Atch 11 - Section L Rev1.docx

DOCX document 76 KB Posted

Attached to
Missile Defense Data Center (MDDC) Program Federal contract opportunity
Solicitation number
HQ0147-10-R-0030
Issued by
DOD Missile Defense Agency

About this file

Section L paragraph L-1 is revised to add subparagraph L.1-4.

View the file

Other files for this federal contract opportunity

Other files attached to Missile Defense Data Center (MDDC) Program, newest first.
File Type Posted
MDDC Industry Day Questions and Answers.docx DOCX document
Exhibit A - CDRL DD Form 1423.doc DOC document
Atch 10 - PPSample SubContractor Consent Ltr.docx DOCX document
Atch 8 - PPQInfoSheet.docx DOCX document
Atch 12 - Section M.docx DOCX document
Contracting Officer Summary Letter_31Aug2011.doc DOC document
Exhibit C - MDDC BOE Summmary.xlsx XLSX spreadsheet
Exhibits B1 through B7.xlsx XLSX spreadsheet
Atch 13 - Compliance Matrix.xls XLS spreadsheet
Atch 4 - GFE List.xlsx XLSX spreadsheet
Atch 5 - OCI Policy Memo.pdf PDF
Exhibit A - CDRL DD Form 1423.doc DOC document
Atch 11 - Section L.docx DOCX document
Atch 6 - OCI Analysis-Disclosure Form.doc DOC document
Atch 7 - PastPerformanceQuestionnaire —
Atch 3 - Govt Labor Categories.docx DOCX document
Atch 9 - PPQCoverLtr.docx DOCX document
Atch 1 - Statement of Work —
MDDC Industry Day Attendees List.xlsx XLSX spreadsheet
MDDC Industry Day Brief 20110630 PAO approved.pptx PPTX presentation
MDDC Industry Day - Jackson Center Map.pdf PDF
HSV Accommodations.pdf PDF
MDDC Program VAR Process for Lab Tour.docx DOCX document
MDDC Lab Tour - VBIII Map.pdf PDF
MDDC Industry Day and Lab Tour Registration Form.xls XLS spreadsheet
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION L – Instructions, Conditions, and Notices to Offerors

Section L - Instructions, Conditions and Notices to Bidders

CLAUSES INCORPORATED BY REFERENCE

52.215-1
Instructions to Offerors--Competitive Acquisition
JAN 2004
52.215-1 Alt I
Instructions to Offerors--Competitive Acquisition (Jan 2004) - Alternate I
OCT 1997
52.215-16
Facilities Capital Cost of Money
JUN 2003
52.222-24
Preaward On-Site Equal Opportunity Compliance Evaluation
FEB 1999
52.237-1
Site Visit
APR 1984
52.237-10
Identification of Uncompensated Overtime
OCT 1997
252.227-7028
Technical Data or Computer Software Previously Delivered to the Government
JUN 1995

252.227-7017 Identification and Assertion of Use, Release, or Disclosure JAN 2011 Restrictions

CLAUSES INCORPORATED BY FULL TEXT

52.211-14 NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)

Any contract awarded as a result of this solicitation will be X DX rated order; DO rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation.

(End of provision)

52.215-20 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA OR INFORMATION OTHER THAN CERTIFIED COST OR PRICING DATA (OCT 2010)—ALTERNATE IV (OCT 2010)

(a) Submission of certified cost or pricing data is not required.

(b) Provide data described below:

Provide data and format prescribed in Section L of the solicitation.

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a single Indefinite Delivery/Indefinite Quantity (IDIQ) Cost Plus Incentive Fee (Term) contract with Travel and Material Cost Reimbursement CLINs resulting from this solicitation.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

MDA/DACT

Belinda Williams Bldg 5222 Martin Road Redstone Arsenal, AL 35898-0001

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://farsite.hill.af.mil

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any Defense Federal Acquisition Regulation Supplement (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

L-1 GENERAL INSTRUCTIONS TO OFFERORS

L-1.1 The Government intends to award a single Indefinite Delivery/Indefinite Quantity (IDIQ) contract resulting from this solicitation for the entire MDDC Program effort. The IDIQ contract will have a base Period of Performance (PoP) of five (5) years with five (5) one year options. Task Orders (TO) will be placed as funds and efforts are identified. TOs may be incrementally funded. The PoP for each additional TO will be determined at TO award.

L-1.2. The Government may award without discussions. Therefore, Offeror‘s initial proposal should contain the Offeror‘s best terms for management, technical, past performance, and cost/price.

L-1.3. NOTICE OF PRE-PROPOSAL CONFERENCE. A pre-proposal conference will be conducted at [TBD] on [TBD] at [TBD] for the purpose of answering questions regarding this solicitation.

Submit the names of all attendees (not to exceed 3) to Ms. Belinda Williams, 256-450-4041, Belinda.williams@mda.mil, with a courtesy copy to Ms. Emily McGee, 256-450-4010, Emily.mcgee@mda.mil, prior to [TBD]. This information must be provided in advance in order to ensure access to the conference site and adequate seating for the conference attendees.

Offerors are requested to submit questions to the point of contact noted above not later than [TBD]. Terms of the solicitation and specifications remain unchanged unless the solicitation is amended in writing. If an amendment is issued, normal procedures relating to the acknowledgment and receipt of solicitation amendments shall apply.

A record of the conference shall be made and furnished to all prospective offerors. The record will include minutes of the meeting, including questions (on a non-attribution basis) and answers.

