FINAL SUBMITTAL - SPECIFICATIONS
1415 Western Ave, Suite 418 | Seattle, WA 98101-2051 | Ph 206 682 2857 ECH Architecture | www.ech-ps.com |
United States Coast Guard Civil Engineering Unit Juneau
Building 54 Renovation Base Kodiak Kodiak, Alaska
Project # 33Q5154 November 22, 2013
Table of Contents
1415 Western Ave, Suite 418 | Seattle, WA 98101-2051 | Ph 206 682 2857 ECH Architecture | www.ech-ps.com | 1
DIVISION 0 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 07 Certification/Seals
DIVISION 1 – GENERAL REQUIREMENTS
01 01 00 Standard Requirements 01 01 20 Special Conditions & Submittals 01 15 00 Health & Safety Requirements 01 31 20 Progress & Payment Schedules 01 40 10 Contractors Quality Control 01 56 00 Environmental Controls 01 57 00 Abatement Demolition & Removal 01 70 00 Closeout 01 78 10 O & M Data 01 78 20 Warranty
DIVISION 3 – CONCRETE
03 30 53 Miscellaneous CIP Concrete
DIVISION 5 – METALS
05 50 00 Miscellaneous Metals 05 52 00 Metal Railings and Stairs
DIVISION 6 – WOOD & PLASTICS
06 10 00 Rough Carpentry 06 20 00 Finish Carpentry 06 41 00 Architectural Casework 06 60 00 Plastic Fabrications
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
07 18 13 Pedestrian Traffic Coatings 07 21 13 Board and Block Insulation 07 21 16 Mineral Fiber Blanket Insulation 07 21 23 Loose Fill Thermal Insulation 07 25 00 Weather Barriers 07 30 00 Steep Slope Roofing 07 46 46 Fiber Cement Siding 07 60 00 Flashing and Sheet Metal 07 92 00 Joint Sealants
DIVISION 8 – OPENINGS
08 11 13 Steel Doors and Frames 08 14 00 Wood Doors 08 22 20 Fiberglass Reinforced Plastic Doors 08 33 13 Metal Rolling Counter Doors 08 53 13 Vinyl Windows 08 71 00 Door Hardware
1415 Western Ave, Suite 418 | Seattle, WA 98101-2051 | Ph 206 682 2857 ECH Architecture | www.ech-ps.com | 2
DIVISION 9 – FINISHES
09 29 00 Gypsum Board 09 51 00 Acoustical Ceilings 09 65 00 Resilient Flooring 09 68 00 Carpet Tile 09 72 00 Wallcoverings 09 77 00 Fiberglass Reinforced Plastic Panels 09 90 00 Paints and Coatings
DIVISION 10 – SPECIALTIES
10 1400.20 Interior Signage 10 1401 Exterior Signage 10 21 13 Toilet Compartments 10 28 13 Toilet Room Accessories 10 44 16 Fire Extinguishers
DIVISION 11 – EQUIPMENT
113113 Electric Kitchen Equipment
DIVISION 21 – FIRE SUPPRESSION
21 13 00 Fire Suppression Sprinkler Systems
DIVISION 22 - PLUMBING
22 00 00 Plumbing, General Purpose 22 05 48.00 20 Mechanical Sound, Vibration, And Seismic Control
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
23 00 00 Air Supply, Distribution, Ventilation, and Exhaust Systems 23 03 00.00 20 Basic Mechanical Materials and Methods 23 05 93 Testing, Adjusting, and Balancing for HVAC 23 07 00 Thermal Insulation for Mechanical Systems 23 08 00.00 10 Commissioning of HVAC Systems 23 09 53.00 20 Direct Digital Control System 23 21 13.00 20 Low Temperature Water [LTW] Heating System 23 22 26.00 20 Steam System And Terminal Units 23 25 00 Chemical Treatment Of Water For Mechanical Systems 23 82 00.00 20 Terminal Heating Units
DIVISION 26 – ELECTRICAL
26 00 20 Basic Electrical Materials and Methods 26 20 00 Interior Distribution System 26 51 00 Interior Lighting
DIVISION 27 – COMMUNICATIONS
27 05 14.00 10 Cable Television Premises Distribution System 27 10 00 Building Telecommunications Cabling System
DIVISION 28 – ELECTRICAL SAFETY AND SECURITY
28 31 74 Interior Fire Detection and Alarm System
Project No. 33Q5154 00 01 07-1 Certification/Seals
SECTION 00 01 07
CERTIFICATION/SEALS
The undersigned hereby certifies that portions of the Division 5 and Division 6 Technical Specifications and the Division 7 - Division 11 Technical Specifications in this Project Manual were prepared by me or under my direct supervision, and that I am duly registered under the laws of the State of Alaska and hereby affix my “Professional Seal.”
ECH Architecture, P.S.
Michael J. Heidenreich, AIA
WilliamA Mike H Alaska Stamp Signed
Date 131122
Project No. 33Q5154 00 01 07-2 Certification/Seals
The undersigned hereby certifies that the Division 3 Technical Specifications and portions of the Division 5 and Division 6 Technical Specifications in this Project Manual were prepared by me or under my direct supervision, and that I am duly registered under the laws of the State of Alaska and hereby affix my “Professional Seal.”
