Demolition RFI.pdf
PDF 33 KB Posted
- Attached to
- Industry Day for the Thayer Hall Demolition and Construction Project at West Point Academy
- Solicitation number
- Not on record
About this file
This is a Request for Information (RFI) regarding pre-demolition site investigations and testing for a construction management project. The government is seeking input from the selected construction manager on what specific destructive and non-destructive testing and site investigations would be performed to minimize unknown risks and establish a guaranteed maximum price (GMP) for the demolition phase of the project. The RFI does not specify required products or services, but rather solicits the contractor's technical approach and methodology for de-risking the demolition scope. Responses are due by August 17, 2026.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The government has an additional RFI regarding the possibility of a guaranteed maximum price (GMP) for the demolition:
“As the selected construction manager for this project, what specific pre-demolition site investigations and testing—both destructive and non-destructive—would you like to perform to minimize unknown risks and better inform your guaranteed maximum price (GMP) for the demolition?”
Please provide your response by August 17, 2026.
Thank you for your interest in this project.