L-1.4 NOTICE REGARDING ORGANIZATIONAL CONFLICT OF INTEREST (OCI) AGREEMENT(S) (Federal Acquisition Regulation [FAR] 9.5).

Responsibility lies with the prime contract Offerors to ensure that both it and its proposed subcontractors are not restricted from participating in this proposed acquisition due to an OCI clause in any Federal Government contract, including, but not limited to, MDA contracts.

Any Offeror who has signed, as well as proposed subcontractors who have signed, a contract with an OCI agreement as either a prime Contractor or subcontractor under any such contract, shall submit a written application to obtain approval to participate in this acquisition to the MDA Directorate of Contracting, Missile Defense Data Center (MDDC) Program, via e-mail to the PCO at Belinda.williams@mda.mil and alternate at Emily.mcgee@mda.mil .

Further, if either the prime Offeror (or any of its proposed subcontractors) is currently performing (or in process of proposing on) an effort that appears to have a potential conflict with the upcoming MDDC Program, regardless of whether there is an OCI clause or not, the prospective prime Contractor shall submit a written application to the MDA Directorate of Contracting, MDDC, via e-mail to the PCO at Belinda.williams@mda.mil and alternate at Emily.mcgee@mda.mil , to obtain approval to participate in this acquisition.

The Offeror(s) with either of the potential OCI restrictions, described in the paragraphs above, shall provide the following information electronically (either via e-mail or on a Compact Disc (CD)/Digital Video Disc (DVD) in Microsoft (MS) Word or Acrobat .pdf format):

(a) A copy of the OCI clause from either the prime contract or from the subcontract.

(b) A copy of each contract or subcontract Statement of Work (SOW).

(c) A copy of each Task Order (TO), Technical Directive (TD), Task Instruction (TI), or Task Assignment (TA) performed or being performed by the Offeror.

(d) The Government technical POC (including their current e-mail address, office symbol, and telephone number) for each contract or subcontract SOW, TO, TD, and/or TA submitted for review.

(e) If necessary, submit a MDDC OCI Risk Mitigation Plan to address both actual organizational conflicts and/or the appearance of an organizational conflict between current contracts or in-process source selections and performance of MDDC Program.

Each file on the e-mail/disc shall be identified by Contract Number, followed by SOW, TO, TD, TI and/or TA number if applicable. The e-mail/disc shall also include a file entitled, Table of Contents, which shall include contracts, TOs, TDs, and TAs with the name, current e-mail address, office symbol, and telephone number of the Government technical POC.

If an OCI package was originally submitted to Government and disposition provided by the Procuring Contracting Officer, the Offeror shall only include the list of proposed subcontractors along with the PCO OCI approval letters for itself and all proposed subcontractors. If the Offeror has not submitted all OCI packages for its proposed subcontractors, then a delta package shall be submitted along with the complete list of proposed subcontractors and any previously provided PCO OCI approval letters.

L-2 PROPOSAL CONTENT AND ORGANIZATION

L-2.1 The table below shall serve as the Offeror’s guide for proposal organization and content by volume, with associated due dates. Proposal volume pages shall be numbered.

Volume Title

Number of Hard Copies
Number of Electronic Copies *
Maximum Number of Pages **
Due Date/Time ***
Executive Summary
Original plus 3 copies
One
15
TBD
Technical Proposal (Volume I)
Original plus 6 copies
One
100
TBD
Management Proposal (Volume II)
Original plus 6 copies
One
50
TBD
Past Performance Information Sheets (Volume III)
Original plus 4 copies
One
N/A
TBD
Price/Cost Proposal (Volume IV)
Original plus 2 copies
One
N/A
TBD

Total Resources (Volume V) Original plus 6 Copies

One
35
TBD

* THE EXECUTIVE SUMMARY AND EACH VOLUME SHALL BE SUBMITTED ON A SEPARATE CD-ROM, EXCEPT VOLUME IV WHICH SHALL BE SUBMITTED ON A DVD-R.

** Page limitations shall be treated as maximums. If exceeded, the excess pages will not be read or considered in the evaluation of the proposal. These limitations shall apply to both electronic and hard copy proposals. Each page shall be counted except the following:

1. Volume Cover Pages

2. Table of Contents

3. List of Tables and Figures
4. Glossaries / Acronym List
5. Tabs / Dividers
6. Blank pages
7. Online Representations and Certifications Applications (ORCA) Information
8. Section L&M Cross Reference Compliance Matrix
9. Consent Letters / Client Authorization Letters
10. Personnel Resumes

*** Note that the Past Performance Information Sheets are due 2 weeks earlier than the other proposal volumes.

L-2.2 The original of each Offeror’s Executive Summary, and technical, management, past performance, cost proposal, and total resource volumes will be retained with the contract file. All extra copies will be destroyed after contract award.

L-2.3 This is an all-electronic solicitation release. No hard copies will be mailed. Amendments to the solicitation will be posted to www.fedbizopps.gov. It is the responsibility of each Offeror to review the webpage for notice of amendments, updates, or changes to current information.

L-3 PROPOSAL INSTRUCTIONS

L-3.1 Page limits and all other proposal preparation instructions in this solicitation apply to the proposal.

