The document is an Invitation to Bid (ITB) ENG/250425 for the City of Ocala, Florida, seeking a contractor to construct a Three Million Gallon (3MG) Ground Storage Tank at Water Treatment Plant #2 located at 3744 S Pine Avenue. The project involves comprehensive concrete water tank construction services, with a non-mandatory pre-bid meeting scheduled for 3/20/2025 at 10:00 AM EST. The contractor will be responsible for providing all materials, labor, and equipment to complete the construction as detailed in Exhibit B (Plan Set) and Exhibit C (Electrical Plan), with specific requirements for site work, mechanical site piping, and tank construction.

The bid is to be submitted on a lump sum basis, with bidders required to bid on all line items. A 5% bid bond is required, and the contract award will be made to the lowest bidder meeting all specified requirements. Bidders must be licensed General Contractors in Florida with at least five years of experience in water ground storage tank construction. The contract includes a three-year warranty period for all materials and workmanship, with the contractor responsible for replacing any defective materials or work at no cost to the City. Pricing shall remain valid for 90 days after award, and the successful bidder must remain current on all obligations to the City throughout the project duration.

View the file

Other files

File Type Posted
ITB_ENG250425_Water_Treatment_Plant_No._2_GST_No._1_Construction_Updated_-_SIGN-IN_SHEET.pdf PDF
ITB_ENG250425_Water_Treatment_Plant_No._2_GST_No._1_Construction_Updated_-_Addendum_2.pdf PDF
ITB_ENG250425_Water_Treatment_Plant_No._2_GST_No._1_Construction_Updated_-_NEW_3.25.25_Exhibit_I_-_Geotechnical_Investigation_Report-_Ocala_WTP_2.pdf PDF
ITB_ENG250425_Water_Treatment_Plant_No._2_GST_No._1_Construction_Updated_-_NEW_3.25.25_Exhibit_K_-_33_16_00_-_3.0_MG_Prestressed_Concrete_Tank.pdf PDF
ITB_ENG250425_Water_Treatment_Plant_No._2_GST_No._1_Construction_Updated_-_NEW_3.25.25_Exhibit_J_-_Confirmation_of_Geotechnical_Recommendation_-_Ocala_WTP_2.pdf PDF
ITB_ENG250425_Water_Treatment_Plant_No._2_GST_No._1_Construction_Updated_-_NEW_Exhibit_H_-_Electrical_Plan__2.pdf PDF
ITB_ENG250425_Water_Treatment_Plant_No._2_GST_No._1_Construction_Updated_-_Addendum_1.pdf PDF
ITB_ENG250425_Water_Treatment_Plant_No._2_GST_No._1_Construction_Updated_-_NEW_Exhibit_G_-_Plan_Set__2.pdf PDF
ITB_ENG250425_Water_Treatment_Plant_No._2_GST_No._1_Construction_Updated_-_Exhibit_F_-_Price_Proposal.xlsx XLSX spreadsheet
ITB_ENG250425_Water_Treatment_Plant_No._2_GST_No._1_Construction_Updated_-_Exhibit_A_-_Scope_of_Work.pdf PDF
ITB_ENG250425_Water_Treatment_Plant_No._2_GST_No._1_Construction_Updated_-_Exhibit_E_-_Executed_Grant.pdf PDF
ITB_ENG250425_Water_Treatment_Plant_No._2_GST_No._1_Construction_Updated_-_Exhibit_B_Plan_Set.pdf PDF
ITB_ENG250425_Water_Treatment_Plant_No._2_GST_No._1_Construction_Updated_-_Exhibit_D_-_Grant_Clauses.pdf PDF
ITB_ENG250425_Water_Treatment_Plant_No._2_GST_No._1_Construction_Updated_-_Exhibit_C_Electrical_Plan.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table 1

REV. 3.15.25 Exhibit F - PRICE PROPOSALCONTRACT# CIP/250425
Bidder nameBidder Location
ENTER COMPANY NAME HEREENTER OFFICE LOCATION HERE
ITB# ENG/250425 Water Treatment Plant No. 2 GST No. 1 Construction
ITEMDESCRIPTIONQUANTITYLUMP SUM COST
1GENERAL CONDITIONS AND REQUIREMENTS1LS$ -
2SITE WORK1LS$ -
3MECHANICAL SITE PIPING1LS$ -
43.0 MG FINISHED WATER GST #11LS$ -
53.0 MG FINISHED WATER GST #21LS$ -
*TOTAL BID AMOUNT$ -
* Enter TOTAL BID AMOUNT into Total Bid Amount Section on your electronic bid response.