The Government has decided not to use the two step acquisition process. Any change to the answers previously posted have been marked with the original question number followed by an a .

View the file

Other files

File Type Posted
Amend0012.pdf PDF
SF30-Amend0005.pdf PDF
4_CostTemplate12Apr07Amendment0004.xls XLS spreadsheet
5_Amend0004SectionJAttachment11.doc DOC document
5_Amend0004FedBizOppsQandA.doc DOC document
6_Amend0004.doc DOC document
Amend0003FedBizOppsQ A.doc DOC document
Amendment0003.doc DOC document
Attachment8 CostTemplate.xls XLS spreadsheet
GovernmentResponsestoQuestionssubmittedontheAT21RFP_2.doc DOC document
Amendment0002.doc DOC document
Amendment002AT21_SV-6.pdf PDF
Amendment0002AT21_SV-6.xls XLS spreadsheet
QuestionsandAnswersPostedtoFedbizopps032007.doc DOC document
GovernmentResponsestoQuestionssubmittedontheAT21RFP.doc DOC document
Amendment0001.doc DOC document
AppendixGProblemReportForm.doc DOC document
Attachment10DeliverableSchedule.doc DOC document
Attachment2PPTemplate.doc DOC document
AppendixCDIDCPR-DI-MGMT-81466A.pdf PDF
MemorandumforProspectiveOfferors.pdf PDF
Attachment4PPQuestionnaire.doc DOC document
Attachment3PPLog.doc DOC document
AT21RequestforProposal.doc DOC document
AppendixFDICMAN80639CECP.pdf PDF
Attachment6NDABiddersLibrary.doc DOC document
Attachment8CostTemplate4Mar07.xls XLS spreadsheet
Attachment5DD254.doc DOC document
AppendixHAT21-CDD-Revised-21Feb07forPublicRelease.pdf PDF
AppendixEDIDIMS-DI-MGMT-81650.pdf PDF
Attachment9PerformancePlan.doc DOC document
AppendixDDIDCWBS-DI-MGMT-81334A.pdf PDF
Attachment7BiddersDemonstration.doc DOC document
NewReleaseDateforAT21RFP.doc DOC document
QuestionsandAnswersPostedtoFedbizopps020707.doc DOC document
QuestionsandAnswersPostedtoFedbizopps020607.doc DOC document
QuestionsandAnswersPostedtoFedbizopps013107.doc DOC document
CopyofAT21_SV-6.xls XLS spreadsheet
QuestionsandAnswersPostedtoFedbizopps011707.doc DOC document
QuestionsandAnswersPostedtoFedbizopps122006.doc DOC document
QuestionsandAnswersPostedtoFedbizopps121506.doc DOC document
1_IndustryDayAttendeesByCompanyName.xls XLS spreadsheet
IndustryDayAttendeesByCompanyName.xls XLS spreadsheet
AT21IndustryDaySlideShow31Oct2006.ppt PPT presentation
A21AwardFeePlan25Oct.pdf PDF
QuestionandAnswersfrom27Oct2006.doc DOC document
DraftRFP10192006.pdf PDF
AT21CDDforRFP19Oct06.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Government Responses to Questions submitted on the AT21 draft RFP December 15, 2006 modified.

The following questions have been modified from their original posting.

34a. What is the Government looking for in the Phase I (10 Page) Technical Summary?

Government Response: The Government has decided not to use the two-step acquisition approach; therefore, there is no longer a requirement for a 10 Page Technical Summary. See final RFP, Section L for requirements.

35a. Would exhibits be included in the 10 page limit?

Government Response: The Government has decided not to use the two-step acquisition approach; therefore, there is no longer a requirement for a 10 Page Technical Summary. See final RFP, Section L for requirements.

36a. Are teams locked in place after receiving the Phase I go/no go decision?

Government Response: The Government has decided not to use the two-step acquisition approach.

88a. Will the contractor’s be given the demonstration scenario in advance?

Government Response: The initial scenario will be provided with the final RFP release. There is also a potential that a scenario update, with additional data, will be given to the contractors the day of the demonstration.

93a. Do we have just 28 days from the time the scenario comes out to build the demo package?

Government Response: No. The initial scenario will be provided with the final RFP release. The 28 days is from the competitive range determination.