Issued by
Marion County, Orlando City, Florida

About this file

This is Addendum #1 to an Invitation to Bid (ITB) issued by the City of Ocala, Florida for the replacement of a 275-ton air-cooled chiller system at City Hall and the Customer Service Center. The project involves supplying and installing a new chiller unit to replace an existing 200-ton York chiller. A mandatory pre-bid meeting was held on November 10, 2025 at 10:00 AM at City Hall, 110 SE Watula Ave, Ocala, FL 34471. An optional site visit for vendors and subcontractors who attended the mandatory meeting is scheduled for November 21, 2025 from 10:00 AM to 11:00 AM, with follow-up questions due through ProRFx by November 24, 2025 at 5:00 PM. Bidders must be licensed mechanical contractors in Florida with a minimum of five years of experience in mechanical services.

The addendum clarifies that temporary cooling will not be required if the contractor can complete the chiller shutdown and replacement over a weekend (Friday midday through Monday morning). The scope includes disconnecting and reconnecting the existing Honeywell building controls system, with the awarded contractor responsible for coordination and commissioning. The contractor must also modify the steel enclosure structure surrounding the chiller by cutting existing steel and welding mounting plates to allow future removal and reinstallation of the top section. The 5-year Total Maintenance and Repair pricing item previously listed in Exhibit B has been removed from the scope. An amended Exhibit B reflecting this change has been uploaded for bidder reference.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum # 1

Date: November 10, 2025

To: All bidders

From: Caley Conard, Buyer

Solicitation Number: ITB# FAC/260128

Solicitation Title: 275-Ton Air-Cooled Chiller Replacement

SECTION 1. QUESTIONS AND ANSWERS

1.1 QUESTION: Will temporary cooling be required as part of this ITB?

ANSWER: The current plan is to shut down the chiller midday on Friday, with work to be completed over the weekend and the chiller operational by Monday morning. As long as the Contractor can meet this schedule, temporary cooling will not be required.

1.2 QUESTION: Who provides the building controls?

ANSWER: Honeywell provides building controls. The scope of work will involve a disconnect and reconnect of the existing system; awarded contractor coordinates and commissions the system to confirm appropriate operation.

SECTION 2. SOLICITATION ADDITIONS, CLARIFICATIONS AND CORRECTIONS

1.1 Awarded contractor will modify the top steel portion of the chiller enclosure located outside the City Hall and

Customer Service building. This will involve cutting the existing steel and welding mounting plates to allow the top section of the enclosure to be removed and reinstalled in the future, as necessary.

1.2 The item listed in Exhibit B – Price Proposal under “5-Year TMR (Total Maintenance & Repair) *Drive time included” is no longer being requested as part of this Invitation to Bid. Amended Exhibit B has been uploaded to reflect the change in scope.

EXHIBITS

Chiller CD6 2002 York

YC1V0247VA46VAB5XTXXXX

XLXX

XX445XXXXXHXDW5AXRBX

X1XXX XXHH1AXX

SBXM855040

200 Ton

SECTION 1. QUESTIONS AND ANSWERS

File details come from the government source that posted it. Updated .