This document is a Performance Work Statement (PWS) for the Next National Geospatial-Intelligence Agency West (N2W) Moving Services contract. The PWS outlines the requirements for a contractor to provide logistics services, including planning support and office relocation, to accomplish the NGA N2W Deployment.
The key details are:
- The contractor shall provide all labor, materials, transportation, and management to relocate approximately 14,000 packing crates and 1,500 pieces of equipment from the existing NGA St. Louis and NGA Arnold locations to the new N2W campus in St. Louis.
- The contract has three phases: support planning, pre-moves, and increment moves over a 12-week period.
- The contractor must develop a comprehensive Support Plan and Schedule, including staffing, packing/equipment handling, inventory tracking, and building protection plans.
- The contractor shall perform detailed inventory tracking, with scans at each step of the moving process.
- The contractor is responsible for providing packing crates, packing materials, and crate management throughout the relocation.
- The contractor must ensure all personnel meet security requirements for NGA facility access.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFIED
Attachment A
Amd 0002
PERFORMANCE WORK STATEMENT
MOVING SERVICES
NEXT NATIONAL GEOSPATIAL-INTELLIGENCE
AGENCY WEST (N2W)
Solicitation HM157524R0010
21 May 2024
Un
PERFORMANCE WORK STATEMENT 2
For the 3
Next NGA West (N2W) Moving Services Contract 4
NATIONAL GEOSPATIAL-INTELLIGENCE AGENCY 5
(NGA) 6
Un
1. GENERAL INFORMATION 9
1.1 Background 10
The National Geospatial-Intelligence Agency (NGA) Next NGA West (N2W) Program 12
Management Office (PMO) is tasked with the construction of a Department of Defense 13
(DoD) Intelligence Community (IC) facility in the city of St. Louis, Missouri. The 14
N2W Moving Services contract shall provide relocation services to accomplish NGA 15
N2W Deployment. 16
1.2 Description of Services 18
The Contractor shall provide logistics services, to include planning support and office 20 relocation, as needed to accomplish the NGA N2W Deployment Execution Plan 21 moving official material, including books, paper, and equipment, from NGA St. Louis 22 located at 3200 South 2nd Street, St. Louis, MO, and NGA Arnold at 3838 Vogel Road, 23
Arnold, MO, to the new N2W campus located at 2301 Cass Avenue, St. Louis, MO. 24
The mileage from the 2nd street location to the new N2W campus is between 4.5 to 6.5 25 miles depending on route, for Arnold the mileage is around 21 miles. 26
1.3 Scope 28
The contractor shall provide logistics experts to provide planning support and execute 29 the relocation of office material, equipment, and components to its new N2W facility. 30
The Contractor shall provide all labor, tools, materials, parts, supplies, components, 31 equipment, transportation, travel, supervision, and management necessary to provide 32 office relocation (moving) services to accomplish the N2W Deployment Execution Plan 33 relocating (moving) office material, equipment, components, and items. This includes 34 an estimated 14,000 packing crates and estimated 1,500 pieces of equipment. 35
The Government’s N2W Deployment Execution Plan details the number of employees, 36 material, and equipment designated to move, along with scheduled move dates and 37 starting and ending locations. The Contractor shall provide support to N2W 38
Deployment Execution Planning, including estimated amount and schedule for labor, 39 materials, supplies, components, equipment, transportation, travel time, supervision, 40 and management needed to accomplish the office relocation within the prescribed time. 41
The Contractor shall support preparatory briefings to Government employees on 42 packing directions and restrictions. The Contractor shall provide planning assistance for 43 disassembly, material tracking/accountability, packing, transport, delivery, and 44 reassembly of mission unique material and equipment. 45
The Contractor shall track inventory and maintain 100% accountability of all material 46 and equipment from point of collection to designated final delivery location. The 47
Contractor shall provide in-progress inventory reporting and location tracking of 48 material, equipment, and vehicles containing NGA material and equipment. This 49 information will be made available for the Government to check after the completion of 50 the 2nd, 3rd, and final scans for each truckload as described in Section 2.2 and upon 51 request. 52
Un
The Contractor shall provide all materials needed to protect floors, walls, corners, 54 elevators, doors, and furniture within NGA buildings. The Contractor shall disassemble, 55 pack, transport, deliver, and reassemble designated material and equipment. 56
1.4 Phases of Services 58
The contract phases of performance will include: 59
• Support planning phase 60
• Pre-moves phase 61
• Increment moves phase 62
The support planning phase starts after contract award and runs until the complete 63 logistics plan is approved by the Government. The pre-move phase occurs two (2) to 64 three (3) months before the increment moves phase begins. The pre-moves will consist 65 of several one-day moves plus possible multiple-day moves for the library, survey and 66 gravity measuring equipment. The increment moves phase is a scheduled twelve (12) 67 weeks of moves, with each week designated as an increment. 68
The three (3) phases are described below in Section 3. The anticipated commencement 69 of relocation services is tentatively late calendar year 2025. The Government will 70 provide the Contractor at least six (6) weeks’ notice of N2W increment move sequence 71 dates once they are determined. 72
1.5 Place of Performance 74
The work under this contract will be performed at NGA’s facilities at 3200 South 2nd 75
Street, St. Louis, MO (NGA St. Louis); 3838 Vogel Road, Arnold, MO (NGA Arnold); 76 and 2301 Cass Avenue, St. Louis, MO (N2W). 77