Appia Consulting Engineers Niranjan Paranjpye, PE
Nick P's Alaska Stamp
Project No. 33Q5154 00 01 07-4 Certification/Seals
The undersigned hereby certifies that the Division 26 and Division 27 Technical Specifications in this Project Manual were prepared by me or under my direct supervision, and that I am duly registered under the laws of the State of Alaska and hereby affix my “Professional Seal.”
Elcon Associates, Inc.
Dean Ralphs, PE
11/22/2013
Project No. 33Q5154 00 01 07-5 Certification/Seals
The undersigned hereby certifies that the Division 21 and Division 28 Technical Specifications in this Project Manual were prepared by me or under my direct supervision, and that I am duly registered under the laws of the State of Washington and hereby affix my “Professional Seal.”
Aegis Engineering, PLLC
Travis Allen, PE
***END OF SECTION***
PROJECT NO. 33Q5154 01 01 00-1 Standard Requirements
SECTION 01 01 00
STANDARD REQUIREMENTS
1.0 SCOPE OF WORK
1.0.1 The work consists of construction activities on USCG facilities, as described in the drawings and specifications.
Work shall be executed in strict accordance with the best practice of the trades in a thorough, substantial, workman like manner by competent workmen.
The Contractor shall provide a competent, experienced, full time Superintendent who is acceptable to the Government, and who is authorized to make decisions on behalf of the Contractor, and who shall be constantly in charge of the work.
Work includes safety and environmental protection provisions as described.
Work includes all documentation, as-builts (including record surveys as may be required by Alaska licensed professional surveyor), final inspection, training and warranty, as specified.
The final completion and acceptance of all work, will be established by a written notice of acceptance issued by the Contracting Officer. No changes, deviations, or waivers shall be effective without a modification of the contract executed by the Contracting Officer (KO) authorizing such changes, deviations, or waivers.
1.0.2 Correspondence Identification: All correspondence and data submitted by the Contractor under this contract shall reference the Contract Number and Project Name.
1.0.3 Scope of Work: The contractor will provide for all labor, material, supplies, transportation, supervision and all other necessary items for a complete and usable project, performing all work in a workman like manner in complete compliance with the contract.
Common trades which may be needed include: all construction trades and technical support personnel, including testing, surveying, and abatement, and any other trades common to the construction industry to include government work. The Contractor will be required to perform multi-discipline construction, repair and remodeling work using these trade workers.
1.0.3.1 Performance Based Statement of Work:
1.0.3.2 The Contractor will be required to typically perform construction from a the performance-based Statement of Work. The contractor is responsible for interpreting the performance based requirements from the specifications, plans and reference documents, including the “Kodiak Standard Specifications” to provide a complete and useable end product.
The Statement of Work and reference documents, including the “Kodiak Standard Specifications” may not provide complete instructions on how to perform the work, or detail/integrate all associated components of the work. The contractor shall apply their
PROJECT NO. 33Q5154 01 01 00-2 Standard Requirements experience and judgment in performing typical commercial construction practices to complete the work with limited additional Government guidance.
1.0.4 Where exact locations are not given for the positioning of equipment, devices, and work;
they shall be positioned to permit easy access for maintenance and for removal and replacement of component parts. The Contractor is responsible for the coordination and proper relation of the work with the existing surroundings.
1.0.5 Schedule work to minimize interference with the facilities’ normal operations. Before any of the work is initiated, the Contractor shall confer with the Contracting Officer (KO), or their authorized representative(s), typically at the Preconstruction Conference; and agree on: a sequence of work; means of access to premises and building; space for storage of materials and equipment; delivery of materials and use of approaches; use of corridors, stairways, and means of communications; and the extent of protective measures required for existing adjacent occupied areas.
1.0.6 The Contractor may be required to provide shop drawings, procedures, or plans certified by an appropriately registered State of Alaska Professional Engineer, or other Certificated Professionals employed or retained by the contractor. The requirement for a professional shall not be construed to imply that normal work requires professional engineering certification.
However, the possibility exists that technical specialties, unforeseen events or unexpected site conditions will require submittals or modifications to the completed designs that will require proof of licensing (i.e., an Engineer’s stamp). The Government anticipates less than five percent of the Contract work will require this type of certification. When such conditions do occur, the contractor shall provide proof for the discipline appropriate. Unless specified otherwise, certifications shall be Alaskan.
1.0.7 PARTNERING: The Government intends to encourage the formation of a cohesive partnership with the Contractor. This partnership will be structured to draw on the strengths of each organization to identify and achieve reciprocal goals. The objective is effective contract performance in achieving completion within budget, on schedule and in accordance with plans and specifications.
1.1 DEFINITIONS APPLICABLE TO TECHNICAL SPECIFICATIONS
The following words and abbreviations have the meaning defined in the Technical Portions of the WORK.
Furnish means to supply and deliver to the site, to unload and unpack ready for assembly, installation, testing, and start-up.
Indicated is a word used to direct the CONTRACTOR to information contained on the drawings or in the Specifications. Terms such as "shown," "noted," "scheduled," and "specified" also may be used to assist in locating information but no limitation of location is implied or intended.
PROJECT NO. 33Q5154 01 01 00-3 Standard Requirements
Install defines operations at the site including assembly, erection, placing, anchoring, applying, shaping to dimension, finishing, curing, protecting, and cleaning, ready for the USCG use.
