ASTM_E1417__E1417M_Standard_Practice_for_Liquid_Penetrant_Testing_.pdf
PDF 176 KB Posted
- Attached to
- Suppress Upper Receiver Group Federal contract opportunity
- Solicitation number
- H92222-17-R-0011
- Issued by
- United States Special Operations Command
About this file
ASTM E1417 E1417M_Standard Practice for Liquid Penetrant Testing_
View the file
Other files for this federal contract opportunity
Show all 36
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Designation: E1417/E1417M − 13
Standard Practice for Liquid Penetrant Testing1
This standard is issued under the fixed designation E1417/E1417M; the number immediately following the designation indicates the year of original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval.
A superscript epsilon (´) indicates an editorial change since the last revision or reapproval.
This standard has been approved for use by agencies of the U.S. Department of Defense.
1. Scope*
1.1 This practice establishes the minimum requirements for
conducting liquid penetrant examination of nonporous metal, and nonmetal components.
NOTE 1—This practice replaces MIL-STD-6866.
1.2 The penetrant examination processes described in this
practice are applicable to in-process, final, and maintenance (in-service) examinations. These processes are applicable for the detection of discontinuities, such as lack of fusion, corrosion, cracks, laps, cold shuts, and porosity, that are open or connected to the surface of the component under examina-tion.
1.3 Caution must be exercised in the usage of elevated
temperature with components manufactured from thermoplas-tic materials. Also, some cleaners, penetrants, and developers can have a deleterious effect on nonmetallic materials such as plastics. Prior to examination, tests should be conducted to ensure that none of the cleaning or examination materials are harmful to the components to be examined.
1.4 Units—The values stated in either SI units or inch-
pound units are to be regarded separately as standard. The values stated in each system may not be exact equivalents;
therefore, each system shall be used independently of the other.
Combining values from the two systems may result in non-conformance with the standard.
1.5 All areas of this practice may be open to agreement
between the cognizant engineering organization and the supplier, or specific direction from the cognizant engineering organization.
1.6 This standard does not purport to address all of the
safety concerns, if any, associated with its use. It is the responsibility of the user of this standard to establish appro-priate safety and health practices and determine the applica-bility of regulatory limitations prior to use.
2. Referenced Documents
2.1 The following documents form a part of this practice to
the extent specified herein:
2.2 ASTM Standards:2
D95 Test Method for Water in Petroleum Products and Bituminous Materials by Distillation
D2512 Test Method for Compatibility of Materials with Liquid Oxygen (Impact Sensitivity Threshold and Pass- Fail Techniques)
D6304 Test Method for Determination of Water in Petro-leum Products, Lubricating Oils, and Additives by Cou-lometric Karl Fischer Titration
E165 Practice for Liquid Penetrant Examination for General Industry
E543 Specification for Agencies Performing Nondestructive Testing
E1135 Test Method for Comparing the Brightness of Fluo-rescent Penetrants
E1316 Terminology for Nondestructive Examinations E2297 Guide for Use of UV-A and Visible Light Sources and
Meters used in the Liquid Penetrant and Magnetic Particle Methods
2.3 ASNT Standards:3
ANSI/ASNT-CP-189 Standard for Qualification and Certifi-cation of Nondestructive Testing Personnel
SNT-TC-1A Recommended Practice for Personnel Qualifi-cation and Certification in Nondestructive Testing
2.4 Military Standards:4, 5
MIL-STD-792 Identification Marking Requirements for Special Purpose Components
1 This practice is under the jurisdiction of ASTM Committee E07 on Nonde-structive Testing and is the direct responsibility of Subcommittee E07.03 on Liquid Penetrant and Magnetic Particle Methods.
Current edition approved June 1, 2013. Published June 2013. Originally approved in 1991. Last previous edition approved in 2011 as E1417/E1417M – 11ε1.
DOI: 10.1520/E1417_E1417M-13.
2 For referenced ASTM standards, visit the ASTM website, www.astm.org, or contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM Standards volume information, refer to the standard’s Document Summary page on the ASTM website.
3 Available from American Society for Nondestructive Testing (ASNT), P.O. Box 28518, 1711 Arlingate Ln., Columbus, OH 43228-0518, http://www.asnt.org.