The NGA St. Louis location has several buildings. The main building is seven levels with 78 approximately 826,000 square feet. There are three larger outbuildings each with two 79 levels and approximately 12,000 square feet. There is one outbuilding with four levels 80 and approximately 8,400 square feet. Additionally, there are seven smaller outbuildings 81 ranging in size between 6,700 to 2,000 square feet. 82
The NGA Arnold location has a three-level, 143,000 square foot building. 83
The N2W location has a four level, 711,000 square foot main building. There are also two 84 single story outbuildings with 9,500 square feet and 7,300 square feet. 85
1.6 Hours of Operation 88
1.6.1 Support Planning Phase 89
N2W deployment execution support planning and associated meetings will be conducted 91 between the hours of 0700 and 1700 CST (core hours), Monday thru Friday, 92 notwithstanding Federal holidays, and other Government-directed site closures. 93
Un
1.6.2 Pre-move Phase 94
A series of pre-moves will occur two to three months before the main increment move 95 sequence to move support personnel into N2W. The pre-moves are for groups of 96 support personnel who provide security, facility management, and information 97 technology capabilities. 98
The pre-moves will consist of several one-day moves plus possible multiple-day moves 99 for the library, survey and gravity measuring equipment. 100
For the moving days, the Contractor shall work between the hours of 1400 and 2230 101
CST, Monday through Friday, notwithstanding Federal holidays, and other 102
Government-directed site closures. Work by the Contractor will be accomplished 103 during listed hours unless prior written approval is obtained from the Contracting 104
Officer Representative (COR), Assistant COR (ACOR), or Contracting Officer. 105
For contingencies that prevent execution of a planned pre-move schedule, abnormal and 106 extended work hours may be required. At a minimum, work hours may include 107 weekends and holidays necessary to support the move sequence schedule, or a pre-108 move work day taking ten (10) hours and finishing at midnight, or until the pre-move is 109 complete with all items accounted for at their designated final delivery location. Written 110 approval of abnormal or extended working hours will be made by the COR/ACOR 111 working with the N2W Deployment Assistant Program Manager (APM). 112
1.6.3 Increment Moves Phase 114
The increment move phase will primarily be conducted over twelve (12) weeks with 115 approximately three (3) days of moving each week. The twelve (12) weeks of moves 116 may or may not be consecutive weeks based on the Federal holiday schedule. For the 117 moving days, the Contractor shall work between the hours of 1400 and 2230 CST, 118
Monday through Friday, notwithstanding Federal holidays, and other Government-119 directed site closures. Work by the Contractor will be accomplished during listed hours 120 unless prior written approval is obtained from the Contracting Officer Representative 121
(COR), Assistant COR (ACOR), or Contracting Officer. After the increment moves 122 phase starts, any adjustments to the increment move sequence schedules will be 123 developed with the Contractor in coordination with the N2W Deployment Team and 124
COR via a weekly meeting. 125
For contingencies that prevent execution of a planned weekly increment move 126 schedule, abnormal and extended work hours may be required. At a minimum, work 127 hours may include weekends and holidays necessary to support the move sequence 128 schedule, or an increment move work day taking ten (10) hours and finishing at 129 midnight, or until the increment move is complete with all items accounted for at their 130 designated final delivery location. Written approval of abnormal or extended working 131 hours will be made by the COR/ACOR working with the N2W Deployment Assistant 132
Program Manager (APM). 133
Un
Quality Control 136
1.7.1 The Contractor shall develop and maintain an effective quality control program to 138 ensure services are performed in accordance with this PWS. The Contractor shall develop 139 and implement procedures to identify, prevent, and ensure non-recurrence of defective 140 services. The Contractor’s quality control program is the means by which they assure 141 themselves and the government that their work complies with requirements in the contract. 142
A Quality Control Plan (QCP) must be delivered per Section 3.1. A copy of a 143 comprehensive written QCP shall be submitted to the Contracting Officer (KO) and COR 144 within five (5) business days when changes are made thereafter. After acceptance of the 145
QCP, the Contractor shall receive the Contracting Officer’s acceptance in writing of any 146 proposed change to their quality control program. 147
1.7.2 Quality Assurance: The Government shall evaluate the Contractor’s performance 149 under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). 150
The QASP is primarily focused on the Government’s role to ensure that the Contractor has 151 performed in accordance with the performance standards. It defines how the performance 152 standards will be applied, the frequency of surveillance, and the Acceptable Performance 153
Levels. The Contractor shall participate in monthly progress meetings with the 154
Government. The progress meetings may be virtual or in person during the first full week 155 of the month. 156
1.8 Meetings 158
Post-Award Conference: The Contractor agrees to attend the post-award conference 160 convened by the Government. The post-award conference will occur within 30 business 161 days of award of the first task order. 162
Monthly Progress Meetings: The APM, COR/ACOR and other Government personnel, 163 as appropriate, may meet periodically with the Contractor to review the contactor’s 164 performance. These meetings will be planned monthly. These meetings may be in 165 person or virtual, at the Government’s discretion. At these meetings, the APM and 166