Installer: a person or firm engaged by the CONTRACTOR or any subcontractor
Provide is defined as furnish and install, ready for the intended use.
KO – Contracting officer
COR – Contracting Officer’s Representative
CI – Government Construction Inspector
1.2 CONSTRUCTION PHASING & CONSTRAINTS
Standard constraints and phasing requirements to incorporate into the schedule and work activities are described below. Additional provisions may be specified in other sections of the contract.
1) Work Hours:
Housing/Barracks Areas:
Weekdays: Start no earlier than 0800. Complete no later than 1900.
Weekends and Holidays: Start no earlier than 0900. Complete no later than 1800.
Non- Housing Areas: Start no earlier than 0700. Complete no later than 1900.
Variations may be coordinated with/approved by the COR, including work to support outages.
2) Work which requires Government supervision or coordination shall not be performed on Federal Holidays or Sundays.
3) The on –site performance period includes; mobilization, to final clean up, punch list and demobilization.
4) All seeding activities shall be completed prior to 15 August. Reseed, fertilize, water, and protect disturbed areas as long as necessary to fully re-vegetate.
5) All asphalt paving shall be complete by 1 October.
6) Notifications; provide notifications as follows;
a. After hours work: 2 working days.
b. Mobilization/demobilization: 2 weeks.
PROJECT NO. 33Q5154 01 01 00-4 Standard Requirements
1.3 TEMPORARY SERVICES
The contractor may obtain utility services from existing USCG services at no cost to the contractor. The contractor shall provide hookups and disconnects, and coordinate with on-site USCG personnel.
Make all arrangements with the local utility providers and pay all fees, charges, and costs of any nature associated with establishing and installing temporary services which are not available via USCG systems.
Installation of temporary utility services shall at a minimum follow the local, state and federal codes governing the installation of the utility service being installed.
Water and sewer is available at the site. Connections to potable water shall have an isolation valve and reduced pressure principal backflow preventer. Fire hydrants shall not be used as a source without the permission of the COR.
Telephone Service: Telephone service is not owned by the USCG. Coordinate with the local telephone company for point of connection (POC) location for temporary telephone service, if required. Pay all installation fees and telephone usage charges directly to the telephone company to provide the service.
Electrical: Coordinate with the local Electrical company for point of connection (POC) location for temporary electrical service requirements beyond capabilities of existing USCG systems. Pay all installation fees and electrical usage charges directly to the electrical company to provide the service.
The Contractor shall provide all other temporary services, utilities, and equipment required, which are not provided by the Coast Guard. These include, but are not limited to: Clean up and disposal of trash and Portable or temporary toilet facilities: Maintain in a sanitary condition at all times. Establish the facilities in manner to minimize public viewing. COR/CI will approve location and installation.
1.4 OUTAGES AND PROTECTION
Before interrupting utility service, make a written request for the interruption to the COR at least 10 work days before the anticipated interruption. Identify the utility, reason for interruption, proposed time of interruption, and duration of interruption. Do not interrupt utilities until authorized. Permission and duration for outages will be granted by the COR based upon the need for the utility, and upon consideration of suitable bypasses, or alternate arrangements. Outages will be granted at the convenience of the Government.
Protection: The Contractor shall safeguard and protect from damage all utilities encountered or uncovered during digging, excavation, and backfilling.
Hand Digging: All excavations with the potential for damaging existing utilities using machine excavation shall be done by hand digging. Complete all excavations within 2 feet of existing
PROJECT NO. 33Q5154 01 01 00-5 Standard Requirements utilities by hand rather than machine methods, or expose piping or cables by hand digging prior to completing excavation by machine.
Contractor shall restore damaged piping, cable(s), and circuits to original condition and full operation if damage occurs through his failure to fully process the digging permit or comply with its instructions, or to obtain utility locations from private utilities. Notification of damage shall be made immediately to the affected utility, to the USCG representative as listed on the digging permit, and to the COR/CI; restoration efforts shall commence within 1 hour. Failure to commence restoration within the required time limit, or to make continuous progress toward restoration, or to complete acceptable restoration within a 4-hour time limit or an alternate time limit negotiated with and established by the COR/CI, shall result in suspension of all other contract work until acceptable restoration is completed and approved by the COR.
All work to repair damage to commercial utilities shall be coordinated through the utility.
In cases where a utility is damaged for reasons noted above, the Contractor shall, if lacking the qualified trades in his organization, employ as necessary such qualified trades or employ another Contractor having such trades to restore the utility to its original condition and full operation at no expense to the Government.
The Government reserves the right to protect damaged communications cables from further damage or deterioration and the right to restore priority circuits; these actions shall not relieve the Contractor of his full responsibility for restoration. Outages: Submit and coordinate outage requests for each outage.
1.4.1 Outages:
Steam outages will be allowed. It is the contractor’s responsibility to perform and schedule the work in a manner that limits the number of outages. Base operating personnel will turn off and reestablish the steam supply for each outage.
Temporary Steam Supply: The contractor shall maintain a temporary steam supply to the affected portions of the system, and buildings while performing the work. Provide a temporary steam pipe supplying steam with a minimum diameter as approved by the
COR.
Temporary Condensate Return: Main Condensate shall not be wasted. Provide temporary condensate return, to ensure condensate returns to the central steam plant as coordinated with the COR.
Submit a steam outage plan that describes outage scheme, technical details of the outage such as installation of temporary lines and the location for condensate return/wasting.