L-3.2 Values to be included in a proposal for Material/Approved ODCs (CLINs 0002, 0006, 0010, 0014, 0018, and 0022) and for Travel (CLINs 0003, 0007, 0011, 0015, 0019, and 0023) are the amounts stated in Section B of the solicitation. All CDRL CLINs (0004, 0008, 0012, 0016, 0020, and 0024) are Not Separately Priced (NSP). Offerors should include Option CLINs in their proposal. Failure to submit a proposal on all CLINs may disqualify the proposal. The CLIN prices shall be submitted in hard copy. If, during technical evaluations, the Government requests revised proposals, Offerors may be instructed to provide them electronically.

L-3.3 All proposals must be complete, self-sufficient, and respond directly to the requirements of the solicitation. Any commitments made in the proposal shall become part of the resultant contract. Proposed innovations and efficiencies must be in sufficient detail to be incorporated into the contract. Apparent inconsistencies between promised performance and proposed prices shall be fully explained by the Offeror. Any significant inconsistency, if unexplained, raises a fundamental issue of the Offeror’s understanding of the program management and resources required and/or ability to perform the contract. This may be a basis for rejection of the proposal. Statements such as “we will comply with the requirements of the contract”, will not by themselves constitute acceptability to meet the requirements of this solicitation. Failure to comply with these instructions may result in an Offeror’s proposal being summarily rejected.

L-3.4 Offerors are advised that data submitted to the Government in response to this solicitation may be released to non-Government advisors for review and analysis. These advisors may be required to provide advice within their area of expertise regarding proposal strengths and weaknesses. Non-Government advisors will be subject to civil and criminal penalties associated with any release of information pursuant to FAR part 3.104 procurement integrity violations. They will not determine ratings or rankings of Offerors' proposals.

If the Offeror has any objection to non-Government advisor access to their proposal information, the Offeror shall provide grounds and justification for their objections. The non-Government advisors are:

Name of Company/Office

Kepler Research, Inc.

Hertha Technology, Inc.

CACI Dynamic Systems, Inc.

Note: The companies listed above may not assist or participate in preparation or submission of any proposal associated with this acquisition.

L-3.5 The technical and management proposals shall be prepared in accordance with these instructions including Paragraphs L-5 and L-6 of this section, and will be evaluated in accordance with the evaluation criteria in Section M, Evaluation Factors for Award. Technical and management proposals shall include necessary information to enable the evaluators to form a definitive conclusion concerning the Offeror’s ability to perform complete program management of the effort for which they are proposing. The Offeror’s proposal must convey to the Government that the Offeror is capable; possesses sufficient technical expertise and experience; possesses sufficient resources; and is able to plan, organize, and use those resources in a coordinated and timely fashion such that technical and management requirements will be achieved and costs will be controlled.

Offerors shall address technical and management proposal risk by identifying those aspects of the proposal considered to have the potential for disruption of schedule, increased cost or degradation of performance, the need for increased Government oversight, and/or the likelihood of unsuccessful contract performance. Classify each risk in accordance with the risk definitions set forth in Section M. Provide the rationale for each risk and its rating, including quantitative estimates of the impact on cost, schedule, and performance. Describe the impact of each identified risk in terms of its potential to interfere with or prevent the successful accomplishment of other contract requirements (for example: SOW requirements), whether or not those requirements are identified as subfactors. Propose a realistic "workaround" or risk mitigators for identified risks that will eliminate or reduce risk to an acceptable level. Identify and classify any new risks introduced by such risk mitigation.

L-3.6 The past performance proposal shall be prepared in accordance with these instructions and Paragraph L-7 of this section, and will be evaluated in accordance with the evaluation criteria in Section M.

L-3.7 The cost/price proposal shall be prepared in accordance with these instructions and Paragraph L-8 of this section, and will be evaluated in accordance with the evaluation criteria in Section M. The price/cost proposal shall be based on the Offeror’s own technical proposal and the Government’s Statement of Work requirements as set forth herein.

L-3.8 The Executive Summary is a concise summary of the Offeror’s proposal, including significant risks, and a highlight of any key or unique features, excluding cost/price. This summary shall specifically identify the Offeror and all proposed team members, subcontractors, and consultants. The name, division, and address of each company should be included. Any summary material presented here shall not be considered as meeting the requirements for any portions of other volumes of the proposal. The Offeror shall ensure the Executive Summary follows the outline below:

a) Narrative Summary

b) Teaming Arrangements

c) Provide a name, title, and telephone number of the person who is authorized to obligate the company contractually

d) Section L&

e) M Cross Reference Compliance Matrix. Using the attached Government provided Cross Reference Compliance Matrix (Section J, Attachment 13), the Offeror shall complete and expand its proposal to the matrix to the level considered adequate to depict the Offeror‘s proposal. The Offeror shall populate (e.g., WBS element, etc.) and include additional columns if deemed appropriate. The proposal paragraph number and format shall mirror Sections L and M paragraph numbering to the maximum extent practical. Offerors may use the volume number as a preface for the paragraph numbering. This matrix shall cross reference the proposal volume and paragraphs to specific RFP requirements, CLINs, WBS, and other parts of the proposal that contain relative information. The paragraph numbering is intended as a tool to assist in the proposal development and evaluation process. The contractor is ultimately responsible for ensuring areas are addressed fully and requested information is completed and turned in appropriately IAW Section L and Section M.