4 Copies of specifications, standards, drawings, and publications required by manufacturers in connection with specific acquisition functions should be obtained from the contracting activity or as directed by the contracting officer.
5 Available from Standardization Documents Order Desk, DODSSP, Bldg. 4, Section D, 700 Robbins Ave., Philadelphia, PA 19111-5098, http:// dodssp.daps.dla.mil.
*A Summary of Changes section appears at the end of this standard
Copyright © ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States
1Copyright ASTM International Provided by IHS under license with ASTM Licensee=NSWC Crane/9963650103, User=Lax, Philip
Not for Resale, 07/01/2016 09:01:59 MDTNo reproduction or networking permitted without license from IHS
QPL-AMS-2644 Qualified Products List, Inspection Material, Penetrant
MIL-STD-45662 Calibration System Requirements
2.5 ANSI/ISO/AIA Standards:6
ANSI/NCSL Z540-1 General Requirement for Calibration Laboratories and Measuring Test Equipment
ISO 10012 Measurement Management Systems— Requirements for Measuring Measurement Process and Measuring Equipment
NAS 410 Certification and Qualification of Nondestructive Test Personnel
2.6 SAE Standard:7
AMS 2644 Inspection Material, Penetrant AMS 2175A Castings, Classification and Inspection of
2.7 DoD Contracts—Unless otherwise specified, the issues
of the documents that are DoD adopted are those listed in the issue of the DoDISS (Department of Defense Index of Speci-fications and Standards) cited in the solicitation.
2.8 Order of Precedence—In the event of conflict between
the text of this practice and the references cited herein, the text of this practice takes precedence.
3. Terminology
3.1 Definitions:
3.1.1 The terminology relating to liquid penetrant examina-
tion that appears in Terminology E1316 shall apply to the terms used in this practice.
3.2 Definitions of Terms Specific to This Standard:
3.2.1 aerospace—any component that will be installed on a system that flies.
3.2.2 cognizant engineering organization (CEO)— Reference Terminology Standard E1316.
3.2.3 component—the part(s) or element(s) of a system described, assembled, or processed to the extent specified by the drawing.
3.2.4 final examination—the final examination performed for the acceptance of the item. Any change to the item’s surface such as machining, grinding, welding, heat treatment, or etching by subsequent manufacturing operation, may render the previous examination invalid, requiring reexamination of all affected surfaces, unless otherwise approved in the contract.
3.2.5 in-process—that which occurs during manufacturing before a component is in final form.
3.2.6 in-service—refers to components that are in use or storage for their intended function.
3.2.7 linear indication—penetrant indications with at least a three to one length to width ratio.
3.2.8 reprocess—repeat, after cleaning, the application and appropriate processing of penetrant, emulsifier (as required), and developer (as required).
3.2.9 rounded indication—penetrant indication whose length to width ratio is less than three-to-one.
3.2.10 supplier—the organization contracted to supply the material, parts, or assembly.
3.2.11 turbine engine critical components—any component on turbine engine designated by the manufacturer as “critical.”
4. Significance and Use
4.1 This practice establishes the basic parameters for con-
trolling the application of the liquid penetrant method. This practice is written so it can be specified on the engineering drawing, specification, or contract. It is not a detailed how-to procedure to be used by the inspector and, therefore, must be supplemented by a detailed procedure that conforms to the requirements of this practice. Specification E165 contains information to help develop detailed requirements.
5. Classification
5.1 Penetrant examination processes and materials are clas-
sified in accordance with the material classification contained in AMS 2644. Penetrant systems covered by this practice shall be of the following types, methods, and sensitivity levels:
5.1.1 Type:
5.1.1.1 Type I—Fluorescent dye.
5.1.1.2 Type II—Visible dye.
5.1.2 Method:
5.1.2.1 Method A—Water washable.
5.1.2.2 Method B—Post-emulsifiable, lipophilic.
5.1.2.3 Method C—Solvent-removable.
5.1.2.4 Method D—Post-emulsifiable, hydrophilic.
5.1.3 Sensitivity—(These levels apply to Type I penetrant
systems only. Type II penetrant systems have only a single sensitivity and it is not represented by any of the levels listed as follows):
5.1.3.1 Sensitivity Level 1⁄2 —Very low.
5.1.3.2 Sensitivity Level 1—Low.
5.1.3.3 Sensitivity Level 2—Medium.
5.1.3.4 Sensitivity Level 3—High.
5.1.3.5 Sensitivity Level 4—Ultrahigh.
5.2 Developers shall be of the following forms:
5.2.1 Form a—Dry powder.
5.2.2 Form b—Water-soluble.
5.2.3 Form c—Water-suspendable.
5.2.4 Form d—Nonaqueous for Type I fluorescent pen-
etrant.