Steam Supply to Two or More Buildings
Steam outages between 4 and 16 hours in duration will commence at 11:00 p.m. and be completed by 3:00 p.m. the following day. The outages will be limited to one every two weeks throughout the performance of the work. The steam supply will be re-
PROJECT NO. 33Q5154 01 01 00-6 Standard Requirements established by base operating personnel no later than 3:00 p.m. the following day and full steam pressure restored by 6:00 p.m.
Steam outages of less than 4 hours in duration will commence at 11:00 p.m. and be completed by 3:00 a.m. the following day. The outages shall be allowed once per week throughout the performance of the work.
Utility Outages: Outages on nights and weekends when facilities are not in use may be approved by the COR. Other outages shall not exceed the following in any 24-hour period:
Steam, Water, Electric, Storm Sewer, and Sanitary Sewer: Four hours is the maximum down time, without specific advance written permission.
1.5 UNDERGROUND UTILITIES
Submit digging requests per Base Kodiak procedures on the form provided, 10 working days in advance, and coordinate utility locates with other servicing utilities.
Mark the excavation route and intersecting utilities and parallel utilities within 10 feet of trench sides.
Where excavation will cross an existing utility line, use hand tools to excavate for a distance of 5 feet on each side of the intersections.
Once exposed, protect underground utilities from damage. Insure there is a dedicated spotter for each excavation during all excavation with power assisted excavating tools the spotter must be dedicated to watching the excavation and may not have any other supplemental duties during excavation activities. Ensure that new utility lines are complete, except for the connection, before interrupting existing
1.6 WEATHER
Delays caused by unusually severe weather (FAR Clause 52.249-10). Unusually severe weather will be considered unforeseeable and unusually severe if it is more severe than the statistical 3-year average for the appropriate weather parameters established by the National Weather Service.
Should warnings of severe weather be issued, the Contractor shall take every practical precaution to minimize danger to persons, the work, and to adjacent property. Precautions shall include, but not limited to, closing all openings, removing all loose material, tools and equipment from exposed locations, and removing or securing scaffolding and other temporary work.
If any part of this project is pursued during periods of cold or inclement weather, the Contractor shall take all appropriate precautions to protect facilities and work involved in the project scope from damage by cold/or inclement weather. The Contractor shall be responsible for snow removal around project site, parking areas, and thoroughfares.
PROJECT NO. 33Q5154 01 01 00-7 Standard Requirements
Working conditions for this work are based on typical weather information in Kodiak (PROVIDED FOR INFORMATIONAL PURPOSES ONLY) as follows; the contractor shall verify actual conditions based on established databases (National Weather Service) :
Prevailing wind: northwest at 8 knots. Maximum wind: 101 knots.
Maximum temperature: 86 degrees F.
Minimum temperature: -12 degrees F.
January average mean temperature: 30.8 degrees F.
July average mean temperature: 54.2 degrees F.
Average annual precipitation: 54.42 inches.
Maximum annual precipitation: 91.1 inches.
60 minute duration rainfall rate: 0.7 inch/hr.
Design roof snow load: 40 psf.
Freeze Data: Frost protection burial depth, 4 ft.
1.7 RECEIPT OF MATERIALS
Shipments of equipment, materials, and supplies shall be addressed to the contractor - not the Government. The contractor must be on hand to accept shipments; the Government will not accept shipments.
1.8 DELIVERY, STORAGE, AND HANDLING OF MATERIALS
No on-Base storage facilities are available to the contractor. Deliver, store, and handle products and materials within the contractor’s laydown area and according to the manufacturer's printed instructions and as follows:
Deliver products and materials in manufacturer's original unopened packages or containers bearing manufacturer's labels.
Store products subject to damage from the elements in weather tight enclosures; maintain temperature and humidity within the ranges stated in the manufacturer's printed instructions.
Store fabricated products off the ground on platforms, blocking, or skids.
Cover or protect products that may discolor or deteriorate due to exposure to the elements.
Provide ventilation to avoid condensation.
Store loose granulated material on solid surfaces such as paving, plywood, or sheet material to prevent mixing with foreign matter. Provide drainage to prevent sheet material to prevent mixing with foreign matter. Provide drainage to prevent flow or ponding of rainwater. Prevent mixing of materials.
PROJECT NO. 33Q5154 01 01 00-8 Standard Requirements
1.9 PUBLIC CONVEYANCES
The CONTRACTOR shall make its own investigation of the condition of available public and private roads and of clearances, restrictions, bridge load limits, and other limitations affecting transportation and ingress and egress to the site of the WORK. It shall be the CONTRACTOR's responsibility to construct and maintain any haul roads required for its construction operations.
1.10 CLEANING
The CONTRACTOR shall provide complete cleaning services of completed work and work area, including re-grading any disturbed unpaved laydown areas.
The contractor shall provide cleaning services after final inspection, immediately prior to government acceptance.
1.11 INTERRUPTION OF TRAFFIC
If during the performance of work it becomes necessary to modify vehicular traffic patterns, notify the COR at least 10 days prior to the proposed interruption date, and submit a detailed Traffic and Fencing Plan as a preconstruction submittal.