COR/ACOR will apprise the Contractor of how the Government views the Contractor’s 167 performance and the Contractor shall apprise the Government of problems, if any, 168 being experienced. The Contractor shall resolve outstanding issues raised by the 169
Government in accordance with the QASP. 170
Coordination Meetings: The Contractor’s representative shall attend coordination 171 meetings to collaborate, receive instruction and provide information about the Support 172
Plan and Schedule. Deliverables from coordination meetings will be any Government 173 requested updates to the Support Plan and Schedule. Coordination Meeting schedules 174 will vary during the different phases, as described below. Although efforts will be made 175 to stick within the below meeting timelines, if the government needs to postpone or add 176 additional meetings to manage requirements, the contractor will remain flexible to that 177 end. 178
Coordination Meetings in Support Planning Phase: During the first 90 business 179 days post-award of first task order, coordination meetings will be held weekly, at a 180
Un minimum. These meetings are to support Contractor work on the Support Plan and 181
Schedule and Quality Control Plan. After 90 business days, coordination meetings will 182 be held monthly, at a minimum. 183
Coordination Meeting in Pre-moves Phase and Increment Moves Phase: 184
Coordination meetings will be held weekly, at a minimum, during both the Pre-moves 185
Phase and Increment Moves Phase. 186
Walk Through(s): The Contractor and Government representatives shall participate in 187 walk throughs, as requested, to inspect the equipment to be moved and facilities at the 188 present and new locations to become acquainted with conditions existing at all 189 locations. This will ensure that the necessary equipment and labor can be furnished to 190 provide for the orderly, timely, and efficient movement of the property. This may 191 include one pre-move survey prior to each scheduled move. There may be up to 15 192 walk throughs. 193
2. SPECIAL REQUIREMENTS 196
2.1 Moving Services 197
The Contractor shall provide all labor, tools, materials, parts, supplies, components, 199 equipment, transportation, travel, supervision, and management necessary to provide 200 office moving services for accomplishment of the N2W Deployment Execution Plan to 201 move office material, equipment, components, and items from NGA St. Louis and NGA 202
Arnold locations to N2W. 203
The Contractor shall provide packing crates and packing material for employees to pack 204 office material. The crates shall be re-usable, made of water-resistant plastic with attached 205 flip top interlocking lids, with a capacity to hold 2.5-3.5 cubic feet and 80-100 pounds of 206 material, ability to be stacked at least four (4) crates high and moved on crate dollies, and 207 can be sealed with non-releasable, single use security ties. The Contractor shall provide a 208 sleeve to insert or method to attach a label on the end (short side) of each crate. The 209
Contractor shall provide tamper-evident tape along with the non-releasable, single use 210 security ties. Two (2) different color non-releasable, single use security ties shall be used 211 to distinguish N2W destination areas. Approximately 80% of crates will need red security 212 ties and 20% will need green security ties. The Contractor shall provide one (1) crate dolly 213 for at least every four (4) stackable crates estimated to be in circulation at any given time 214 across all locations. All packing material, such as packing paper and bubble wrap, must be 215 new and unused, except for the re-usable packing crates. 216
The Contractor is responsible for handling and maintaining packing crate inventory 217 throughout the project to support the move sequence plan. The Contractor shall 218 distribute the crates to each pickup or pre-staging location. Crates shall be delivered to 219 the designated buildings in the N2W Deployment Execution Plan’s move sequence at 220 least ten (10) business days ahead of time to support Government distribution to each 221 employee prior to a move. Packing material, security ties, and tamper-evident tape shall 222 be provided for the number of crates delivered. 223
The Contractor is responsible for collection of crates from designated areas, movement 224 to loading docks, loading on trucks, movement to N2W, unloading at N2W loading 225
Un dock, delivery to the designated final delivery location, and then collecting and 226 transporting empty crates from N2W to the Government-directed NGA St. Louis or 227
Arnold sites. Government employees will pack their own official material at their 228 workstation into packing crates, label them with their new N2W workstation number, 229 and seal each crate. 230
Upon completion, of a move increment, the government, within 7 business days, will 231 return at least 90% of the crates to the designated staging area. Within 14 business days 232
100% of the crates will be returned. 233
A Government escort will remain in any Contractor vehicle that contains Government 234 material during movement between Government facilities. 235
The Contractor shall support moving Government material such that no Government 236 material is stored outside a Government facility overnight. The Contractor shall deliver 237 all Government material within the fence lines of an NGA Government facility by the 238 end of work day. 239
The Contractor shall protect floors, walls, corners, elevators, doors, and furniture within 240
NGA buildings. The Contractor shall disassemble, pack, transport, deliver, and 241 reassemble designated material and equipment. The Contractor shall provide in-242 progress inventory reporting and location tracking of vehicles with NGA material and 243 equipment. 244
2.2 Inventory Tracking 246
The Contractor shall track inventory of all material and equipment from point of 247 collection to designated final delivery location. The Contractor will operate an 248 inventory system that provides the Government in-progress status of material and 249 equipment. The in-progress status will be available for the Government to check and 250 validate after the completion of the 2nd, 3rd, and final scans for each truckload as 251 described below and upon request. 252