5.2.5 Form e—Nonaqueous for Type II visible dye.
5.2.6 Form f——Specific application.
5.3 Solvent removers shall be of the following classes:
5.3.1 Class 1—Halogenated.
5.3.2 Class 2—Nonhalogenated.
5.3.3 Class 3—Specific application.
6. General Practices
6.1 Responsibility for Examination—Unless otherwise
specified in the contract or purchase order, the cognizant engineering organization is responsible for the performance of all examination requirements as specified herein. The cogni-zant engineering organization may specify more stringent
6 Available from American National Standards Institute (ANSI), 25 W. 43rd St., 4th Floor, New York, NY 10036, http://www.ansi.org.
7 Available from SAE International (SAE), 400 Commonwealth Dr., Warrendale, PA 15096-0001, http://www.sae.org.
E1417/E1417M − 13
2Copyright ASTM International Provided by IHS under license with ASTM Licensee=NSWC Crane/9963650103, User=Lax, Philip
Not for Resale, 07/01/2016 09:01:59 MDTNo reproduction or networking permitted without license from IHS requirements than the minimum specified in this practice when necessary to ensure that a component meets its functional and reliability requirements. Except as otherwise specified, the supplier may utilize his own facilities or any other facilities suitable for the performance of the examination requirements specified herein. The purchaser reserves the right to perform any of the examinations set forth in this practice where such examinations are deemed necessary to ensure that supplies and services conform to prescribed requirements.
6.2 Specifying—When examination is required in accor-
dance with this practice the orders, contracts, or other appro-priate documents shall specify the criteria by which the acceptability of components is to be evaluated. Engineering drawings or other applicable documents shall indicate the acceptance criteria for the entire component; zoning may be used. Examination on a sampling basis shall not be allowed unless specifically permitted by the contract.
6.3 Personnel Qualification—Personnel performing exami-
nations to this practice shall be qualified and certified in accordance with ASNT Personnel Qualification SNT-TC-1A, ANSI/ASNT-CP-189 or NAS 410 for military purposes, or as specified in the contract or purchase order.
6.4 Agency Qualification—The agency performing this
practice may be evaluated in accordance with Specification E543.
6.5 Materials:
6.5.1 Qualified Materials—Only materials listed or ap-
proved for listing on QPL-AMS-2644 (reference AMS 2644) shall be utilized for penetrant examination. Materials not conforming to the requirements of AMS 2644 may be used only when a waiver is obtained from the cognizant engineering organization.
6.5.2 Liquid Oxygen (LOX) Compatible Materials—
Penetrant materials tested in accordance with Test Method D2512 and passing at 70 ft·lbf [95 J] or higher, shall be used on LOX wetted surfaces that cannot be thoroughly post-cleaned.
Use of these materials shall be in accordance with the material supplier instructions and shall require approval of the cogni-zant engineering organization when such materials do not meet the requirements of AMS 2644.
6.6 Equipment and Facilities—Processing equipment used
in the penetrant examination process shall be constructed and arranged to permit a uniform and controlled operation. The equipment shall meet all applicable national and local safety requirements as well as the requirements specified herein.
6.6.1 Viewing Areas—Areas where parts are reviewed shall
be kept clean at all times. For visible dye examination, Type II, the lighting system shall provide at least 100 fc [1076 lx] of visible light when measured at the examination surface. For stationary fluorescent dye examination, Type I, the ambient visible light background shall not exceed 2 fc [21.5 lx] at the examination surface. The black lights shall provide a minimum of 1000 µW/cm2 at the examination surface. Black lights shall meet the requirements of 7.8.4.1. Viewing areas for portable fluorescent dye examination shall utilize dark canvas, photog-rapher’s black cloth, or other methods to reduce the visible light background to the lowest possible level during examina-tion and black light intensity shall meet the above require-ments.