1.11.1 Road Closures
Submit a detailed Traffic and Fencing Plan as a preconstruction submittal. The contractor’s plan shall show, but not limited to, traffic flow pattern, location of warning signs, flaggers, barricades, etc. This project will affect traffic in areas which are distant from the actual construction site.
The contractor shall evaluate, as part of the road closure plan, area-wide traffic flow as it is affected by construction activities. Continuous pedestrian and vehicle access is required to all facilities, from at least one path of access. The Contractor needs to sequence their work to maintain access and continuity of operations.
a. Closure of more than one road at a time shall not be allowed.
b. No long term stockpiling of excavated material or debris shall be allowed in the work area.
c. For road closures, or traffic modifications; submit an “outage request” ten days in advance.
d. For any one-way temporary traffic, provide a flagger(s) from 0800 to 1630 Monday through Friday.
e. Sign roads in the project area to indicate road closures and alternative routes. Post signs to indicate pending road closures 3 days prior to the actual closure. Install signs upstream of closure to warn traffic in advance of closed section. Coordinate all signage requirements with the COR.
PROJECT NO. 33Q5154 01 01 00-9 Standard Requirements
f. Temporary barriers shall be erected to delineate a corridor through which tenant vehicles and equipment can pass, and temporary fencing shall be installed to control normal pedestrian pathways.
g. The contractor shall erect a temporary barrier(s) to demark their work area(s). Where necessary, the barriers should be supplemented with traffic control and informational signs.
h. Provide fence barriers to prevent unauthorized entry in excavation areas, where heavy equipment operates or is parked, demolition areas, and to protect existing facilities and adjacent properties from damage from construction operations. Construct and maintain barricades as required by OSHA sufficient to prevent injury to persons and damage to property.
i. Provide barricades around trenches and holes to prevent access. Special precautions shall be taken to prevent accidental use of residential doorways abutting the work to safe guard residents and their pets.
j. Provide and maintain warning lights and signs as necessary to prevent damage or injury.
Keep warning lights burning from dusk to dawn. Traffic Control devices shall be in constructed and installed in accordance with the Alaska Traffic Manual.
k. Install Asbestos Abatement barriers and signage for asbestos abatement work.
1.12 WARNING SIGNS
Provide warning signs at the limits of construction stating that access is restricted to authorized personnel and hard hats are required. Also provide warning signs to warn pedestrians and drivers to potentially dangerous areas.
1.13 BARRIERS AND TRENCH PLATES
Provide temporary barriers with warning lights where construction work intersects existing roads, walkways, at open excavations, and where pedestrian and driver safety may be endangered in the area of work. Provide barriers and warning signs to re-route pedestrians and drivers around potentially dangerous areas. Barriers shall be manufacturer's standard A-frame, barrel, or Jersey style with flashing amber lights and reflective orange/white striping on both sides of the barrier. Minimum barrier height shall be 42". Monitor barricades for wind/weather conditions, and restore promptly.
Provide trench plates for excavations in roads left open overnight on Coast Guard property.
1.14 QUARTERS
No Government quarters are available for use under this contract.
PROJECT NO. 33Q5154 01 01 00-10 Standard Requirements
1.15 SALVAGE
All existing materials which are to be removed, and are not indicated or specified for reuse in the new work, shall, unless otherwise specified, become the property of the contractor, be removed from government property at the Contractor’s expense, and be disposed of in accordance with Federal, State and local regulations. Remove all salvage from government property.
Excess clean soils excavated from the work site, and NOT reused in the construction may be disposed on USCG property. Coordinate requirements and location of disposal site with COR.
Excess clean concrete materials (with protruding rebar and other devices removed) may be disposed on USCG property, on Nymans Peninsula. Coordinate requirements and location of disposal site with COR.
1.16 EMERGENCY CONTACT
Maintain an after-working hours contact point, and provide the COR with a telephone number, so that the Government may contact the Contractor at any time in case of emergency.
Base Kodiak is a “911” response location. USCG typically provides first response under a mutual aide agreement, however, transportation and treatment are provided by community/commercial resources.
1.17 IDENTIFICATION OF EMPLOYEES AND EQUIPMENT
Prior to the commencement of work, submit to the COR a complete list of all employees, representatives, and subcontractors, including name, age, and address. Contact the COR regarding regulations concerning vehicle passes. Furnish a complete list of over-the-road vehicles and construction equipment to the COR. The list shall include the make, model, year built, and identifying marks.
Furnish similar lists to Base Military Police for obtaining contractor Base vehicle passes.
Become familiar with and obey station fire, traffic, and security regulations. Personnel shall not stray from the immediate area of work.
All personnel shall carry proper identification (ID) when on site. Proper ID is defined as either the individual's driver's license, or state federal picture ID or Passport. The identification must be laminated, and show a facial picture of the individual.
1.18 FIRE PREVENTION AND PROTECTION
Perform all work in a fire-safe manner. Provide and maintain adequate fire fighting equipment during the entire construction period.
Comply with local fire protection regulations and, where the regulations do not apply, comply with the standards of the National Fire Protection Association.
PROJECT NO. 33Q5154 01 01 00-11 Standard Requirements
Obtain hot work permits from the Base Fire Department. These permits are issued on a daily or weekly basis, depending on the work. Notify Fire Department 2 hours in advance.
For any hotwork performed within an existing or newly constructed structure, provide a dedicated independent fire watch, and maintain watch for 30 minutes after completion of hot work.