Due to security requirements inside Government buildings, the scanning equipment 253 used inside (other than the actual loading dock area) cannot have WIFI capability, 254 cellphone connectivity, or cameras and are limited to low energy Bluetooth (version 4 255
LE) signals. Scanning equipment that meets the security requirements and has been 256 approved by the Government may be used inside the Government building. Uploading 257 of the data would be limited to a loading dock or outside the building. RFID trackers 258 cannot be used on crates or equipment. All Contractor scanning equipment must be 259 inspected and approved by NGA Security before use in Government facilities. 260
The Contractor shall perform the following: 261
Initial Scan - Crates and Mission Unique Equipment (MUE) scanned at point of 262 collection and moved from the original office location to the loading dock or designated 263 loading area. 264
2nd Scan- Crates and MUE scanned at the loading dock or designated loading area to 265 validate receipt, then loaded onto the moving truck. The Contractor shall provide 266 validation to the Government that all crates and MUE scanned at point of collection 267
Un were also scanned being loaded into moving truck prior to authorizing sealing and 268 departure of the moving truck. The Contractor shall provide a bolt seal or padlock to 269 secure the truck contents. The Government will maintain control of key(s) to bolt seal 270 or padlock. Truck seals or locks cannot be opened or broken without Government 271 presence and approval. 272
3rd Scan - Crates and MUE scanned and offloaded from the moving truck at an N2W 273 loading dock. The Contractor shall provide validation to the Government that all crates 274 and MUE offloaded at N2W match the crates and MUE scanned at point of collection. 275
Upon validation, the Government approves departure of any crates and MUE from the 276 loading dock area. 277
Final Scan - Crates and MUE scanned when delivered to designated final delivery 278 location (workstation or location at N2W). The Contractor shall provide validation to 279 the Government that all crates and MUE moved from points of collection are delivered 280 to the designated final delivery location and that all crates handled by the Contractor 281 that day are accounted for. 282
The Contractor shall track vehicle location in real time. The in-progress status and 283 location of vehicles with Government material and equipment shall be available for the 284
Government to check and validate after the completion of the 2nd, 3rd, and final scans 285 for each truckload as described above and upon request. The Contractor shall provide 286 daily inventory reports of all Government material and equipment handled by the 287
Contractor that day. 288
Un
2.3 Equipment Packing and Moving Services 292
The Contractor shall provide planning assistance for disassembly, packing, transport, 293 delivery, and reassembly of Mission Unique Equipment. The Contractor shall provide 294 all labor, tools, material, parts, supplies, components, equipment, transportation, 295 supervision, and management necessary to execute the movement of approximately 296
1,500 equipment items within the prescribed time. The attached list of Mission Unique 297
Equipment (Attachment 1 of PWS) identifies equipment that will be relocated via 298 orders under this contract. The Government may add additional equipment. Equipment 299 or materials not specifically listed herein may or may not be relocated under this 300 contract. 301
2.4 Contractor Job Site Clean Up 303
At the end of each week and upon completion of the project, the Contractor shall clean-305 up/remove any trash or debris and restore walls, floors/carpet, paint, ceiling tiles, doors, 306 and door frames to a condition indistinguishable from similar nearby areas. Protective 307 material may be left in place with prior approval from the N2W Deployment Team. 308
Un
2.5 Workforce Requirements 311
Background Checks/Records. Prior to engaging in any services identified herein, the 312
Contractor shall ensure a background check is conducted (at Contractor expense), in 313 accordance with industry standards, for all persons performing under this contract whose 314 role involves interacting with a Government employee and/or presence on a Government 315 facility. 316
The Contractor shall provide birth names, to include middle name, and visitor access 318 request information ten (10) business days prior to each NGA facility visit, to include for 319 pre-move and increment move weeks. 320
The Contractor workforce shall have a standard uniform that allows easy identification by 322
Government employees. The Contractor shall prevent their personnel from entering any 323 area other than the designated project areas for that day and remain within view of 324 designated security escorts. 325
The Contractor shall ensure all persons interacting with Government employees under 327 this contract meet the specific requirements for Government installation escorted access 328 as listed in DoD Manual 5200.08 (see https://www.esd.whs.mil). The Contractor shall 329 ensure all employees remain trained and qualified in their assigned duties. English shall 330 be the only language used with regard to this contract for written correspondence, 331 discussions, and other business transactions. Smoking is prohibited on a Government 332 facility during all phases of movement. 333
The Contractor shall ensure all persons, vehicles, and equipment under this contract 334 meet the specific prohibited items requirements in NGAI 5210.8 (provided by the 335
Government). 336
3. PERFORMANCE OBJECTIVES 338
3.1 Support Planning Phase 339