L-3.9 Proposals may be submitted by US Mail, carriers such as FedEx and UPS, or by hand delivery. Proposals to be submitted by US mail need to be addressed to:

Belinda Williams

MDA/DACT
Bldg 5222, Martin Road
Redstone Arsenal, AL 35898

Proposals to be delivered by FedEx, UPS, or hand carried should be addressed to:

Belinda Williams

MDA/DACT
Bldg 5224, Martin Road
Redstone Arsenal, AL 35898

A copy of the price/cost proposal (Volume IV) shall also be simultaneously submitted to the Offeror’s cognizant DCAA office.

L-3.10 Submitted materials shall be fully responsive to and consistent with the following:

· Requirements of the solicitation and SOW, and the CLINs contained therein;

· Government standards and regulations pertaining to the SOW; and

· Evaluation factors and subfactors for award in Section M of this solicitation.

· No cost data will be included in the technical materials. Offerors shall provide cross-reference matrices in each volume, as necessary. For the purposes of the technical evaluation, BOEs will not be considered cost data.

· Format of the proposal volumes (and any resulting responses to Evaluations Notices (ENs)) shall be as follows:

· All typing, including that on charts and graphs, shall be no smaller than what is equivalent to Microsoft Word, Times New Roman, 11 pitch, uncompressed font.

· Pages shall be single sided, one and one half spaced. Past Performance Information Sheets, Attachment 8, and Charts, Tables and Figures, may be provided single spaced.

· Pages shall be dated and numbered.

· Elaborate format, color representations, and bindings are not desirable. Three ring binders are preferred. The pages in the binders shall be easily removed and replaced to facilitate page changes. Any pages that are changed (as the result of negotiations) should be of a different color (as specified by the CO) and have changed information clearly marked by a vertical line in the right margin of the page and/or circling if changing data in a chart. The Offeror shall indicate the new date on revised pages.

· Page margins shall be a minimum of one inch top, bottom, and each side.

· Technical Proposal, Volume I, shall each be limited to 100 pages, excluding documents listed in paragraph L-2.1 above and requested attachments. Pages in excess of 100 will be removed and will not be evaluated.

· Management Proposal, Volume II, shall each be limited to 50 pages, excluding documents listed in paragraph L-2.1 above. Pages in excess of 50 will be removed and will not be evaluated.

· Past and Present Performance, Volume III, is not limited as to the number of pages.

· The Cost/Price Proposal, Volume IV, is not limited as to the number of pages.

· The Executive Summary is limited to 15 pages, excluding documents listed in paragraph L-2.1 above.

· Pages shall not be printed in column format. Text shall be printed from the left margin to the right margin.

· All charts, graphs, and matrices which are larger than 8.5” x 11” must be provided in a fold-out format so that they are capable of being evaluated without removal from the Offeror’s binder. The entire chart should be visible with the notebook open and the folded page fully extended. Each fold-out page counts as one page.

· Electronic copies must be provided on compact disks, read-only memory. Microsoft word processing, presentation and spreadsheet products are preferred. Changes as a result of negotiations will be conformed into a compact disk and have changed information clearly marked by a vertical line in the right margin.

· If discrepancies are identified between the paper version and the electronic version, the paper version shall prevail.

L-3.11Technical data furnished by the Government is in an “as is” condition without any warranty as to its accuracy, completeness, or adequacy. The Offeror shall use this technical data at its own risk. The Government assumes no responsibility for such furnished data/documentation nor will the Government have any liability for an Offeror’s proposal should such data/documentation prove to be inaccurate, incomplete, or otherwise defective. The contractor shall use technical data as marked and IAW DFARS 252.227-7013 and 252.227-7014.
L-4VOLUME DESCRIPTIONS

Executive Summary

· Narrative Summary

· Teaming Arrangements

· Provide a name, title, and telephone number for the person who is authorized to obligate the company contractually

· Section L&M Cross Reference Compliance Matrix Volume I - Technical

· Subfactor 1 – Information Technology

· Subfactor 2 – Software

· Subfactor 3 – Test and Evaluation Data Acquisition and Communications

· Subfactor 4 – Telemetry Operations

· Subfactor 5 – Truth Analysis

· Subfactor 6 – Library Operations Volume II - Management

· Subfactor 1 – Team

· Subfactor 2 – Management Approach

· Subfactor 3 – Programmatic Execution Approach

· Subfactor 4 – Transition

· Subfactor 5 – Small Business Compliance Volume III - Past and Present Performance Volume IV - Cost/Price and Contract Forms Volume V – Total Resources Supports all Technical, Management Subfactors and cost/price

L-5 VOLUME I: TECHNICAL

The Technical Volume shall be divided into six sections: Information Technology, Software, Test and Evaluation Data Acquisition and Communications, Telemetry Operations, Truth Analysis and Library Operations.

L-5.1 Technical Subfactor 1 – Information Technology

The Offeror shall describe their capabilities and approach to executing Information Technology Operations across the MDDC Program. in the following areas:

1) Managing the day-to-day activities and processes associated with Information Technology (IT) system and network management operations; the recruitment and staffing of a well trained, knowledgeable workforce; the short- and long-term technical direction planning; and IT inventory and cost management sustainment activities for IT classified and unclassified networks and systems meeting the following requirements:

a. Manage, administrate and document large network architectures with >100 physical and virtual servers in concurrent use, 250+ users/workstations, and data/file repositories >25 TB that are backed up on a frequent, periodic schedule.

b. Maintains multiple network access points to include file transfer capabilities to external sites.

c. Familiarity with administration and management of network architecture hardware and software including Microsoft Windows Server, Linux distributions, Cisco networking equipment and Cisco IOS, and Storage Array Networks.