On site burning for disposal is not allowed.
Contractor Fire Prevention Responsibility
It is the inherent responsibility of the Contractor to practice good fire prevention measures while working on USCG property.
When work is accomplished in/on structures, contractor personnel will confine smoking to established/designated smoking area(s).
Flammable paints, oil, varnishes, etc., stored inside structures must be in a metal storage cabinet.
When stored outside, flammables must be in a controlled area. Flammables being used outside of these areas are limited to a one day supply.
Temporary wiring must be in compliance with Article 305 of the National Electric Code.
1.19 LAYDOWN AREA AND ADJACENT WORK
1.19.1 A contractor’s laydown area will be provided in the general vicinity of the construction site. The contractor shall erect temporary barriers to demark their work/storage areas. There should be no expectation of security for the contractor’s materials.
The adjacent areas, are working areas. Equipment/people move past the work area. Access to, and functions of the adjacent site shall remain operational during construction.
1.19.2 Material Stockpile and Laydown Area. The contractor’s laydown area shall be within the limits of construction. Additional laydown areas may be provided on Base. Coordinate location with COR.
There shall be no long term stock piling of excavated soils in the work area(s). Excess excavated soil shall be transported and stockpiled within an approved laydown area, with proper erosion control methods. Restore stockpile area(s) upon completion of the work. Excess or unsuitable materials not incorporated into the work, may be accepted by the government, or shall be disposed of by the contractor off Base.
Demolished asphalt, concrete and other debris shall be removed daily from the work area.
Demolished asphalt and concrete may be disposed on Base subject to government approval.
1.19.3 The contractor shall install security fencing around the work area(s) and laydown areas.
Fencing shall be substantial, to prevent pedestrian and vehicle access, and to denote areas of construction. Temporary barriers shall be erected to delineate a corridor around the construction areas, for temporary pedestrian passage, and temporary fencing shall be installed to control/divert normal pedestrian pathways. Where necessary, the barriers should be
PROJECT NO. 33Q5154 01 01 00-12 Standard Requirements supplemented with traffic control and informational signs. Fencing placed in existing paved areas (which are not replaced with the work) shall be surface mounted.
1.19.4 Contractor’s Parking Area: The Contractor shall limit parking to within the limits of fenced/barricaded construction work.
1.19.5 Maintain a tidy worksite. Proximity of the work to the Air Station and operating airfields makes this particularly important.
1.19.6 Disturbance to adjacent grass areas shall be restored, which may include cutting grass that has not been maintained due to contractor temporary work or other obstructions.
1.20 CONTRACT REQUIREMENTS
1.20.1 Reports
Daily: The Contractor shall submit daily reports to the COR and CI on forms provided by the Government. Daily reports shall be submitted by 10:00 am on the following work day.
Weekly: Weekly payroll reports required by Labor Standards Provisions, shall be submitted to the Contracting Officer.
1.20.2 Punch List
Submit after pre-final inspection, and final inspection. The Discrepancies and Omissions list (punch list) is not an all-inclusive listing of discrepancies which exist between the contract specifications and the work as performed up to the date of the list. It is also not a waiver of any other Government Claim. The Government at all times reserves all of its rights and remedies under the Contract.
1.20.3 Notices to COR and CI
Unless otherwise provided for herein, advise the COR and CI a minimum of 72 hours in advance of the following planned actions:
Commencement or recommencement of work at the site.
Shutdowns.
Requests for inspection.
1.20.4 Cost Proposals for Modifications: Itemize every cost proposal submitted as outlined in this paragraph. Costs allocable to material, labor, equipment, subcontractors, overhead, bonding, insurance and profit must be separately itemized for each distinct category or item of work encompassed. Include documentation such as invoices, quotes, vendor estimates, or other supporting cost figures. Clearly state in the proposal if an extension in the performance period is required. For proposals involving time extensions, include rationale for the extension and a proposed adjusted progress schedule.
1.20.5 Design Clarification Requests (DCR)
PROJECT NO. 33Q5154 01 01 00-13 Standard Requirements
In the event that the contractor, subcontractor, or supplier, at any tier, determines that some portion of the Government supplied; drawings, specifications, or other contract documents require clarification or interpretation by the Government; the contractor shall submit a DCR on form CM-06 in writing to the COR, with a copy to the CI. DCRs may only be submitted by the prime contractor. In the DCR, the contractor shall set forth their interpretation or understanding of the requirement, along with reasons why such an understanding has been reached.
The Government will review all DCRs to determine whether they are DCRs within the meaning of this term. If the Government determines that the document is not a DCR, or missing required information from the contractor, it will be returned to the contractor without review as to content, for resubmittal in the proper manner (e.g., submittal, request for variation, etc.).
Responses to DCRs will be issued within 14 work days of receipt of the request, unless the Government determines that a longer period of time is necessary to provide an adequate response. If a longer period of time is determined necessary by the Government, the Government will, within 14 days of receipt of the request, notify the contractor of the anticipated response time. The 14 days referred to herein will start on the date stamped received "in from the contractor" by the Government. If the contractor submits a DCR on an activity with 14 days or less of float on the current project schedule, the contractor shall not be entitled to any time extension due to the time it takes the Government to respond to the request, provided that the Government responds in the days set forth above.