The support planning phase starts in the fall of 2024 and lasts until pre-move moves 340 begin. In addition to the meetings described in Section 1.8, the Contractor shall 341 determine scheduling, staffing, resources, and timeline to support execution of the N2W 342
Deployment Execution Plan. The Contractor shall deliver a Support Plan and Schedule 343 for accomplishment of the N2W Deployment Execution Plan. During implementation, 344 the Contractor shall provide weekly updates to this information. At a minimum, the 345
Support Plan and Schedule will include the following: 346
• Staffing schedule with number and role of Contractor personnel required at 347 the Government facility each day 348
• Type, quantity, and vehicle utilization plan at a Government facility each day 349
• Crate circulation management plan detailing number of crates in circulation 350 each week, distribution schedule, and collection of emptied crates schedule 351
• Packing and equipment handling plan for all Mission Unique Equipment 352 moving requirements 353
Un
• Inventory Tracking Plan with inventory tracking equipment details and 354 utilization description 355
• Load calculations and timing predictions 356
• Internal building route review with N2W Deployment Team 357
• Packing directions and restrictions for employees 358
• Communication plan and equipment description for truck and trailer tracking 359
• Feedback on N2W Deployment Execution Plan 360
• Methods and materials used to protect floors, walls, corners, elevators, doors, 361 and furniture within NGA buildings 362
The Support Plan and Schedule shall be delivered in three parts. 363
Part 1: 364
• Spend two days minimum on site to collect information on Mission Unique 365
Equipment, all three site locations and the various buildings. 366
• Rough order of magnitude estimates for staffing schedule, load calculations and 367 move timeline, crate circulation management plan, Mission Unique Equipment 368 packing and equipment handling plan, inventory tracking plan, vehicle 369 utilization plan, and actions to protect NGA buildings. 370
• Provide general comments on packing directions and restrictions, feedback on 371
N2W Deployment Execution Plan, and internal building moving routes. 372
• Provide intended format of all required reports to gain initial government 373 feedback. 374
Part 2: 375
• Provide definitive estimates for staffing schedule, load calculations and move 376 timeline, crate circulation management plan, Mission Unique Equipment 377 packing and equipment handling plan, inventory tracking plan, vehicle 378 utilization plan, and actions to protect NGA buildings. 379
• Provide specific packing directions and restrictions to distribute to Government 380 employees 381
• Provide sample of four packing crates, dolly, non-releasable security ties in 382 green and red, tamper-evident tape, bolt seal or padlock used as the truck seal 383 and proposed packing material. 384
• Provide demonstration of inventory and vehicle tracking equipment and method 385 available for Government to get in-progress information. 386
Part 3: 387
• Provide any updates to estimates for staffing schedule, load calculations and 388 move timeline, crate circulation management plan, Mission Unique Equipment 389 packing and equipment handling plan, inventory tracking plan, vehicle 390
Un utilization plan, and actions to protect NGA buildings. 391
• Provide a comprehensive written Quality Control Plan 392
• Provide demonstration of installation of protective material for floors, walls, 393 corners, elevators, doors, and furniture along planned movement route. 394
3.2 Pre-move Phase 396
The pre-move phase is to relocate NGA support personnel who provide security, 397 facility management, and information technology capabilities. The pre-moves will 398 consist of several one-day moves plus possible multiple-day moves for the library, 399 survey and gravity measuring equipment. 400
At least ten (10) business days prior to any move the contractor will provide the Visitor 401
Access Request (VAR). At least ten (10) business days before a pre-move, the 402
Contractor will deliver up to four (4) packing crates per employee moving in that 403 particular pre-move. The Contractor shall provide adequate packing material, security 404 ties, and tamper evident tape for each packing crate. The Contractor shall provide a 405 crate dolly for at least every four (4) packing crates. Government employees will pack 406 their own official material at their workstation into packing crates, label them with their 407 new N2W workstation number, and seal each crate. The Contractor will not be held 408 responsible for damage to items inside sealed crates packed by Government employees. 409
The Contractor will be responsible for ensuring each crate is tracked and delivered to an 410 employee’s new N2W workstation location. The Contractor will be responsible for 411 ensuring crates are delivered intact and remain sealed. The Contractor will not move 412 any crate that is not properly sealed with security ties and tamper evident tape. If a crate 413 is discovered to not be sealed or becomes unsealed during the move transition, the 414
Contractor shall notify in-person and follow the directions of the N2W Deployment 415
Team to secure the crate. Contractor will be responsible to keep metrics of the number 416 of unsealed crates and include in daily and weekly inventory reports. 417
The Contractor is responsible for collecting packing crates from designated areas at 2nd 418
Street and Arnold locations, moving them to N2W, and placing them at the employee’s 419 new N2W workstation location. Government employees will be responsible for packing 420 and moving their own personal items. The Contractor is not responsible for and shall 421 not move Government employees’ personal (non-work related) items. 422
The Contractor is responsible for disassembling, packing, transporting, delivering, and 423 reassembling Mission Unique Equipment. 424