2) Accrediting classified and unclassified IT networks and systems IAW the DoD Information Assurance Certification and Accreditation Process (DIACAP).

3) Developing and managing Information Assurance plans and procedures.

L-5.2 Technical Subfactor 2 – Software

The Offeror shall decribe their capabilities and approach to executing and managing software development activities across the MDDC Program in the following areas:

1) Execute and manage software development activities commensurate with Software Engineering Institute/Capability Maturity Model Integration (SEI/CMMI) Level 3 requirements; describe knowledge and expertise regarding processes, procedures, and configuration management approach on similar sized activities.

2) Design, develop, and implement complex software programs that meet the following requirements:

a. Managing and utilizing a codebase >50,000 LOC (lines of code);

b. Use of complex mathematical constructs (such as: matrix and coordinate transformations, linear interpolation, vector mathematics, quaternions);

c. Development of graphical user interfaces to support 3D modeling;

d. Use of authentication and authorization security paradigms;

e. Interconnectivity and use of database systems within the codebase;

f. Familiarity and use of link margin analysis/planning toolsets;

g. Familiarity with and use of:

i. C#, C++, Adobe CFML (Coldfusion Markup Language), SQL (Structured Query Language);

ii. Microsoft SQL Server;

iii. Windows Authentication/Authorization methods.

L-5.3 Technical Subfactor 3 – Test and Evaluation Data Acquisition and Communications

The Offeror shall describe their capabilities and approach in the following areas:

1) Acquiring and processing of critical flight test data (telemetry, radar, optical, etc.), recording and distributing in real-time across the MDA communications network. Experience with bandwidth management/compression, data tagging to support sensor cueing/pointing for range and mobile sensors at primary and remote execution nodes.

2) Planning and executing comprehensive flight test data architectures and provide real-time/non-real time situational awareness displays at primary and remote execution nodes supporting high-fidelity data driven displays, video relays, mission voice nets and countdown clock displays across MDA communications network.

L-5.4 Technical Subfactor 4 – Telemetry Operations

The Offeror shall describe their capabilities and approach in the following areas:

1) Acquiring telemetry data from multiple sources, decommutate/process telemetry from target and interceptor telemetry streams, record, reduce telemetry to critical key parameters and disseminate real-time across MDA communications network necessary to support flight test launch operations.

2) Development of target health and status displays which support real-time launch authority decisions and range safety assessments.

3) Operations, identification, reporting and anomaly resolution with government furnished equipment for global positioning system data supporting truth analysis and range safety solutions.

4) Planning and executing large complex flight test architectures using systematic systems engineering processes collecting quantifying MDA BMDS weapon system performance parameters.

L-5.5 Technical Subfactor 5 – Truth Analysis The Offeror shall describe their capabilities and approach in the following areas:

1) Development of best estimate trajectories (BETS) for all interceptor and target objects, instrumented and un-instrumented.

2) Development of BETS in multiple reference frames and formats.

3) Development of infrared and radar frequency phenomenology analysis.

4) Iidentifying, reporting, and resolving anomalies seen in Truth analysis activities.

L-5.6 Technical Subfactor 6 – Library Operations

The Offeror shall describe their capabilities and approach to executing Library Operations across the MDDC Program in the following areas:

1) Manage and operate a technical library with >100,000 different data items in a variety of media types. Provide a table to list/show experience with different media types.

2) Distribute data electronically and physically.

3) Manage and maintain accountability of data items IAW DoD and MDA security policies and guidance.

L-6 VOLUME II: MANAGEMENT

The Management Volume shall be divided into five sections: Team, Management Approach, Programmatic Execution Approach, Transition and Small Business Compliance. The Offeror shall describe their understanding of the MDDC Program and their ability to tailor best practices to fit its requirements.

L-6.1 Management Subfactor 1 – Team

The Offeror shall describe their management approach to provide a Team and framework including subcontractors necessary to successfully execute the MDDC Program SOW and provide flexible, responsive, innovative, and efficient MDDC Program products and operations.

1) Provide a description and organization chart depicting the team and framework, subcontractors, lines of authority, and communication process between technical and management that address the MDDC Program SOW holistically.

2) Provide a table that identifies key positions within the organizational structure that can support the SOW requirements, their planned responsibilities, and detail their applicable SOW experience. Position requirements shall be provided to fulfill this requirement. Offeror shall submit position descriptions and qualification packages for each individual proposed to fill a key position. (The position descriptions and qualification packages count is limited to 2 pages per key position. This does not count against the 50 page limit for the Management section).

L-6.2 Management Subfactor 2 – Management Approach

The Offeror shall describe their capabilities and approach to organizing resources to most efficiently and effectively manage contract execution and mitigate program risk.

1) Offeror shall describe a program-wide approach to managing technical, performance, cost, and schedule risk.

2) Offeror shall describe their process and approach to organize, staff, and allocate resources to meet the SOW. Offeror shall describe an approach for personnel recruitment and retention to ensure personnel are in place and trained.

3) Offeror shall describe their approach to provide a crossed-trained work force for SOW efficiencies.

4) Offeror shall describe an approach to risk management that includes identification, tracking, and mitigation of program risk.