Responses from the Government will not change any requirement of the contract documents unless so noted in the response to the DCR. If noted as a change, the Government will issue either a no-cost Field Adjustment or formal modification under the Changes clause. If the contractor believes that a response to a DCR will cause a change to the requirements of the contract documents, the contractor shall immediately give written notice to the Contracting Officer stating that the contractor considers the response to be a change. Failure to give such written notice immediately shall waive the contractor's right to seek additional time or cost under the Changes clause of the contract.
1.21 STANDARD SPECIFICATIONS AND CODES
In case of conflict between the referenced specifications or standards and this specification, this specification shall govern. When a number is suffixed to a referenced specification or standard, it denotes the effective amendment(s) or change to the document. Referenced specifications and standards are not available for distribution by the Coast Guard.
The work shall be performed in accordance with applicable provisions of the Law(s) and the latest publication and/or amendments of the following:
Williams-Steiger Occupational Safety and Health Act of 1970, Public Law 91-596, as amended in 1990.
By agreement between the US Department of Labor, Occupational Safety and Health Administration (OSHA) and State Department of Labor, Division of Occupational Safety
PROJECT NO. 33Q5154 01 01 00-14 Standard Requirements and Health (DOSH), applicable OSHA regulations as amended by the State of Alaska are enforced for Contractors and Contractor personnel only by DOSH. At no time will the level of protection afforded the worker be less than the strictest of either the Federal or State regulations.
Code of Federal Regulations, Title 29, Parts 1910 (Occupational Safety and Health Standards) and 1926 (Safety and Health Regulations for Construction).
Federal Standard 313B, as it pertains to the procurement, identification, marking and control of potentially toxic or hazardous materials, and to the reporting of information concerning these materials.
International Building and Mechanical Codes; Uniform Plumbing Codes
National Electric Code
NFPA 101, Life Safety Code
National Fire Protection Association Codes and Standards
Applicable portions of standards listed in the Specifications that are not in conflict with Contract Documents or with the Federal Acquisition Regulations (FAR).
Any and all USCG and local regulations as pertain to construction, safety, fire, health, and associated activities are hereby made part of this Specification.
Modifications or exceptions to standards shall be considered as amendments, and unmodified portions shall remain in full effect.
All site activities are to be conducted in accordance with applicable EPA and State regulations.
U.S. Army Corp of Engineer Safety and Health Requirements manual EM 385-1-1 03 Sep 96 shall be strictly adhered to.
Applicable Standard Specifications: Referenced Technical Sections, including Asphalt Concrete Pavement to Standard Specifications shall mean the Alaska Department of Transportation and Public Facilities "Standard Specifications for Highway Construction - 2004" and any supplements or amendments thereto.
Relevant AKDOT or AASHTO standards may be substituted upon approval by COR.
Notify the COR of any observed conflicts between the Contract Documents and governing code. COR will issue instructions as to procedures. If the Contractor performs any work knowing it to be contrary to governing code and without notice to the COR, they assume full responsibility.
1.22 CONSTRUCTION DOCUMENTS
The drawings and specifications will be supplied to the contractor in electronic format.
Publications incorporated into the technical provisions by reference will not be furnished.
PROJECT NO. 33Q5154 01 01 00-15 Standard Requirements
The Contractor shall check all drawings and specifications furnished, immediately upon their receipt, and shall promptly notify the Contracting Officer of any discrepancies (this shall include all sheets and pages that are part of the set of contract documents). Large scale drawings shall take precedence over small scale drawings. The Contractor shall compare all contract drawings, and verify the dimensions and conditions at the site before laying out the work.
1.22.1 Order of Precedence
Where specifications or standards documents are referenced in these Contract documents, they apply as if they were incorporated into the contract, except if specifically noted otherwise. If there are differences between referenced documents and any contract documents the following precedence applies. Additionally, see FAR 52.236-21 and notify the Contracting Officer of any discrepancies.
Contract
Specifications
Drawings
Base Kodiak Standard Specifications. These specifications are the default requirements for items to be included in the work, but not specified in the contract specifications.
References
Applicable code or standard governing the work in question
1.23 SAMPLING AND TESTING
Unless otherwise stated herein all required sampling and testing shall be by the Contractor at their own expense. All tests shall be performed using specified testing procedures, or if no procedure is specified, the standard testing procedure used by the ASTM will be used. The Contractor shall notify the COR/CI when such testing will be performed so that the test may be observed by the COR/CI and/or designated representatives. In addition to the specified testing requirements herein, the Government may perform additional verification testing at its own expense. All necessary samples and/or work associated with such samples for such testing shall be provided by the Contractor at no additional cost to the Government.
PROJECT NO. 33Q5154 01 01 20-1 Special Conditions and Submittals
SECTION 01 01 20
SPECIAL CONDITIONS and SUBMITTALS
1.1 PRECONSTRUCTION CONFERENCE
The preconstruction conference will be scheduled 1 week after receipt of the contractor’s preconstruction submittals.
The government will attempt to reply to the contractor’s preconstruction submittals in conjunction with the preconstruction conference. However, the government will be allowed up to 10 working days for response.
The preconstruction conference will be held on site in Kodiak. Required on-site attendance;
contractor’s superintendent and Quality Control Manager. Other attendees may participate telephonically.
Notice to proceed will be issued after completion of the preconstruction conference.
Note well: the performance period for this contract commences with Notice of Award, therefore the time period from notice of award, to completion of the preconstruction conference and notice to proceed is included in the overall performance period.
