About this file

This document contains an infection control construction permit for multiple buildings at a Department of Veterans Affairs facility. The permit details construction activities to correct deficiencies identified in Project 520-22-178. Work includes minor demolition and remodeling classified as Risk Group 2 or 3 depending on location. The related federal contract opportunity is a 100% Veteran-Owned Small Business set-aside solicitation to perform the required corrective work. The solicitation number is 36C25623R0012 and represents a reissue of a previous solicitation that received no offers. The work locations, requirements for infection control protocols, and responsibility assignments are clearly defined in the permit to ensure the project is completed safely and effectively.

View the file

Other files

File Type Posted
36C25623R0012 RFI Responses R1.docx DOCX document
Wall Guard Specs.pdf PDF
BL T-102 flooring common areas.pdf PDF
T-105.pdf PDF
Starc Catalog.pdf PDF
Canopy 3.pdf PDF
Access Drive for Rollup Door.pdf PDF
REVISED SOW 520-22-178 Correct FCA Deficiencies Multiple Bldgs 11.23.22.docx DOCX document
36C25623R0012 0001.pdf PDF
Canopy 1.pdf PDF
T-104 Rm 101-103-104-104A-104B-104C-C113-C111.pdf PDF
Canopy 2.pdf PDF
T-102 Renovations Floor Covering 4-12-22.pdf PDF
SOW 520-22-178 Correct FCA Deficiencies Multiple Bldgs R1.docx DOCX document
bldg 3 various room elevations and details- Laundry_Garbage Chutes.pdf PDF
36C25623R0012 EXHIBIT B.docx DOCX document
42 - 3-4 - Ground Floor Plan Area 2.pdf PDF
Exhibit 15 Walkways For Dock Access.pdf PDF
Brand Name JA-FCA-22-178_Signed 1_Redacted.pdf PDF
36C25623R0012 EXHIBIT C.docx DOCX document
Specs_05_16.pdf PDF
31 ACCESS DRIVE.pdf PDF
B30 - Dock LVT 8-22-22.pdf PDF
51 - 3-13 - Third Floor Plan Area 2.pdf PDF
T-105 ArchDiagram.pdf PDF
Exhibit 3 Chutes-VA HOSPITAL_Redacted.pdf PDF
T102 Floor Framing Layout.pdf PDF
36C25623R0012 EXHIBIT A.docx DOCX document
48 - 3-10 - Second Floor Plan Area 2.pdf PDF
VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors.pdf PDF
T-102 Fire Spklr Shop Drawing.pdf PDF
36C25623R0012 EXHIBIT D.docx DOCX document
T-102 STARC Systems.pdf PDF
VA Medical Ctr Bldg 3 2204284 IH Survey Report_PDF FINAL 04 19 2022 0934.pdf PDF
Handrails Details.pdf PDF
36C25623R0012 EXHIBIT E.docx DOCX document
T-102-FLOORING Issues_Updated.pdf PDF
96 - 3-58 - Toilet Room and Shower Elevations Soiled Linen and Trash Rooms.pdf PDF
WD MS20220050 Mod 3 dtd 10-7-2022.pdf PDF
36C25623R0012 Solicitation.pdf PDF
T-104 ArchDiagram.pdf PDF
30a - Wall Paint Details.pdf PDF
T-102 Blocking and TieDown Details.pdf PDF
Exhibit 30 - Automatic Scan Door Opener.pdf PDF
36C25623R0012 EXHIBIT F.docx DOCX document
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Infection Control Construction Permit Project Title: FCA Deficiencies Multiple Buildings Permit No:520-22-178

Location of Construction: Building 15, 3, 30,31, T-102,104,105 Project Start Date: TBD

Project Coordinator/COR: Paul Ezell Estimated Duration: 180 days

Contractor Performing Work: TBD Permit Expiration Date:TBD

Supervisor: Telephone: 228-523-4653

YES NO CONSTRUCTION ACTIVITY YES NO INFECTION CONTROL RISK

GROUP

TYPE A: Inspection, non-invasive activity * GROUP 1: Low Risk

TYPE B: Small scale, short duration, moderate to high levels * GROUP 2: Medium Risk

TYPE C: Activity generates moderate to high levels of dust, requires greater 1 work shift for completion

GROUP 3: Medium/High Risk

TYPE D: Major duration and construction activities

Requiring consecutive work shifts

GROUP 4: Highest Risk

CLASS I 1. Execute work by methods to minimize raising dust from construction operations.

2. Immediately replace any ceiling tile displaced for visual inspection.

3. Minor Demolition for Remodeling

CLASS II

*4/12/20/2

TSC

1. Provides active means to prevent air-borne dust from dispersing into atmosphere

2. Water mist work surfaces to control dust while cutting.

3. Seal unused doors with duct tape.

4. Block off and seal air vents.

5. Wipe surfaces with disinfectant.

6. Contain construction waste before transport in tightly covered containers.

7. Wet mop and/or vacuum with HEPA filtered vacuum before leaving work area.

8. Place dust mat at entrance and exit of work area.

9. Remove or isolate HVAC system in areas where work is being performed.

CLASS III

*4/12/2022

1. Obtain infection control permit before construction begins.

2. Isolate HVAC system in area where work is being done to prevent contamination of the duct system.

3. Complete all critical barriers or implement control cube method before construction begins.

6. Vacuum work with HEPA filtered vacuums.

7. Wet mop with disinfectant

8. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.

9. Contain construction waste before transport in

Date 4. Maintain negative air pressure within work site utilizing

HEPA equipped air filtration units.

5. Do not remove barriers from work area until complete project is thoroughly cleaned by Facilities Management

Service.

tightly covered containers.

10. Cover transport receptacles or carts. Tape covering.

11. Remove or isolate HVAC system in areas where work is being performed/

Initial

TSC

CLASS IV

1. Obtain infection control permit before construction begins.

2. Isolate HVAC system in area where work is being done to prevent contamination of duct system.

3. Complete all critical barriers or implement control cube method before construction begins.

4. Maintain negative air pressure within work site utilizing

HEPA equipped air filtration units.

5. Seal holes, pipes, conduits, and punctures appropriately.

6. Construct anteroom and require all personnel to pass through this room so they can be vacuumed using a HEPA vacuum cleaner before leaving work site or they can wear cloth or paper coveralls that are removed each time they leave the work site.

7. All personnel entering work site are required to wear shoe covers

8. Do not remove barriers from work area until completed project is thoroughly cleaned by the Environmental Service Dept.

9. Vacuum work area with HEPA filtered vacuums.

10. Wet mop with disinfectant.

11. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.

12. Contain construction waste before transport in tightly covered containers.

13. Cover transport receptacles or carts. Tape covering.

14. Remove or isolate HVAC system in areas where work is being performed.

Date

Initial

Construction taking place in negative pressure rooms where TB patients are housed or work with exhaust to these rooms? ___Yes /_✓_No

If yes, the contractor must provide written certification that all employees assigned to the work site have a negative TB screening within 90 days prior to assignment to work area.

Additional Requirements: Control dust while constructing Structure

*Depends on Location- Class II Bldg. 15,2,31, T102,T104,T105 Class III Bldg. 3,30

Infection Control: Tanya Chandler COR: Paul Ezell

Safety: Contracting Officer:

Adapted with permission V Kennedy, B Barnard, St Luke Episcopal Hospital, Houston TX, Forms modified and provided courtesy of Judene Bartley, ECSI Inc Beverly Hills MI 2002 Reviewed 2005