5) Offeror shall provide a Contract Work Breakdown Structure (CWBS) and dictionary, which reflects the Offeror’s understanding of the contract effort. The CWBS shall serve as the framework for organizing the MDDC effort to include in-house, inter-divisional, subcontractor, and associate contractor activities. The reference document for developing the WBS and dictionary is MIL-HDBK-881A. The CWBS shall be developed to a depth (level) and breadth sufficient to accurately describe the Offeror's understanding of the effort required as reflected in the SOW. Each element of the CWBS shall include a reference to the primary SOW paragraph or paragraphs. Illustrate how the CWBS will be used to manage the work outlined in the SOW. The top four levels may be placed on contract as the CWBS."5) Offeror shall provide a Contract Work Breakdown Structure (CWBS) and dictionary, which reflects the Offeror’s understanding of the contract effort. The CWBS shall serve as the framework for organizing the MDDC effort to include in-house, inter-divisional, subcontractor, and associate contractor activities. The reference document for developing the WBS and dictionary is MIL-HDBK-881A. The CWBS shall be developed to a depth (level) and breadth sufficient to accurately describe the Offeror's understanding of the effort required as reflected in the SOW. Each element of the CWBS shall include a reference to the primary SOW paragraph or paragraphs. Illustrate how the CWBS will be used to manage the work outlined in the SOW. The top four levels may be placed on contract as the CWBS."

L-6.3 Management Subfactor 3 – Programmatic Execution Approach

The Offeror shall describe their capabilities and approach to providing a Management Plan/System for effective planning and control of resources, and the process for accounting and collecting costs for the entire contract, separate tasks, and ACRNs to accomplish multiple and complex tasks and/or task orders simultaneously.

L-6.4 Management Subfactor 4 – Transition

The Offeror shall describe their capabilities and approach to providing a plan and resources to work with the incumbent contractor(s) during the transition period to maintain all MDDC Program SOW requirements and to complete the transition period within the minimum time and cost.

1) Offeror shall describe their approach to transition resources and personnel to this contract required to perform the MDDC Program mission and SOW requirements.

2) Offeror shall describe a process to work with the incumbent contractor(s) to smoothly transition the MDDC Program products / operations.

3) Offeror shall provide a realistic schedule, which includes key milestones with metrics to measure progress, to successfully transition all tasks within a designated transition period of no more than 45 days.

4) Offeror shall provide their phase-in schedule that would obtain the appropriate staffing levels, skill mix, expertise, security clearances, and certifications to provide adequate trained, certified, and cleared personnel.

L-6.5 Management Subfactor 5 – Small Business Compliance

The Offeror shall provide a plan, to be incorporated into the resultant contract, that describes how they plan to comply with the limitation on subcontracting requirement that at least 50% of the price on the contract will be performed by employees of the concern and submit supporting documentation applicable to all concerns you wish to count towards the accomplishment of the 50% rule. See FAR 52.219-14, Limitations on Subcontracting.

L-7 VOLUME III: PAST AND PRESENT PERFORMANCE

L-7.1 Contents. The Offeror shall submit a Past Performance Volume containing the following:

1) Table of Contents

2) Summary Page describing the role of the Offeror and each subcontractor and/or teaming partner for which the Offeror is required to provide Past Performance Information Sheets in accordance with paragraph L-7.2 below.

3) Past Performance Information Sheets in accordance with Section J, Attachment 8 to the solicitation – see paragraph L-7.2 below.

4) Consent Letters executed by each subcontractor and/or teaming partner, authorizing release of adverse past performance information so the Offeror can respond to such information. A sample letter is attached as Section J, Attachment 10.

5) Organization Structure Change History—See paragraph L-7.4 below.

L-7.2 Past and Present Performance Information Sheets. Submit information on contracts you consider most relevant in demonstrating your ability to perform the proposed effort. The Offeror shall submit Performance Information Sheets in accordance with the format contained in Section J, Attachment 8 to the solicitation. This information is required on the Offeror and subcontractors and/or teaming partners proposed to perform any of the proposed effort that the Offeror considers critical to overall successful performance. The Offeror shall submit a maximum of five (5) and a minimum of three (3) Performance Information Sheets identifying active or completed contracts, either Government or commercial, for the prime; and three (3) Performance Information Sheets for each major and/or critical subcontractor. A major subcontractor is defined as one performing $3M or more of the total basic contract. A critical subcontractor is one whose performance on the awarded contract is such that if it fails, could significantly impact program success. Each relevant contract shall meet the Government’s definition of recency. The Government defines recency as any contract having been performed during the past five (5) years from the date of issuance of this solicitation. Each Performance Information Sheet for each contract is limited to ten (10) pages. Offerors are cautioned that the Government will use data provided by each Offeror in this volume and data obtained from other sources in the evaluation of past performance. The Offeror shall provide a list of the proposed respondents with two points of contact, current e-mail address, and phone numbers in its Past Performance Volume. The Government reserves the right to contact these sources if they do not submit responses by the proposal due date.

L-7.3 Relevant Contracts. In determining relevancy at the Technical and Management subfactor level, consideration will be given to past performance in providing the program management, mission assurance, operations and sustainment, mission focus and security capabilities and support to other programs that are similar in size and scope to the MDDC Program as described in the SOW. Include rationale supporting your assertion of relevance and how the referenced contract is a relevant indicator of performance against the Technical and Management subfactors. This information shall be submitted as part of the Past Performance Information Sheet, Section J, Attachment 8. For a description of the characteristics or aspects the Government will consider in determining relevance, see Section M, paragraphs M-3.2 and M-7.0.