The Contractor shall collect and dispose of used and/or excess packing material from 425 completed moves. The Contractor shall collect used packing crates at N2W and 426 transport empty crates to the Government directed location. Packing crates shall be 427 replaced and cleaned as needed. 428
The timelines/tasks detailed below should be considered firm; however, are subject to 429 change if Government mission requirements necessitate. 430
Pre-move #1 432
Un
Approximately 20 crates 433
15 Mission Unique Equipment items 434
Crates and equipment items shall be moved from 2nd Street to N2W. 435
Pre-move #2 436
Approximately 20 crates 437
15 Mission Unique Equipment items 438
Crates and equipment items shall be moved from Arnold to N2W. 439
Pre-move #3: Library 440
Approximately 200 crates 441
10 Mission Unique Equipment items 442
Crates and equipment items shall be moved from 2nd Street to N2W. 443
Pre-move #4: Survey Equipment 444
Approximately 20 crates 445
400 Mission Unique Equipment items 446
Crates and equipment items shall be moved from 2nd Street to N2W and placed in 447 designated storage location. Contractor shall remove equipment from current shelving 448 racks, pack or palletize as needed, transport, and then unpack and place on new 449 shelving racks. Shelving racks are as high as 12 feet. Contractor shall provide qualified 450 personnel to operate and maintain material handling equipment, such as a forklift, to 451 move/place equipment as needed. 452
3.3 Increment Moves Phase 454
The N2W Deployment Execution Plan increment move sequence is broken down into 455 twelve (12) weeks over a sixteen (16) week period, with each week designated as an 456 increment. Each increment is anticipated to move official material in approximately 457
800-1600 packing crates and potentially some additional Mission Unique Equipment. 458
At least ten (10) business days prior to any move the contractor will provide the Visitor 459
Access Request (VAR). At least ten (10) business days before an increment move, the 460
Contractor will deliver up to four (4) packing crates per employee moving in the 461 increment. The Government will notify the Contractor of the exact number of crates 462 needed for the increment. The Contractor shall provide adequate packing material, 463 security ties, and tamper evident tape for each packing crate. The Contractor shall 464 provide a crate dolly for at least every four (4) packing crates. Government employees 465 will pack their own official material at their workstation into packing crates, label them 466 with their new N2W workstation number, and seal each crate. The Contractor will not 467 be held responsible for damage to items inside sealed crates packed by Government 468 employees. The Contractor will be responsible for ensuring each crate is tracked and 469 delivered to an employee’s new N2W workstation location. The Contractor will be 470 responsible for ensuring crates are delivered intact and remain sealed. The Contractor 471
Un will not move any crate that is not properly sealed with security ties and tamper evident 472 tape. If a crate is discovered to not be sealed or becomes unsealed during the move 473 transition, the Contractor shall notify in-person and follow the directions of the N2W 474
Deployment Team to secure the crate. Contractor will be responsible to keep metrics of 475 the number of unsealed crates and include in daily and weekly inventory reports. 476
The Contractor is responsible for collecting packing crates from designated areas at 2nd 477
Street and Arnold locations, moving them to N2W, and placing them at the employee’s 478 new N2W workstation location. Government employees will be responsible to pack and 479 move their own personal items. The Contractor is not responsible for and shall not 480 move Government employees’ personal (non-work related) items. 481
The Contractor is responsible for disassembling, packing, transporting, delivering, and 482 reassembling Mission Unique Equipment. 483
The Contractor shall collect and dispose of used and/or excess packing material from 484 completed moves. The Contractor shall collect used packing crates at N2W and 485 transport empty crates to the Government directed location. Packing crates shall be 486 replaced and cleaned as needed. 487
The timelines/tasks detailed below should be considered firm; however, are subject to 488 change if Government mission requirements necessitate. 489
Example of an increment week schedule: 490
Monday: Install protective material for floors, walls, corners, elevators, doors, and 491 furniture along planned movement route. 492
Tuesday: Movement of XXX crates from 2nd Street to N2W. 493
Wednesday: Movement of XX Mission Unique Equipment items from 2nd Street to 494
N2W. 495
Thursday: Movement of approximately XXX crates from 2nd Street to N2W. 496
Friday: Collect unpacked crates and re-distribute for ensuing increment move. Remove 497 protective material from floors, walls, corners, elevators, doors, and furniture. 498
Protective material may be left in place with prior approval from the N2W Deployment 499
Team. 500
Example of individual increment week quantities: 501
Increment #1 Week: 502
Approximately 750 crates 503
30 Mission Unique Equipment items 504
Crates and equipment items shall be moved from 2nd Street and Arnold to N2W. 505
Increment #2 Week: 506
Approximately 850 crates 507
30Mission Unique Equipment items 508
Crates and equipment items shall be moved from 2nd Street to N2W. 509
Un
Increment #3 Week: 510
Approximately 750 crates 511
30 Mission Unique Equipment items 512
Crates and equipment items shall be moved from 2nd Street to N2W. 513
Increment #4 Week: 514
Approximately 1000 crates 515
30 Mission Unique Equipment items 516
Crates and equipment items shall be moved from both 2nd Street and Arnold to N2W. 517
Increment #5 Week: 518
Approximately 1150 crates 519
30 Mission Unique Equipment items 520
Crates and equipment items shall be moved from 2nd Street to N2W. 521
Increment #6 Week: 522
Approximately 1700 crates 523
30 Mission Unique Equipment items 524
Crates and equipment items shall be moved from 2nd Street to N2W. 525
