CGC HEALY NOTIONAL SPECIFICATION (ATTACHMENT J.1) CORRECTIONS
D-1 Production control, Gantt Bar Chart Provide:
· Delete the text in Paragraph 3.4 and the associated table and replace with “Reserved” D-2 Tanks (Aviation Fuel Service) Clean and Inspect:
· 3.1 Replace “approximately XXX gallons” with “approximately 400 gallons” D-4 MDE Turbocharger Overhaul:
· 3.9.2 Remove Highlighting
D-6 MDE Camshaft Inspection:
· 3.1.2 Remove Highlighting
· 3.10.2 Remove Highlighting
D-7 MDE Main Bearing Inspection:
· 3.1.2 Remove highlighting and delete note “S/F…specified during the availability.”
· 3.9 Remove Highlighting
· 3.9.1 Remove Highlighting
· 3.10.2 Remove Highlighting
D-10 Pressure Gauges and Thermometers (Critical) Calibration:
· 3.2 Remove Highlighting and Delete “<<<CUTTER, VERIFY LIST PROVIDED IN THE FIGURE.>>>”
· Delete the Figure “List of Pressure and Thermometer Critical Gauges” and the associated highlighting
· Insert the attached Figure “List of Pressure Gauges and Thermometers” D-11 Pyrometers and Thermocouples (Critical Calibration):
· 3.2 Remove Highlighting and Delete <<<CUTTER, VERIFY LIST PROVIDED IN THE FIGURE. >>>
· Delete the Figure “List of Pyrometer and Thermocouple (Critical)” and the associated highlighting
· Insert the attached Figure “Pyrometer and Thermocouples List”
D-12 Flexible Hose Renewal:
· 3.1 Delete this paragraph and insert the following:
· 3.1 Provide and renew all the hose assemblies for miscellaneous machinery and crane systems provided in attached list in accordance with NAVSEA S6340-AE-TED-010, NSTM Chapters 505 and 556, and COMDTINST M9000.6.
· Delete the Figure “Flexible hose list <EXAMPLE:CUTTYHUNK LIST>”
· Insert the attached Figure “Flexible Hose Renewal List” D-25 Bow 3 Ton Crane Level 2 Inspect and Repair:
· 3.1 Delete the highlighted portion
D-26 04 Deck Cranes, and Port Miranda Davit Level 1 test and Inspect:
· 3.9.2 Remove highlighting and delete “ <<Ateam, verify washer renewal>>” D-29 Deck Coverings (Interior Polymeric) Renew:
· Replace Table 3.1.A with the attached Table 3.1.A
· 3.2 Delete Highlighted portion
· 3.4.2 Delete Highlighted Portion
· 3.4.3 Delete text and substitute “Reserved”
· Note: Page footers have incorrect Items Nos. from this point forward. Use D-Item title pages and paragraph numbering to keep subsequent pages in correct order.
D-30 Miscellaneous Lagging Repairs:
· 3 Delete Highlighted Portion
· 3.2.1 Remove highlighting and delete <<CUTTER/ATEAM, PROVIDE A NEW LIST SIMILAR TO THE ENCLOSED FIGURE.>>
· 3.4 Remove highlighting and Delete <<CUTTER/ATEAM PROVIDE A NEW LIST.>>
D-31 Temporary Services, Dockside, Home Pier:
· Delete the entire note below 3.1.4
· Delete Highlighted portion in the second note under 3.2.1.1
· Delete the figure captioned “ISC ALAMEDA CONTRACTOR POWER”
· Delete 3.5.1 text and substitute “Reserved”
· Delete the first sentence in 3.9.1
· Delete the highlighted portion below paragraph 3.9.1
HSCG85-09-R-6BX-020
Amendment 0003