L-7.4 Organizational Structure Change History. Many companies have acquired, been acquired by, or otherwise merged with other companies, and/or reorganized their divisions, business groups, subsidiary companies, etc. In many cases, these changes have taken place during the time of performance of relevant present or past efforts or between conclusion of recent past efforts and this source selection. As a result, it is sometimes difficult to determine what past performance is relevant to this acquisition. To facilitate this relevancy determination, include in this proposal volume a "roadmap" describing all such changes in the organization of your company. As part of this explanation, show how these changes impact the relevance of any efforts you identify for past performance evaluation/performance confidence assessment. Since the Government intends to consider past performance information provided by other sources as well as that provided by the Offeror(s), your "roadmap" should be both specifically applicable to the efforts you identify and general enough to apply to efforts on which the Government receives information from other sources.

L-7.5 Resolution of Problems. Offerors may include a discussion of efforts accomplished by the Offeror to resolve problems encountered on prior contracts as well as past efforts to identify and manage program risk. Merely having problems does not automatically equate to a No Confidence rating, since the problems encountered may have been on a more complex program, or an Offeror may have subsequently demonstrated the ability to overcome the problems encountered. The Offeror is required to clearly demonstrate management actions employed in overcoming problems and the effects of those actions, in terms of improvements achieved or problems rectified. This may allow the Offeror to be considered a High Confidence or Significant Confidence candidate. Submittal of quality performance indicators or other management indicators that clearly support that an Offeror has overcome past problems is required.

L-7.6 Questionnaires. The Government requests the Offeror send out Past Performance Questionnaires, Section J, Attachment 3, to each of the Points of Contact (POCs) identified in the Past Performance Volume. The Offeror shall fill in the project and evaluator information on the questionnaire prior to sending it to the POC. Completed questionnaires shall be submitted by the POC directly to the Contracting Officer. A cover letter for transmitting the questionnaire to each POC is provided as Section J, Attachment 9. Each of the Offeror's POCs shall e-mail the completed Past and Present Performance Questionnaire to Belinda.williams@mda.mil with a courtesy copy to TBD or fax the completed Questionnaire directly to TBD. Although an e-mailed Questionnaire is preferable, mailing the Questionnaire(s) to the address listed below is an acceptable alternative method of transmission. If faxing or mailing, the cover page or outside envelope, as applicable, must be marked as follows:

NOTE: SOURCE SELECTION SENSITIVE
Belinda J. Williams
Contracts Directorate
BLDG 5222 Martin Road
Redstone Arsenal, AL 35898-0001
Solicitation HQ0147-10-R-0030

L-7.7 Subcontractor/Teaming Partner Consent Form. Past performance information concerning key subcontractors or subsidiaries cannot be disclosed to a private party without consent. Because the Offeror is a private party, the Government will need that consent before disclosing key subcontractor and/or subsidiary past performance information to the Offeror during exchanges. In an effort to assist the Past Performance Team in assessing past performance, the Government requires that a Subcontractor/Teaming Partner Consent Form for the Release of Past Performance Information (Section J, Attachment 10) be completed by each key subcontractor and/or subsidiary identified in the proposal. The completed consent forms should be submitted as part of Volume III Past Performance (not subject to page count limitation).

L-8 VOLUME IV: COST/PRICE AND CONTRACT FORMS

L-8.1 FAILURE TO COMPLY WITH SOLICITATION REQUIREMENTS FOR COST INFORMATION MAY RESULT IN AN ADVERSE ASSESSMENT OF AN OFFEROR’S PROPOSAL AND REDUCE OR ELIMINATE ITS CHANCE OF BEING SELECTED FOR AWARD. When an Offeror fails to furnish pricing information required by the solicitation, the Offeror bears full responsibility for any adverse impact upon the evaluation of its proposal.

L-8.2 General Instructions. The Offeror shall ensure the information presented in this volume is consistent with the information contained in the other proposal volumes. The Offeror shall submit the Original plus two (2) hardcopy volumes of the prime contractor’s proposal and the Original plus two (2) hardcopy volumes of each major subcontractor’s cost proposal. The Offeror shall submit one (1) electronic copy of the prime contractor’s proposal and one (1) electronic copy of each major subcontractor’s cost proposal on DVD-R, which is separate from the other proposal volumes. The Offeror’s cost proposal shall be submitted in one volume labeled Volume IV Cost/Price Proposal and Contract Forms.

For each Cost Plus Incentive Fee (CPIF) CLIN, the Offeror shall propose a Target Cost and Target Fee. The Target Fee shall be based on the Offeror’s proposed Target Cost. The Share Ratio shall be 50/50 (50% Government / 50% Offeror) for Above Target Cost, and the same 50/50 for Below Target Cost. The Maximum Fee shall be 15%. The Minimum Fee shall be 0%.