6.6.1.1 Where lamps are physically too large to directly
illuminate the examination surface, special lighting, such as UV pencil lights, or UV light guides, or remote visual examination equipment shall be used. When using a borescope, the image viewed must have sufficient resolution to effectively evaluate the indication. Light intensity shall be measured at the expected working distance and shall be a minimum 1000 µW/cm2.
6.6.2 Drying Oven—When components are oven dried, the
dryer must be a forced-air recirculating type. In automated systems, where parts are dried by radiant heat and forced air, the travel speed of the system shall be such as to preclude overdrying of parts. The forced air does not have to be recirculating but must preclude contamination of the parts. The temperature shall be controlled with a calibrated device ca-pable of maintaining the oven temperature at 615°F [8.3°C] of the temperature for which it is set. The oven shall not exceed 160°F [71°C]. The temperature indicator shall be accurate to 610°F [5.6°C] of the actual oven temperature.
6.7 Written Procedures—All liquid penetrant examination
procedures are similar for many components, a master written procedure may be utilized that covers the details common to a variety of components. All written procedures, including tech-nique sheets for specific parts shall be approved by an individual who is a qualified and certified Level III for penetrant examination in accordance with the requirements of
6.3. As a minimum, the following information is required
either in individual procedures, specific technique sheets, or a master procedure, or a combination thereof:
6.7.1 Details of the precleaning and etching process, includ-ing the materials used and specification or other document controlling the examination process, the drying parameters and the processing times. If these operations are performed by other than examination personnel, details concerning the op-erations may be specified in other documents but must be referenced in the procedure(s). Reference Test Method E165 for detailed cleaning methods and instructions.
6.7.2 Classification of the penetrant examination materials
required in accordance with Section 5 and AMS 2644.
6.7.3 Complete processing parameters for the penetrant
examination materials including concentrations, application methods, dwell times, drying times, temperatures, and controls to prevent excessive drying of penetrant or overheating of component, as appropriate. Reference Practice E165 for addi-tional details.
6.7.4 Complete examination/evaluation requirements in-
cluding light intensities (both examination and ambient), the accept/reject criteria and the method and location of marking.
Reference Practice E165 for additional details.
6.7.4.1 When battery-powered lights are used, define the
frequency for verifying intensity and documentation required.
6.7.4.2 When the examination is performed in accordance
with this Standard Practice, engineering drawings, specifications, technique sheets, or other applicable documents
E1417/E1417M − 13
3Copyright ASTM International Provided by IHS under license with ASTM Licensee=NSWC Crane/9963650103, User=Lax, Philip
Not for Resale, 07/01/2016 09:01:59 MDTNo reproduction or networking permitted without license from IHS shall indicate the accept/reject criteria by which the compo-nents are judged acceptable.
6.7.5 Identification of the components or areas within a
component to be examined in accordance with the procedure.
6.7.6 Complete postcleaning procedures. If postcleaning is
performed by other than examination personnel, details con-cerning this operation may be specified in other documents, but must be referenced in the procedure. Reference Test Method E165 for additional details.
6.8 Examination Sequence—Final penetrant examination
shall be performed after completion of all operations that could cause surface-connected discontinuities or operations that could expose discontinuities not previously open to the surface.
Such operations include, but are not limited to, grinding, welding, straightening, machining, and heat treating.
6.8.1 Surface Treatment—Final penetrant examination may
be performed prior to treatments that can smear the surface but not by themselves cause surface discontinuities. Such treat-ments include, but are not limited to, vapor blasting, deburring, sanding, buffing, sandblasting, lapping, or peening. Perfor-mance of final penetrant examination after such surface treat-ments requires that etching be included in the precleaning operation unless otherwise agreed on between the cognizant engineering organization and the NDT facility.
NOTE 2—Final penetrant examination should always precede peening.
6.8.2 Surface Coatings—All coatings and other surface
conditions, such as, paint, plating, corrosion, etc. shall be removed from the area to be examined prior to penetrant examination. The penetrant examination shall precede any surface finish, such as anodize, except for inservice parts that may be examined without removing the anodize.
