This document is a Clarification Letter issued by the City of Austin's Capital Delivery Department regarding the FM 812 Landfill Leachate Tank Connection project (IFB# CLMC1077, CIP ID 5698.017). The letter, dated April 30, 2026, provides answers to 27 bidder questions received during the solicitation process. The project encompasses connecting leachate storage Tank A to Tank B, connecting Tank B to an existing municipal manhole, and installing approximately 4,089 linear feet of 3-inch and 6-inch HDPE and PVC piping, along with new pumping and metering systems. Key clarifications address specifications for concrete structures, topsoil management, slope stabilization, erosion control, video inspection requirements for newly installed pipe, asphalt milling handling, and contractor responsibilities for loading and transporting owner-provided materials. The document confirms that no trees require protection along the force main alignment, internal drops are permitted as detailed on Sheet C-305, and the contractor is responsible for providing aggregate for buried pipe while the owner will designate a location for excess excavated material.

The clarification letter addresses several administrative and technical inquiries that establish the scope boundaries and contractor responsibilities. Notable responses indicate that the city does not have preferred electrical contractors, will not add separate pay items for seeding, erosion control, slope stabilization, native seeding, stabilized construction entrances, or silt fence (as these are addressed in standard specifications), and will coordinate the job shack location with the selected contractor after award. The document references multiple standard specifications and sheet details (including Sheets C-101 and C-305, and Sections 403, 510, 601S, 607S, 609S, 641S, and 642S) to guide contractor performance. Additionally, a clarification regarding bid submission timing addresses a scheduling conflict where May 2nd fell on a Saturday, with reference made to Addendum 8 for resolution.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

City of Austin

CAPITAL DELIVERY DEPARTMENT

Project Management Division

505 Barton Springs Road, Suite 900, Austin, TX 78704

Phone (512) 974-7221 Fax (512) 974-7222

April 30, 2026

PROJECT: FM 812 LANDFILL LEACHATE TANK CONNECTION

CIP ID: 5698.017

IFB# CLMC1077

SUBJECT: Answers to Bidders Questions as of the date of this letter, per 00100-IFB Article

1.(3)(C).

The following are answers to Bidders received on the above project. These answers do not modify the Contract. Any modifications to the Contract will be through Addenda

Q-1: Does this site have a preferred Electrical Contractor?

A-1: No.

Q-2: Can the Owner add Pay items for the seeding and erosion control as described under section

604S.10?

A-2: No, see SP604S.

Q-3: Can the Owner add Pay items for the slope stabilization as described under section 607S.6?

A-3: No, See SP607S.

Q-4: Will slope stabilization be required as described in section 607S.6?

A-4: See COA Standard Specification 607S and SP607S.

Q-5: Can the Owner add Pay items for the Native Seeding as described under section 609S.9?

A-5: No, see SP609S.

Q-6: Can the Owner add Pay items for the Stabilized Construction Entrance as described under section

641S.6?

A-6: No, see SP641S.

Q-7: Can the Owner add Pay items for the Silt fence as described under section 642S.6?

A-7: No, see SP642S.

Q-8: Would an internal drop be allowed at WWMH-237234?

A-8: See Detail 2 on Sheet C-305.

Q-9: Is the contractor replacing WWMH-237234 or just converting the existing manhole to a drop structure?

A-9: Convert the manhole as shown on the drawings.

Q-10: Is the Cast in Place Drop included in the Pre-Cast Drop Manhole?

A-10: Follow Detail 2 on Sheet C-305.

Q-11: Will topsoil stripping be required for aboveground piping?

A-11: Topsoil may remain in place.

Q-12: Can the owner provide a location where the millings and backfill material will be located?

A-12: See Sheet C-101.

Q-13: Will the owner consider extending the bid date 2 weeks?

A-13: Will consider and advise.

Q-14: Can the Owner provide locations for the CIP project signs and a quantity under the Lump Sum Pay

Item?

A-14: We don’t have any signs listed on the plans.

Q-15: Will the owner provide a waste site for excess excavated material?

A-15: The location for the existing soil stockpile is shown on Sheet C-101. The owner will provide a convenient location to the selected vendor for excess excavated material.

Q-16: Will video inspection be required for the newly installed pipe?

A-16: Yes, see 510.3(26)(d) Quality Testing for Installed Pipe. For the Dual-Contained HDPE Pipe follow Section SS15111 paragraph 3.05 Testing and Leakage.

Q-17: Will the onsite topsoil that is stripped meet the requirements under Section 601S?

A-17: Topsoil stripped may be reused onsite.

Q-18: Are there any trees to be protected under 610S Preservation of Trees? Is so can the owner provide a quantity?

A-18: There are no trees to be protected along the force main alignment.

Q-19: Will the owner provide a location for a field office, and will there be temp power, water and sewer nearby?

A-19: The location of the Job shack will be coordinated with the Owner. once the project is awarded. See

Section 01500 for temporary utilities.

Q-20: Please provide a detail and description and definition for Concrete for Structures. The specifications do not clearly identify the required class or mix design of concrete to be used for this scope. Kindly confirm the intended concrete class and any associated placement or finishing requirements.

A-20: See Section 403 for mix design. Table 7 indicates the class required for types of structure.

Q-21: Please clarify who is responsible for loading the Owner-provided millings and select backfill material for use on the project.

A-21: The Contractor is responsible for loading and transporting provided materials.

Q-22: Will the contractor be required to hydro mulch between the sleepers in the over waste sections?

A-22: Hydro mulch will be required on disturbed surfaces.

Q-23: Can you provide locations and depths for the Asphalt Milling where we are cutting through the existing road. Also, does the city want to keep the generated millings, and if so, where should we stockpile them??

A-23: Remove all HMAC in areas of excavation if required. Place excess removed HMAC on the existing Asphalt Millings Stockpile shown on Sheet C-101. Millings needed for fill material are available at the same location.

Q-24: Can you provide locations and details for the Concrete for Structures10 CY pay item?

A-24: See plans for locations of concrete to be installed on the project.

Q-25: Is the City providing all the aggregate for the buried pipe?

A-25: No, See item 510. Contractor to provide.

Q-26: Where is the closest hydrant to the project that the contractor can use for construction water?

A-26: Existing Hydrants are shown on the plans. Contractor to select the hydrant that he desires to use.

Q-27: Addendum 7 for the FM 812 Landfill Leachate Tank Connection #IFB 6100 CLMC1077 project, says bids have been changed from April 2nd to May 2nd but May 2nd is a Saturday. Would you please clarify?

A-27: See Addendum 8.

Christine Whitney

Austin Resource Recovery