Inter-divisional Work Transfer Agreements (IWTAs)/teammates/subcontractors are not required to disclose proprietary cost/price information to the prime Offeror. IWTAs/teammates/subcontractors performing $3M of the basic contract period effort, whichever is less (excluding ODC and Travel), are “Major Subcontractors” for Cost Volume purposes. Major Subcontractors shall follow the same instructions as the prime contractor regarding cost proposal format and content. Major Subcontractors are not required to disclose proprietary cost information to the prime Offeror. However, the prime Offeror must include summary level cost information for all Major Subcontactors work requirements and must ensure an un-sanitized proposal is submitted for each subcontract proposal at any tier equal to or greater than $3M of the first contract period’s effort. In a case where the prime Offeror’s Cost volume does not contain full cost information for a specific Major Subcontractor, the Major Subcontractor must forward an un-sanitized proposal directly to the Government no later than the closing date of the solicitation. Any proposal submission made directly to the Government by a Major Subcontactor shall clearly identify the prime Offeror and RFP to which their submitted cost data applies. All Major Subcontractor proposal submissions made directly to the Government shall include both an electronic and hardcopy submittal for inclusion into the Offeror’s Cost Volume. Major Subcontractor submissions must conform to the same standards set forth as applicable to the prime Offeror (including electronic submissions addressed in L-3.10). Alternatively, in lieu of direct submission to the Government, Major Subcontractors may provide both the electronic and hardcopy un-sanitized submittals, in a sealed envelope, to the prime Offeror for inclusion into the proposal and further submittal to the Government. The envelope(s) shall remain sealed and be placed within or attached to Volume IV by the prime Offeror.

In accordance with FAR 15.305(a)(1), adequate price competition is anticipated which will establish price reasonableness. Therefore, certified cost or pricing data is not required at this time. Information other than Cost or Pricing data shall be required. However, if after receipt of proposals, the PCO determines that there is inadequate price competition, and none of the exceptions in FAR 15.403-1 apply, the Offeror shall be required to submit cost or pricing data. To ensure that the Government is able to perform a fair assessment of the proposed costs/prices, each Offeror is required to submit a cost proposal that is suitable for evaluation. A cost volume that is suitable for evaluation shall:

a. Account for all Direct Person Labor Hours (DPLH) necessary to complete requirements of this RFP and reconcile with the DPLHs as proposed in the Total Resources Volume V.

b. Provide traceability to the technical/management proposal(s).

c. Explain in detail all pricing and estimating techniques.

d. Disclose the basis of all projections, rates, ratios, percentages, and factors in sufficient detail to facilitate the SSET’s understanding and ability to mathematically verify these estimating tools.

e. Comply with applicable Federal Acquisition Regulation (FAR), DOD FAR Supplement (DFARs), and governing statutory requirements.

f. Include a narrative portion that explains all judgmental elements of cost projections, profits and fee policies.

g. Include all pricing exhibits required in this RFP.

Cost proposals shall be submitted in accordance with FAR 15.408(1) and with FAR 15.403-5. In submitting its proposal, the Offeror grants the Contracting Officer or an authorized representative the right to examine, at any time before award, books, records, documents, or other directly pertinent records to the reasonableness and realism of proposed cost or prices.

For pricing purposes, an estimated start date of January 1, 2012 is to be used for the overall effort. The Offeror’s proposal shall be submitted with any information reasonably required to explain the estimating process, including the judgmental factors applied and the mathematical or other methods used in the estimate, including those used in projecting from known data; and the nature and amount of any contingencies included in the proposed price. The Offeror’s cost proposal shall clearly describe or define all contractor labor categories proposed and must include a cross reference to the labor categories listed on the Pricing Exhibits. The RFP Labor Categories descriptions are specified in Section J, Attachment 4. Provide any other general information that may be beneficial in evaluation of the Offeror’s proposal.

In the event the Offeror’s fiscal year and anticipated contract periods do not coincide, the prime Offeror and all major subcontractors shall provide the rate reconciliation showing how the fiscal year direct labor rates were blended to produce the contractor direct labor category cost included on Pricing Exhibit B1.

L-8.3 Contract Cost Volume. Offerors shall propose in accordance with the CLIN structure set forth in Section B and the Statement of Work. The Contract cost Volume shall support the Offeror’s proposed amounts for all MDDC CLINs, as shown in Section B of the model contract.

The Cost Plus Incentive Fee (CPIF) – Level of Effort (LOE) CLIN 0001 and Option CLINs 0005, 0009, 0013, 0017, and 0021 shall be priced in accordance with Government provided Total DPLH Pricing Exhibit B7.

The Cost Type CLIN 0002, and Option CLINs, 0006, 0010, 0014, 0018, and 0022, for Materials and Approved ODCs shall be proposed in accordance with Government provided Maximum Amounts in Section B.

The Cost Type CLIN 0003, and Option CLINs 0007, 0011, 0015, 0019, and 0023, for Travel shall be proposed in accordance with Maximum Amounts in Section B.

CDRL CLIN 00014, and Option CLINs 0008, 0012, 0016, 0020, and 0024 are not separately priced.

L-8.4 SECTION I – COVER PAGE AND INDEX

Provide the following information on the inside cover page:

a. Solicitation number.

b. Name and address of the Offeror.

c. Name, telephone number (and if applicable, cell phone number), fax number, and e-mail address for proposal point of contact at contractor’s facility.

d. Type of contract.

e. Place and period of performance.

f. Name, address, voice telephone number of contract administration office.

g. Name, address, voice telephone number, fax number, and e-mail address of cognizant Defense Contract Audit Agency point of contact.

h. Date of submission.

i. Name, title and signature of authorized representative.

Include an index showing section number, title, and proposal page number.

L-8.5 SECTION II – SYNOPSIS OF CURRENT DEFENSE CONTRACTS AUDIT AGENCY DETERMINATION STATUS OF ESTIMATING, PURCHASING, AND ACCOUNTING SYSTEMS. Provide a summary description of your standard estimating system or methods, current policies, and/or new policies. State whether the estimating system and new policies have been reviewed by the Government and provide evidence of review and/or Administrative Contracting Officer approval. Provide any known/cited estimating system deficiencies.