Increment #7 Week: 526
Approximately 950 crates 527
30 Mission Unique Equipment items 528
Crates and equipment items shall be moved from 2nd Street to N2W. 529
Increment #8 Week: 530
Approximately 1150 crates 531
30 Mission Unique Equipment items 532
Crates and equipment items shall be moved from 2nd Street to N2W. 533
Increment #9 Week: 534
Approximately 500 crates 535
30 Mission Unique Equipment items 536
Crates and equipment items shall be moved from 2nd Street to N2W. 537
Increment #10 Week: 538
Approximately 1600 crates 539
30 Mission Unique Equipment items 540
Crates and equipment items shall be moved from 2nd Street to N2W. 541
Increment #11 Week: 542
Un
Approximately 800 crates 543
30 Mission Unique Equipment items 544
Crates and equipment items shall be moved from 2nd Street to N2W. 545
Increment #12 Week: 546
Approximately 500 crates 547
0 Mission Unique Equipment items 548
Crates and equipment items shall be moved from 2nd Street to N2W. 549
3.4 Crew Requirements 551
General Crew Requirements: 552
The Contractor shall provide a supervisor for its employees (and sub-contracted employees) any 553 time work is being performed at any NGA location (St. Louis, Arnold, N2W). The crew will be 554 adequately sized to complete all tasks on the day scheduled for each specific task. The crew 555 should remain the same throughout the performance of an increment move. 556
Project Manager: 558
Responsible for managing the overall moving services project and is primary point of contact for 559 the Government. Minimum 8 years’ experience in commercial moving industry with at least 5 560 years’ experience at a management or supervisory level. Minimum education level of Bachelor’s 561
Degree or 4 years’ project management experience. 562
Supervisor: 564
Responsible for commercial moving team at a Government facility and coordinating moving 565 services with Government. Minimum 5 years’ experience in commercial moving industry with at 566 least 2 years’ experience at a management or supervisory level. Minimum education level of 567
High School Diploma or high school equivalent. 568
Key Positions: 570
The Project Manager and Supervisors shall be key positions. Resumes for key positions shall be 571 submitted to the COR/ACOR for review and approval. Resumes will be submitted no later than 572 ten business days prior to conducting work on this contract. 573
4. SECURITY INFORMATION 575
Unclassified Work Performance Security Requirements 577
Uncleared Contractor personnel are authorized to work on this contract at the 578
Unclassified level, with access up to DoD Controlled Unclassified Information 579
(CUI) at the Contractor site without the requirement of a security clearance. 580
Uncleared Personnel Security Requirements 582
Any Contractor personnel working with CUI information must receive a favorable 583
HSPD-12 and/or HSPD-12 Tier 1 adjudication prior to accessing CUI information. 584
Contractor personnel who require access to CUI for 60 days or less must receive 585
Un a favorable HSPD-12 adjudication. Contractor personnel who require CUI access 586 for more than 60 days must receive a favorable HSPD-12 Tier 1 adjudication. 587
NGA will sponsor the HSPD-12 and HSPD-12 Tier 1 background investigation for 588
Contractor personnel as needed. 589
Foreign nationals are not permitted to perform unclassified work under the terms 590 of this contract without prior written approval from the Contracting Officer (CO) or 591 the COR. Should NGA identify the use of unauthorized personnel, the CO may 592 direct the Contractor, at its own expense, to remove and replace any 593 unauthorized Contractors, Subcontractors, or other personnel performing on the 594 contract. Such action may be taken at the NGA's discretion without prejudice to 595 its rights under any other contract provision, e.g., termination for default. 596
Uncleared Contractor personnel visiting NGA facilities or other sites may receive 597 the appropriate visitor badge and be escorted, as appropriate. The Contractor will 598 return the visitor badge at the end of each visit day. 599
Physical Security Requirements 601
Contractor personnel are forbidden from bringing prohibited or unauthorized 602 items into any NGA installation or Sensitive Compartmented Information facility covered under this 603 contract. These items include weapons, cell phones, cameras, two-way pagers, 604 laptops, recording devices of any kind, flash drives, or any other removable 605 media. Exceptions may be granted by NGA Security upon the Contractor’s 606 request. If granted, Contractor personnel must bring documentation showing 607 approval prior to entering with the item(s). Violations may subject the Contractor 608 and its offending personnel to civil and/or criminal liability IAW applicable laws 609 and regulations governing access to Sensitive Compartment Information facilities. 610
Information Security Requirements 612
NGA shall have the sole authority to determine whether, and to what extent, 613 protected information shall be provided to the Contractor under the terms of the 614 contract. The Contractor shall not access, download, print, or further disseminate 615 any unclassified information outside the execution of the defined contract 616 requirements without the guidance and written permission from the COR. 617
When the Contractor receives protected information under the terms of this 619 contract, the Contractor will comply with all applicable NGA, DoD, and IC 620 information security policies for the proper marking, handling, processing, storing, 621 and safeguarding of unclassified and CUI material. The Contractor will ensure 622 that document markings are given the lowest possible security classification to 623 maximize dissemination while still maintaining the information’s confidentiality 624 and integrity as necessary. 625
