Industry Day Slides - CM at Risk.pdf
PDF 286 KB Posted
- Attached to
- Industry Day for the Thayer Hall Demolition and Construction Project at West Point Academy
- Solicitation number
- Not on record
About this file
This document describes the Other Transactional Authority (OTA) and Construction Manager at Risk (CM@Risk) process for the demolition and construction of Thayer Hall at the U.S. Military Academy at West Point. OTA is a legal authority that allows the Department of War to enter into transactions outside standard Federal Acquisition Regulations (FAR), providing flexibility to adopt commercial industry standards and best practices. The construction authority is granted under 10 U.S.C. § 2808a and is currently limited to Department of War projects only. OTAs are awarded by Agreements Officers and may have Administrative Agreements Officers for construction administration support. Key advantages of CM@Risk with OTA include tailored administration frameworks, flexible risk allocation, project-specific incentives, and faster issue resolution compared to traditional FAR Integrated Design and Construction (IDaC) processes. However, the approach requires negotiation of administration frameworks and has fewer established precedents than FAR contracting.
The CM@Risk acquisition process for Thayer Hall consists of six steps: (1) full and open competition advertised publicly for at least 30 days on SAM.gov with submissions via PIEE; (2) Request for Qualifications requiring a qualifications narrative, constructability report and risk register, proposed organizational chart, and proof of bonding capability; (3) initial evaluation by the Agreements Officer with approximately three most-qualified firms invited to individual 60-minute pitch meetings followed by government panel questions; (4) evaluation by the USACE acquisition team considering proposals, pitch discussions, and other available information, with one firm selected for negotiations; (5) negotiation of agreement terms, pricing, and other considerations with fair and reasonable pricing required; and (6) award of Phase 1 (Pre-Construction Services) if negotiations succeed, with Phase 2 (Full Construction) to be awarded later and fixed-price demolition work potentially awarded simultaneously or separately. The project must comply with applicable laws including construction wage rates, OSHA requirements, environmental compliance, Miller Act payment and performance bonds, cybersecurity standards, fiscal law, and Brooks Act architect/engineer selection requirements. Feedback on the CM@Risk process is requested by August 17, 2026, directed to Brian Mannion at brian.t.mannion@usace.army.mil.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Other Transactional Authority (OTA) / Construction Manager at
Risk (CM@Risk) Process For the Demolition and Construction of Thayer Hall at West Point
Academy
What is Other Transaction Authority (OTA)?
• A legal authority to enter into transactions other than standard contracts, grants, or cooperative agreements. It provides the flexibility to adopt commercial industry standards and best practices.
• OTAs are not subject to the Federal Acquisition Regulations (FAR). This can attract non-traditional partners and encourages flexible, collaborative, and commercial arrangements.
• Primarily were used for research and prototyping, but new authority has expanded its use for construction.
o 10 U.S.C. § 2808a grants the authority to use OTA for facility construction and repair.
• Currently only authorized for Department of War (DoW) projects.
• OTAs are awarded by Agreements Officers (AOs).
o Can have Administrative Agreements Officers (AAOs) for Construction Admin support.
FAR vs. OTA Construction
Advantages
• Established clauses and remedies
• Extensive case law and precedent
• Familiar processes and training resources
• Defined dispute framework
Challenges
• Less flexibility
• Formal change processes
• Potentially slower adaptation
• Can become adversarial
Advantages
• Tailored administration framework
• Flexible risk allocation
• Project-specific incentives
• Potentially faster issue resolution
Challenges
• Must negotiate administration framework
• Fewer precedents
• Poor drafting creates administration risk
Neither approach eliminates construction administration problems. The difference is where the authority comes from and how the issue is resolved.
FAR OTA
• CM@Risk w/OTA allows for more flexibility than the traditional FAR IDaC Process and aligns more with the commercial sector o Ability for a streamlined and simplified selection process similar to
PDB w/OTA o Negotiated terms and conditions o Both FAR IDaC and CM@Risk OTA provide increased cost fidelity, identification of problems and risks earlier, and builder perspective on the appropriate building material and system selections.
