Attachment 10 - Responses to Industry not provided in Attachment 9 - Amend6.pdf

PDF 19 KB Posted

Attached to
HE1280-11-R-0001 Mediterranean School Maintenance Program (MSMP)
Solicitation number
he1280-11-r-0001
Issued by

About this file

Attachment 10 - Responses to Industry not provided in Attachment 9 - Amend6

View the file

Other files

File Type Posted
Exhibit R - Non-Routine Pricing Spreadsheets Amend6.xlsx XLSX spreadsheet
HE1280-11-R-0001 Amendment 0006.pdf PDF
Exhibit H - Installed Equipment Summary.pdf PDF
Exhibit R - Non-Routine Pricing Spreadsheets Amend5.xlsx XLSX spreadsheet
HE1280-11-R-0001 Amendment 0005.pdf PDF
HE1280-11-R-0001 Amendment 0004.pdf PDF
Attachment 9 - Responses to Questions-Comments from Industry - Final Solicitation.pdf PDF
HE1280-11-R-0001 Amendment 0003.pdf PDF
Exhibit R - Non-Routine Pricing Spreadsheets Amend3.xlsx XLSX spreadsheet
HE1280-11-R-0001 Amendment 0002.pdf PDF
HE1280-11-R-0001-0001_Amend__MSMP.pdf PDF
Exhibit E1 - Aviano EMHS.pdf PDF
Exhibit H - Installed Equipment Summary.pdf PDF
Exhibit Q2 - Livorno Facility Utilization Survey Data Plans.pdf PDF
Exhibit F1 - Q Ratings.pdf PDF
Exhibit F2 - Italy Facility Report.pdf PDF
Attachment 3 - MSMP Past Performance Certification.docx DOCX document
Exhibit U - Historical Routine Services.pdf PDF
Exhibit A - Med District Regional Maps.pdf PDF
Exhibit P - Elementary School Education Specifications.pdf PDF
Exhibit Q4 - Sigonella Facility Utilization Survey Data Plans.pdf PDF
Exhibit E8 - Mediterranean DSO.pdf PDF
Exhibit N - SchoolDude WorkOrderProcess.pdf PDF
Exhibit Q1 - Aviano Facility Utilization Survey Data Plans.pdf PDF
Attachment 2 - PAST_PERFORMANCE_QUESTIONNAIRE.doc DOC document
ATTACHMENT 4B - SF 1035 Continuation Sheet.pdf PDF
Exhibit L - Occupancy Data 2010.pdf PDF
Exhibit C - Official School Addresses.pdf PDF
Attachment 8 - MSMP PreProposal Conference Slides.pdf PDF
Exhibit K - DoDDS School Calendar 10-11 and 11-12.pdf PDF
Exhibit F3 - Spain Facility Report.pdf PDF
Attachment 1 - Seed Project.pdf PDF
Exhibit Q8 - Med DSO Facility Utilization Survey Data Plans.pdf PDF
Attachment 6 - Responses to Questions-Comments from Industry 1st Draft Solicitation.pdf PDF
Exhibit E4 - Sigonella ESMSHS.pdf PDF
HE1280-11-R-0001 FINAL.pdf PDF
ATTACHMENT 4A - SF 1034 Public Voucher.pdf PDF
Exhibit T - Historical Non-Routine Financial Data.pdf PDF
Exhibit Q5 - Rota Facility Utilization Survey Data Plans.pdf PDF
Exhibit E3 - Livorno EMS.pdf PDF
Exhibit B - Driving Directions.pdf PDF
Exhibit R - Non-Routine Pricing Spreadsheets Final.xlsx XLSX spreadsheet
Exhibit J - Project Workload Other than Routine Services.pdf PDF
Exhibit Q6 - Seville Facility Utilization Survey Data Plans.pdf PDF
Exhibit Q3 Vicenza Facility Utilization Survey Data Plans.pdf PDF
Exhibit F4 - Portugal Facility Report.pdf PDF
Exhibit D - Med District Areas.pdf PDF
Attachment 5 - Quality Assurance Surveillance Plan.pdf PDF
Exhibit M - Government Furnished Facilities.pdf PDF
Cover Letter HE1280-11-R-0001 Final Solicitation.pdf PDF
Show 40 more

Latest 50 of 59 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 10 – Responses to Questions-Comments from Industry Final Solicitation Amendment 0006

1) Reference: Attachment 7, Government’s Response to GENERAL 3, General Comment (See Item 4)

Discussion: The Government’s answer to Item 4 that “It is the contractor’s responsibility to comply with local laws” is not a proper response to the question asked. The contractor (offeror) cannot provide a proper offer that is in compliance with local laws unless the Acquired Rights information discussed in Question 4, Attachment 7 and Question 5, Attachment 7 is provided to the contractor sufficiently in advance of the time that an offer is due. Since only the incumbent(s) has (have) this information and thus is (are) able to comply, the solicitation is potentially biased unless all possible offerors are provided the information or the solicitation provides for an equitable adjustment for additional labor costs that may result after award if the successful offeror must hire incumbent personnel with salary and benefits above those calculated in the successful offeror’s price proposal.

Question: Please provide the required Acquired Rights information for all incumbent personnel who may be required to be taken over by a successor contractor. If the answer is none, please so state in the solicitation.

RESPONSE: The Government does not have in its possession nor does it have access to any employment information for employees who currently provide the services required in this solicitation. Offerors are reminded that DFARS Clause 252.222-7022 entitled “Compliance with Local Labor Laws (Overseas) is included in this solicitation.

2) Question: In all services the common question is about TUPE costs. As we have no information about that, should we assume there is not TUPE to be transferred? If awarded the contract we would need to increase our proposal by the value of actual TUPE costs?

RESPONSE: See response to Question 1.