Access to CUI will be pursuant to DFARS clause 252.204.7012. The prime 627 contractor shall include this clause, including paragraph (m), in subcontracts, or 628 similar contractual instruments, for operationally critical support or for which 629 subcontract performance will involve covered defense information, including 630 subcontracts for commercial items, without alteration, except to identify the 631
Un parties. The Contractor shall determine if the information required for 632
Subcontractor performance retains its identity as covered defense information 633 and will require protection under this clause. Contractor personnel shall not 634 release any unclassified information, regardless of medium (e.g., film, tape, 635 document), pertaining to any part of this contract or any program related to this 636 contract, unless the COR has given prior written approval or in performance of a 637 project that has been scoped and negotiated by NGA. 638
NGA will assess and authorize Contractors to process unclassified information 640 on government-owned information systems, conduct oversight of such 641 information system processing, and provide information system security 642 guidelines IAW with FAR clause 52.204-21 and other information system security 643 control policies, standards, and procedures. Contractor will be responsible for 644 executing specific provisions under the contract for the accreditation of classified 645 information systems, and upon request, shall provide the COR a written 646 statement confirming accreditation compliance with the minimum information 647 systems requirements established in the DD254. The Contractor shall include the 648 substance of FAR clause 52.204-21 in subcontracts under this contract (including 649 subcontracts for the acquisition of commercial products or commercial services, 650 other than commercially available off-the-shelf items), in which the Subcontractor 651 may have federal contract information residing in or transiting through its 652 information system. 653
In accordance with FAR Part 4.7 and FAR clause 52.215-2, the Contractor may 655 retain one archival copy of any Government-furnished information provided to the 656
Contractor during the course of performance of the contract, subject to Contractor following relevant 657 data safeguarding practices and CUI restrictions. The disposition of such Government-furnished 658 information is otherwise solely at the discretion of the Government. As directed by the NGA CO or 659
COR, the Contractor will destroy or return to NGA all Government-furnished information upon contract 660 termination or when no longer required for contract performance. 661
Cybersecurity Requirements 663
The Contractor must, at a minimum, implement 10 U.S.C. Sections 391 and 393 664 along with National Institute of Standards and Technology (NIST) Special 665
Publication (SP) 800-171, “Protecting Controlled Unclassified Information in 666
Nonfederal Information Systems and Organizations” requirements. 667
If the Contractor intends to use an external cloud service provider to store, 669 process, or transmit any covered defense information in performance of this 670 contract, the Contractor shall require and ensure that the cloud service provider 671 meets security requirements equivalent to those established by the Government 672 for the Federal Risk and Authorization Management Program (FedRAMP) 673
Moderate baseline (https://www.fedramp.gov/resources/documents/) 674
In the event that the Contractor discovers a cyber incident that affects a covered 676
Contractor information system or covered defense information residing therein, or 677 https://www.fedramp.gov/resources/documents/
Un that affects the Contractor’s ability to perform the requirements of the contract that 678 are designated as operationally critical support and identified in the contract, the 679
Contractor shall— 680
1. Notify the DoD Cyber Crime Center (DC3) and the COR in writing within 72 682 hours of incident discovery 683
2. Conduct a review for evidence of compromise of covered defense information, 685 including, but not limited to, identifying compromised computers, servers, 686 specific data, and user accounts. This review shall also include analyzing 687 covered Contractor information system(s) that were part of the cyber incident, 688 as well as other information systems on the Contractor’s network(s), that may 689 have been accessed as a result of the incident in order to identify compromised 690 covered defense information, or that affect the Contractor’s ability to provide 691 operationally critical support. 692
In the event the Contractor discovers and isolates malicious software in 694 connection with a reported cyber incident, the Contractor shall submit the 695 malicious software to DC3 in accordance with instructions provided by the COR. 696
The Contractor should NOT send the malicious software to the COR. 697
5. LIST OF ATTACHMENTS 700
Attachment 1 – List of Mission Unique Equipment 701
Attachment 2 – Deliverables Schedule 702
Attachment 3 – Compliant Document List 703
Un
Attachment 1 – List of Mission Unique Equipment 705
See Attachment 1 of the PWS. The attachment represents a list of up to 1500 Mission Unique 707
Equipment items that may require disassembly, packing, transport, delivery, and reassembly. 708
Un
Attachment 2 – Deliverables Schedule 711
Deliverable
PWS
Task #
Deliverable Title Frequency and Remarks Delivered To
001 1.7 Quality Control Plan Within 5 business days when updated
COR/APM
002 2.2 Inventory Reports End of Day during Pre-move and Increment
Moves / Upon request
APM
003 3.1 Support Plan and Schedule Part 1 due 12/9/2024, Part
2 due 2/3/2025, Part 3 due
4/7/2025 / When Updated
COR/APM
004 3.1 Weekly Support Schedule
Updates
Weekly during Pre-move and Increment Moves
COR/APM
005 Financial Report Monthly COR
006 2.5 Visitor Access Request No later than ten business days prior to NGA facility visit
NGA
Security/APM
Note: All deliverable formats shall be Contractor proposed and Government approved. 713
Un
Attachment 3 – Compliant Document List 727
References: 729
1. DoD Manual 5200.08 Physical Security Program 730