This is a Price Proposal Exhibit B for ITB AIR/260692, submitted to the City of Ocala, Florida for the Runway 36 Runway Safety Area (RSA) Grading Project at Ocala International Airport (OCF). The project scope encompasses site preparation, demolition, earthwork, grading, and site restoration to bring the Runway 36 RSA into compliance with Federal Aviation Administration (FAA) design standards. Key line items include mobilization, construction layout and survey, contractor quality control programs, traffic management and runway closure markers, borrow excavation (3,632 cubic yards), unclassified excavation and topsoil stripping (2,088 cubic yards), gravel road removal and replacement (350 square yards), disconnection and removal of existing Medium Intensity Approach Lighting System with Runway Alignment Indicator Lights (MALSR) station, installation of new MALSR MG-20 support structure, reinstatement of existing MALSR approach light bar and T-brace assembly, topsoil placement (2,088 cubic yards), and sodding of disturbed areas (12,500 square yards). The proposal document is dated April 2026 and is formatted as a cost estimate worksheet with columns for item number, specification number, item description, quantity, unit of measurement, unit price, and total cost.
All line items in the price proposal are currently listed with zero dollar amounts for both unit prices and total costs, indicating this is a blank template awaiting contractor pricing submission. The proposal follows standard construction bidding format with separate sections for construction costs and total bid price. No information regarding contract award dates, contract terms, renewal options, specific response deadlines, or funding sources is provided in this exhibit. The document includes references to two images (image1.png and image2.jpg) which are not visible in the file content provided.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OCF-RSA GRADING-COST EST
| RUNWAY 36 RUNWAY SAFETY AREA GRADING |
| Exhibit B - Price Proposal |
| DATE: April 2026 | ||||||
| Item No. | Spec. No. | Item Description | Quantity | Unit | Unit Price | Total |
| CONSTRUCTION COSTS | |||||
| 1 | C-105-1 | MOBILIZATION | 1.00 | LS | $ - 0 |
| 2 | 02000 - 1 | CONSTRUCTION LAYOUT & SURVEY | 1.00 | LS | $ - 0 |
| 3 | C-100 | CONTRACTOR QUALITY CONTROL PROGRAM (CQCP) | 1.00 | LS | $ - 0 |
| 4 | 1530 - 1 | MOT, BARRICADES, SAFETY AND SECURITY AND LIGHTED RUNWAY CLOSURE MARKERS | 1.00 | LS | $ - 0 |
| 5 | 1720 | PROJECT RECORD DOCUMENTS | 1.00 | LS | $ - 0 |
| 6 | P-152-4.5 | BORROW EXCAVATION | 3,632.00 | CY | $ - 0 |
| 7 | P-152-4.1 | UNCLASSIFIED EXCAVATION (STRIPPING, STOCKPILING AND RE-USE AS TOPSOIL) | 2,088.00 | CY | $ - 0 |
| 8 | P-101-1 | GRAVEL ROAD REMOVAL, STOCKPILING AND REPLACEMENT | 350.00 | SY | $ - 0 |
| 9 | L-125-1 | DISCONNECT AND REMOVE EXISTING MALSR STATION COMPLETE(APPROACH LIGHT BAR, T-BRACE ASSEMBLY, LIR TUBE, SUPPORT STAND, CONCRETE FOUNDATION) | 1.00 | EA | $ - 0 |
| 10 | L-125-2 | INSTALL NEW MALSR STATION MG-20 SUPPORT STRUCTURE COMPLETE (CONCRETE FOUNDATION, NON-TILT SUPPORT STAND ASSEMBLY, LIR TUBE) | 1.00 | EA | $ - 0 |
| 11 | L-125-3 | REINSTALL EXISTING MALSR APPROACH LIGHT BAR & T-BRACE ASSEMBLY ON NEW MG-20 SUPPORT STRUCTURE | 1.00 | LS | $ - 0 |
| 12 | T-905-1 | TOPSOIL (REMOVED FROM STOCKPILE) | 2,088.00 | CY | $ - 0 |
| 13 | T-901 | SODDING | 12,500.00 | SY | $ - 0 |
| CONSTRUCTION TOTAL | $ - 0 | ||||
| TOTAL BID PRICE | $ - 0 |