• Only authorized for DoW Projects per 10 U.S.C. § 2808a restrictions!
CM@Risk w/OTA Overview
Laws applicable to OTAs
• Construction Wage Rates & applicable labor laws
• OSHA safety requirements
• Environmental compliance
(NEPA/UFC/installation standards)
• Miller Act Payment & Performance Bonds
• Cybersecurity / CMMC Level 1 requirements
• Fiscal law / Anti-Deficiency Act compliance
• Security, export control, DPAS priority rating
• Brooks Act / Selection of Architects &
Engineers
CM@Risk Process for the Thayer Hall Project
Step 1: Advertising
• Competition will be full and open
• The requirement will be solicited publicly for at least 30 days on
SAM.gov.
• Submissions will be made via the PIEE solicitation module.
Step 2: Request for Qualifications
• Interested firms will submit qualification statements to demonstrate their qualifications and understanding of the project.
• The district is considering the following proposal requirements:
• Qualifications Narrative
• Constructability Report & Risk Register
• Proposed Organizational Chart
• Proof of Bonding Capability
• Incomplete submissions may be disqualified from further consideration at the Agreements Officer’s discretion
Step 3: Initial Evaluation & Pitch Meetings
• The Agreements Officer will determine which firms demonstrate the highest potential in their qualifications statement.
• Approximately 3 of the most qualified firms will be invited to individual, confidential Pitch Meetings.
• Firms will have 60 minutes to deliver an oral presentation about why they are the best qualified firm to deliver the project.
• After 60 minutes, a panel of government reviewers will ask questions about the qualification statement, presentation, and the firm’s capabilities.
• The Pitch Meetings are intended to be conversational, rather than a strict Q&A session.
Step 4: Evaluation
• The USACE acquisition team, led by the Agreements Officer, will meet to discuss the advantages and disadvantages of each firm.
• The team may consider:
• The firm’s proposal
• Pitch meeting discussions
• Other information within the government’s possession
• Any other publicly available information about the firms
• Agreements Officer will select one qualified firm to proceed to negotiations.
• All other firms will be notified that they were not selected. However, non-selected firms may be asked to return for negotiations if the negotiations with the selected firm are unsuccessful.
Step 5: Negotiation
• USACE will provide a draft agreement to the selected firm.
• The parties will meet to negotiate and finalize the terms of the agreement.
• Negotiations may include the agreement articles, pricing, and other considerations.
• All elements of the price schedule must be fair and reasonable.
• If USACE and the selected offeror cannot reach consensus on the agreement, USACE reserves the right to discontinue negotiations and take any action determined to be in the government’s best interest, including entering negotiations with another firm, revising the acquisition approach, or canceling the solicitation.
Step 6: Agreement
• If negotiations are successful, the Agreements Officer will award Phase 1 of the agreement (Pre-Construction Services) to the awardee.
• The fixed-price demolition work may or may not be awarded simultaneously with the pre-construction activities.
• Phase 2 (Full Construction) will not be awarded at this time.
Feedback
• Please provide all feedback on the CM@Risk process for the Thayer Hall project by August 17, 2026.
• Please provide all feedback to Brian Mannion at brian.t.mannion@usace.army.mil
• We ask that you consolidate feedback into as few e-mails as possible mailto:brian.t.mannion@usace.army.mil
| Slide 1: Other Transactional Authority (OTA) / Construction Manager at Risk (CM@Risk) Process |
| Slide 2: What is Other Transaction Authority (OTA)? |
| Slide 3: FAR vs. OTA Construction |
| Slide 4: CM@Risk w/OTA Overview |
| Slide 5: Laws applicable to OTAs |
| Slide 6: CM@Risk Process for the Thayer Hall Project |
| Slide 7: Step 1: Advertising |
| Slide 8: Step 2: Request for Qualifications |
| Slide 9: Step 3: Initial Evaluation & Pitch Meetings |
| Slide 10: Step 4: Evaluation |
| Slide 11: Step 5: Negotiation |
| Slide 12: Step 6: Agreement |
| Slide 13: Feedback |