6.9 Material and Process Limitations—Not all penetrant
sensitivity levels, materials, and process methods are appli-cable to all examination requirements. The sensitivity level shall be adequate for the intended purpose of the examination.
Unless there is an approval for deviation given by the cogni-zant engineering organization, the following selections are mandatory or forbidden, as indicated:
6.9.1 Forms a and b (dry powder and water soluble)
developers shall not be used with Type II (visible dye) penetrant systems. This is not intended to prohibit the use of a Form f developer that has been qualified with a particular Type II system in accordance with AMS 2644.
6.9.2 Type II penetrant examination shall not be used for
final acceptance examination of aerospace products. In addition, Type II penetrant examination shall not be used prior to a Type I penetrant examination of the same surface. This is not intended to eliminate the use of in-process Type II examinations where subsequent fabrication/forming operations remove the surfaces inspected.
6.9.3 The maintenance or overhaul examination of turbine
engine critical components shall be done only with Type I, Methods C or D (solvent removable or post emulsified, hydrophilic) processes and either sensitivity Levels 3 or 4 penetrant materials.
6.10 Records—Results of all final penetrant examinations
shall be recorded. All recorded results shall be identified, filed, and made available to the cognizant engineering organization upon request. Records shall provide for traceability to the specific part or lot inspected. As a minimum, the records shall include: identification of the procedure used, disposition of the examination; identification of the inspector’s examination stamp, electronic ID or signature; and the date of examination.
Records shall be kept for a minimum of three years or as otherwise specified in the purchase order or contract.
7. Specific Practices (Fig. 1)
7.1 Surface Preparation—All surfaces to be examined shall
be clean, dry, and free of soils, oil, grease, paint and other coatings (except as allowed by 6.8.2), corrosion products, scale, smeared metal, welding flux, chemical residues, or any other material that could prevent the penetrant from entering discontinuities, suppress dye performance, or produce unac-ceptable background. Cleaning methods, including etching, selected for a particular component shall be consistent with the contaminants to be removed and shall not be detrimental to the component or its intended function.
7.1.1 One or more appropriate cleaning methods such as
solvent cleaning, vapor degreasing, ultrasonic cleaning, aqueous-based cleaning, or methods agreed upon with the cognizant engineering organization shall be used for the removal of oils, greases, and waxes, and as the final step before penetrant examination. If etching is required, the parts shall be appropriately cleaned, then etched and delivered to penetrant examination.
FIG. 1 Process Flow Chart
E1417/E1417M − 13
4Copyright ASTM International Provided by IHS under license with ASTM Licensee=NSWC Crane/9963650103, User=Lax, Philip
Not for Resale, 07/01/2016 09:01:59 MDTNo reproduction or networking permitted without license from IHS
7.1.2 Chemical cleaning shall be used for the removal of
paints, varnishes, scale, carbon, or other contaminants that are not removable by solvent cleaning methods. (Warning— Caution should be exercised when using chemicals because they may irritate the eyes or skin.)
7.1.3 Mechanical cleaning shall be used for the removal of
soils and other contaminants that cannot be removed by solvent or chemical cleaning methods.
7.1.4 Grit blasting without etching may be an acceptable
cleaning method if it can be demonstrated that a sufficiently fine abrasive (150 grit or finer) will not cause peening and can be removed by a detergent or alkaline cleaner.
7.1.5 Etching, unless otherwise specified, shall be per-
formed when evidence exists that previous cleaning, surface treatments, or service usage has produced a surface condition that degrades the effectiveness of penetrant examination. Etch-ing processes shall be developed and controlled to prevent damage to the component under test. Etching is not required for those features such as close tolerance holes, close tolerance surfaces, faying surfaces, etc., where the function of the component or assembly would be degraded. Etching is not required for intermediate examination when the surface(s) are not retained in the final part/component configuration or when the final penetrant examination is preceded by etching.
7.2 Penetrant Application—Unless otherwise specified, the
entire surface of the component shall be covered with pen-etrant. Large components may be examined in sections. Pen-etrant shall be applied by spraying, dipping, brushing, or other method to provide coverage as required. The component, penetrant, and ambient temperatures shall all be in the range from 40 to 125°F [4 to 52°C] unless otherwise specified.
