HSCG85‐16‐R‐P45245

Question and Response Matrix 2

# Question Response 4 Attachment 1, Specification

Work Item 19, Paragraph 3.2

Para. 3.2 has the contractor renewing 109 hoses. Please provide the material type, size and length of ea. hose that is to be renewed. Please provide the material and type of fitting for ea.

hose that is to be renewed.

Table 1 ‐ Hose Particulars will be amended in Amendment 2 with updated information.

5 Attachment 1, Specification

Work Item 45, Paragraph 3.2

Para. 3.2 states that the cleaning and gas freeing of (6) healing tanks and (1) roll stabilization tanks are covered under a separate work item of this specification package. Please specify which work item these tanks are covered under.

Cleaning of the tanks in question will be added to Work Item 15 in Amendment

2. Marine chemist certification will be added as part of Work Item 45 in Amendment 2.

6 Attachment 1, Specification

Work Item 42, Paragraph 3.2

Para. 3.2 under General Information states the USCGC POLAR STAR is heavily loaded. With fuel (not to exceed 600,000 gallons).

The contractor shall off‐load Fuel as necessary to accommodate drydocking of the vessel at the contractor’s facility. Is it the intent of the USCG to have the KTR bid for the entire removal of the 600,000 gallons of fuel and any change in quantities of less than the stipulated amount be credited back to the USCG?

Contractor shall propose removal of fuel needed to successfully dry‐dock the cutter. The amount is dry‐dock specific.

7 Attachment 1, Specification

Work Item 31 Please provide the size, type and material of each of the (33) valves to be overhauled or replaced.

For WI 31, the fuel manifold drawings are: 400‐WAGB 5501‐6, Rev AD, ARRGT

OF DIESEL OIL TRANSFER PIPG, AND

400‐WAGB 5501‐7, Rev U, ARRGT OF

DIESEL OIL TRANSFER PIPG AFT FR 143

ABV TANK TOP. These drawings include the list of materials and sizes of all of the fuel manifolds. Work Item 31 will be updated to reflect these additions in Amendment 2.

RFP Reference

HSCG85‐16‐R‐P45245

Question and Response Matrix 2

8 Attachment 1, Specification

Please provide the following references. CG Tech Pub 3027, Section 551A; CG Dwg 400‐WAGB 1500‐3 Rev ‐ , Tank Level Indicator Sys; CG Dwg 400‐WAGB 3901‐1, CG Dwg 400‐WAGB 3901‐2

CG Tech Pub 3027 was misreferenced in the specification. The correct Tech Pub is 2037 and was already included in the references. CG Dwg 400‐WAGB‐ 1500‐3, Rev (‐) does not exist and will be removed from the specification.

Remaining drawings will be added to the reference section of the specification in Amendment 2.

Drawings will be provided by the Coast Guard to all vendors who have requested drawings and are approved for access.