ITB_32701-13862_-_Amendment_1_Questions_and_Comments_Final.pdf
PDF 187 KB Posted
- Attached to
- WTRBA Running Reelfoot Bayou - UPDATED
- Solicitation number
- Event 32701-13862
- Issued by
- Gibson County, Tennessee
About this file
This Amendment #1 document clarifies and updates the Invitation to Bid (ITB #32701-13862) issued by the Tennessee Department of Environment and Conservation and the West Tennessee River Basin Authority (WTRBA) for stream maintenance and restoration services at Running Reelfoot Bayou in Gibson County. The project encompasses floodplain bench excavation across four phases, equipment rental and operation (hydraulic excavators, amphibious excavators, and skid steer loaders), labor services, material installation (rip rap and warm-season grasses), and allowances for landowner impacts, drainage structures, third-party services, and construction contingencies. The ITB was issued on April 29, 2026, with a questions and comments deadline of May 6, 2026 at 10:00 a.m. Central Time and an ITB response deadline of May 29, 2026 at 2:00 p.m. Central Time. No pre-bid walkthrough is scheduled; site familiarization is the bidder's responsibility. The contract period extends 36 months to completion with no official phasing timetable for the floodplain portion, and the State retains discretion to exercise cost negotiations with respondents. Award will be made to the lowest responsive and responsible bidder.
The amendment addresses critical bidding clarifications including landowner impact allowance submission of $1,500 per unit for 300 units totaling $450,000, drainage structure allowance of $500,000, third-party allowance of $500,000, materials cost allowance of $200,000, and construction contingency of $500,000. No bid bond is required. Cut and fill volume adjustments will not result in lump sum payment modifications, though field adjustments may be made to balance the site and manage farmable slopes. Contractors bear responsibility for obtaining adjoining landowner contact information, though WTRBA will share preliminary outreach information. Excess excavated material must be managed through negotiated adjacent uses with landowners or by adjusting backslopes to balance material on-site. All drainage structure materials, including flapgates on outlet pipes, are compensated as line items with installation costs paid separately. Permits have not yet been issued; WTRBA is currently obtaining necessary authorizations. The specifications document has been replaced in its entirety with Version 2.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITB # 32701-13862 – Amendment # One Page 1 of 3
STATE OF TENNESSEE
ENVIRONMENT AND CONSERVATION
INVITATION TO BID # 32701-13862, RUNNING
REELFOOT BAYOU
AMENDMENT # ONE
FOR WTRBA RUNNING REELFOOT BAYOU
DATE: May 20, 2026
ITB # 32701-13862, RUNNING REELFOOT BAYOU IS AMENDED AS FOLLOWS:
1. This ITB Schedule of Events updates and confirms scheduled ITB dates. Any event, time, or date containing revised or new text is highlighted.
EVENT
TIME
(central time zone)
DATE
1. ITB Issued April 29, 2026
2. Questions and Comments Deadline 10:00 a.m. May 6, 2026
3. ITB Response Deadline 2:00 p.m. May 29, 2026
2. State responses to questions and comments in the table below amend and clarify this ITB.
Any restatement of ITB text in the Question/Comment column shall NOT be construed as a change in the actual wording of the ITB document.
RFP
SECTION
PAGE
QUESTION / COMMENT STATE RESPONSE
1. With respect to the cut and fill volumes in the revised plans for excavation, once clearing is complete-if the volumes differ from the plans will adjustments be made to the payment of the lump sum item?
No. There may be adjustments in the field to vary the farmable slope to help balance the site but no payment adjustments will be made.
2. Does the contractor have the full 36 months to complete the lump sum excavation item?
Yes. Consideration should be given to the landowner impact allowance that is intended for 1 year of impact and is not intended for repeatable payment on the same parcel when determining the phasing of construction
3. Will this project exercise the best and final offer option?
The State, at it’s sole discretion, may exercise cost negotiations with Respondents.
4. Will a list of the affected/adjoining land owners be provided or contractors responsibility to obtain contact information?
It will be the responsibility of the contractor to obtain this information.
WTRBA has obtained much of this information through preliminary outreach to local producers that can be shared.
5. I see the requirement for a payment and performance There is no requirement for a bid bond included in the terms and conditions.