1.2 SUBMITTALS AND DATA REQUIREMENTS
1.2.1 Submit for approval plans, submittal data, operations and maintenance (O&M) data, reports and as-built drawings. Approval of the data shall not eliminate responsibility for compliance with the drawings or specifications unless deviations are requested and approved in writing.
1.2.2. A draft submittal log is attached to Section 014010. The contractor shall revise this draft log, submit as a preconstruction submittal, and manage submittals.
1.2.3 Where submittals are specified; submit the following:
1 Copy to the PM/COR/CI
1 Copies to the USCG’s AE firm (Technical Submittals only)
For Field Test Reports, certifications, inspection reports, Notices:
1 Copy to the PM
1 Copy to the On-site Government Rep.
Preconstruction Submittals, Submit prior to preconstruction conference, NLT 30 days after award, to PM/COR/CI.
PROJECT NO. 33Q5154 01 01 20-2 Special Conditions and Submittals
1.2.3 Review and Approval: Partial submittals will be rejected without review for resubmission as a complete package. Submittals may be approved, approved as noted, or disapproved. The government will require up to 10 working days to respond to submittals. For submittals requiring resubmission, the contractor shall resubmit within 10 working days of notice.
1.2.4 Trade names and catalog numbers of manufactured products indicate the type, size, and grade of quality of equipment and materials required. Such equipment and materials are approved for installation, subject to full compliance with the specifications. Except where single manufacturer is specified for standardization, requests for approval of other manufacturers than those specified must be accompanied by complete descriptions including overall dimensions, performance data, and, if catalog material, identification of specific products or items proposed.
1.2.5 Prior to the purchase of any materials or equipment, submit, for approval, data which completely describes all items intended for use in the work. Include the manufacturer, identifying number or nomenclature; the manufacturer's published data as to dimensions, capacity, power requirements; and such other information as necessary to properly describe each item. Catalog cuts fulfilling these requirements will be considered appropriate for this application. Clearly indicate the model, size, and/or features associated with each item. Markings that the Contractor or his supplier adds to printed materials shall be made in a color other than black.
1.2.6 Variations: Variations from contract requirements require Government approval pursuant to Contract Clause entitled "Specifications and Drawings for Construction" and will be considered where advantageous to the Government. Where variations are proposed for consideration, submit a written request, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to the Government. This includes, but is not limited to: catalog pricing data, samples of product variation, and complete credit or cost proposals. The proposed variation shall be identified separately and included along with the required submittal for the item.
1.2.7 Contractor's Responsibilities:
Determine and verify field measurements, materials, field construction criteria; review each submittal; and check and coordinate each submittal with requirements of the work and Contract documents, prior to submission. Ensure that submitted material is clearly legible. Advise the approving authority of variation, as required by the paragraph entitled "Variations."
Correct and resubmit submittal as directed by the approving authority. Direct specific attention, in writing or on resubmitted submittal, to revisions not requested by the approving authority on previous submissions.
Retain a copy of approved submittals at the project site, including the Contractor's copy of approved samples.
PROJECT NO. 33Q5154 01 01 20-3 Special Conditions and Submittals
Ensure no work is begun until the submittals for that work have been returned as "approved" or "approved as noted", or the work falls under an authorized partial submittal.
By approving and submitting shop drawings and samples, the Contractor thereby represents that he has determined and verified all field measurements, field construction criteria, materials, catalog numbers, and similar data, or will do so, and that he has checked and coordinated each shop drawing with the requirements of the Work and of the Contract Documents.
1.2.8 Approving Authority's Responsibilities:
Submittals will be reviewed for approval with reasonable promptness and only for conformance with project design concepts and compliance with the Contract documents.
Submittals will be returned with one of the following notations:
Submittals marked "approved" authorize the Contractor to proceed with the work.
Submittals marked "approved, see remarks below" (or similar comment) authorize the Contractor to proceed with the work as noted, provided the Contractor takes no exception to the remarks.
Submittals marked "disapproved" indicate the submittal does not comply with the requirements of the Contract documents and shall be resubmitted with appropriate changes.
1.2.9 Format
Transmittal Form: Use USCG provided form SHOP DRAWING/ MATERIAL APPROVAL REQUEST for all submittals. An electronic form is available. Alternately the contractor may complete the form by typewriter or ballpoint pen. Refer to the following instructions for proper completion and use of submittal form:
All information indicated on top of form shall be filled in. This includes contract number, date, contractor, signature and date of person completing form, submission number, and whether or not the submittal is new or a resubmittal.
The "SUBMISSION NUMBER" is a sequential number which increases with each new submission. There shall be only one (1) submission number per specification section submitted
on. In other words, although a specific submittal may involve 2, 3, or more forms; all the forms will have the same submission number.
When the submittal is a resubmission, the block titled "PREVIOUS SUBMISSION NR" shall be filled out. This is the number of the most previous submittal sent in for that particular specification section. A resubmission is required for all disapproved submittals and it shall be numbered sequentially with all other submittals (i.e.: it receives the next available number).
"ITEM NUMBER" is a sequential number which corresponds to the number of submittal items required under the "SUBMITTALS:" paragraph for a particular specification section. In other
PROJECT NO. 33Q5154 01 01 20-4 Special Conditions and Submittals words, if a specification…