ITB # 32701-13862 – Amendment # One Page 2 of 3
PAGE
QUESTION / COMMENT STATE RESPONSE
bond. Is a bid bond required for this project?
6. Is there a timetable on the floodplain portion of this contract?
The contract period of 36 months to completion is the only official timetable.
This is also referenced in question #2.
7. There is an import of material in the upstream right section.
Where will that shortage be located and where will the material come from on-site?
The most significant fill appears to be on the south side near Hwy 78.
Approximately STA 90+00 – 135+00.
The additional material for phase 4 should come from the overruns estimated for the other 3 phases.
Please note that cut/fill estimates are from Lidar and do not have any material shrink/swell factored in the estimate.
8. Can you tell me if there will be a pre-bid walk through for this project?
There is not a pre-bid walk through scheduled for this site.
9. In the Floodplain Bench plans is there a break point which divides the downstream left & right and the upstream left & right?
Please refer to the updated set of plans.
References on sheet C2.0 should be to phase 1-4. Any reference to left or right bank is not the appropriate construction set of plans.
Ph 1 – downstream Hwy 78 south bank
Ph 2 – downstream Hwy 78 north bank
Ph 3 – upstream Hwy 78 North/West bank
Ph 4 – upstream Hwy 78 South/East bank
10. There will be a net cy in dirt excavated, what are we to do with the extra?
This will be the responsibility of the contractor. Adjacent uses negotiated and permitted separately with landowner’s will be acceptable or the 15:1 back slope to the adjacent ag fields may be adjusted to balance the material on site.
11. There are two sets of plans one
Floodplain Bench & the other RRB Mid Bench but they appear to be the same plans.
Plans have been updated on the shared folder for clarification. Please refer to sheet C2.0. The excavated material table should have reference to phase 1
– 4 on the correct plan set. If you see a reference to left and right bank, you need to get the corrected plan set.
12. The Drainage Structure
Allowance states that it will pay for structures delivered and installed on-site. Then states installation of structures will be paid in other line items can you clarify.
The wording was intended to clarify that staged materials will not be paid for.
The structure must be “installed” at the time payment. The drainage structure allowance is solely for material costs.
The act of installing the structures will be paid for by appropriate other line items.
13. The Permanent Warm Season
Grasses allowance will pay contractor for seed & mulch.
Does this also pay for the placement of material?
Yes. The placement of the materials is also compensated under this line item.
14. Have permits been issued for this site?
No. WTRBA is currently working to obtain the necessary permits for this project.
ITB # 32701-13862 – Amendment # One Page 3 of 3
PAGE
QUESTION / COMMENT STATE RESPONSE
15. Flapgates are not shown on the riser pipe detail. Are they required?
Yes. They will be included on all outlet pipes. They will be purchased as part of the drainage structure material costs and installed by skilled laborer line item.
16. We cannot access the CAD files in the OneDrive link. Are these necessary to view before responding to the solicitation?
No. All documents necessary to respond to the solicitation are the documents included with the event and the PDF documents in the OneDrive link.
17. Do we need to enter the land owner impact dollar amount from the specs in the bid document?
This should be submitted as $1,500 for the 300 unit request to total the $450,000 allowance indicated in specifications estimate quantity table.
This is also further described in the specifications in section A-14 on page 18.
18. Do we need to enter the drainage structure allowance dollar amount from the specs in the bid document?
Yes. For line item 11, drainage structure allowance requesting a dollar amount be entered, this should match the specifications estimate quantity table of $500,000
19. Do we need to enter the third party allowance dollar amount from the specs in the bid document?
Yes. For line item 12, third party allowance requesting a dollar amount be entered, this should match the specifications estimate quantity table of $500,000
20. Do we need to enter the materials allowance dollar amount from the specs in the bid document?
Yes. For line item 17, material cost allowance requesting a dollar amount be entered, this should match the
$200,000
21. Do we need to enter the construction contingency dollar amount from the specs in the bid document?
Yes. For line item 13, construction contingency requesting a dollar amount be entered, this should match the
$500,000
3. Delete Specifications Document in its entirety and insert the following in its place (any sentence or paragraph containing revised or new text is highlighted):
32701-13862_Specifications_Version2
4. ITB Amendment Effective Date. The revisions set forth herein shall be effective upon release.
All other terms and conditions of this ITB not expressly amended herein shall remain in full force and effect.