7.2.1 Penetrant Dwell Time—The dwell time, unless other-
wise specified, shall be a minimum of 10 min. For temperatures between 40 and 50°F [4.4 and 10°C], dwell time shall be a minimum of 20 min. It is recommended to rotate or otherwise move components as necessary, during dwell to prevent pooling of the penetrant. For dwell times greater than two hours, the penetrant shall be reapplied as required.
7.3 Penetrant Removal:
7.3.1 Method A Process—Water-washable penetrants shall
be removed with a manual or automated water spray, or a manual wipe, or an air agitated immersion wash.
7.3.1.1 Manual Spray—For handheld spray guns water pres-
sure adequate to remove the penetrant shall be used but shall not exceed 40 psi [275 kPa]. Water temperature shall be between 50 to 100°F [10 to 38°C]. When hydro-air nozzles are used the air pressure shall not exceed 25 psi [172 kPa]. A coarse spray shall be used with a minimum distance of 12 in.
[30 cm], when possible between the spray nozzle and the part.
Washing shall be conducted under appropriate illumination.
Caution shall be exercised to ensure that over-washing does not occur. If over-washing occurs, the component(s) shall be thoroughly dried and reprocessed. After rinsing, drain water from the component and utilize repositioning, suction, blotting with clean absorbent materials, or filtered shop air at less than 25 psi [172 kPa] to prevent pooling in cavities, recesses, and pockets. (Warning— Over-removal of the surface penetrant shall require that the component be cleaned and reprocessed. A good indicator of over-wash or over-removal of the surface penetrant is evidenced by the total lack of residue that may occur on all or a specific area of the part, see Test Method E165.)
7.3.1.2 Automated Spray—For automated spray systems, the wash parameters shall be such that the requirements of
7.8.3 are met. Water temperature shall be maintained between 50 to 100°F [10 to 38°C].
7.3.1.3 Manual Wipe—Excess penetrant shall be removed
with a clean, dry, lint-free cloth or absorbent toweling. The remainder of the surface penetrant shall then be removed with a water-dampened cloth or towel. The surface shall not be flushed with water and the cloth or towel shall not be saturated with water. The component shall be examined under appropri-ate illumination to ensure adequate removal of the surface penetrant. The surface shall be dried by blotting with a clean, dry towel or cloth, or by evaporation.
7.3.1.4 Immersion—Immersion wash may be utilized if the
water is air agitated and good circulation is maintained throughout the wash operation. Water temperature shall be maintained between 50 and 100°F [10 and 38°C].
7.3.2 Method B Process—Lipophilic post-emulsifiable pen-
etrant shall be removed by air agitated water immersion or with a water spray or hydro-air spray rinse after application of an emulsifier and an appropriate emulsifier dwell time. Water pressure and temperature and air pressure shall meet the requirements specified in 7.3.1.1, 7.3.1.2, and 7.3.1.4.
7.3.2.1 Lipophilic emulsifiers shall be applied by immersion
or flowing. Lipophilic emulsifiers shall not be applied by spray or brush and shall not be agitated while on the surface of the component. Maximum dwell times, unless otherwise specified, shall be 3 min for Type I systems and 30 s for Type II systems, or as recommended by the manufacturer. Actual dwell times shall be the minimum necessary to produce an acceptable background on the component.
7.3.2.2 Rinsing—After the appropriate emulsifier dwell
time, emulsification shall be stopped by immersion or water spray. For spray removal of the penetrant/emulsifier mixture, the parameters of 7.3.1.1, 7.3.1.2, and 7.3.1.4 apply. Dwell time in an agitated immersion rinse, if used, shall be the minimum required to remove the emulsified penetrant. Exam-ine the components under appropriate illumination after rins-ing. Clean and reprocess those components with excessive background. After rinsing, drain water from the component and utilize repositioning, suction, blotting with clean absorbent materials or filtered shop air at less than 25 psi [172 kPa] to prevent pooling. Caution shall be exercised to ensure that the air nozzle is held at a sufficient distance from the part to ensure that the developing indication is not smeared by the air blast. If over-emulsification is observed, the component must be cleaned and reprocessed.
7.3.3 Method C Process—Solvent-removable penetrants are
removed by first wiping the excess penetrant with a clean, lint-free, dry cloth or absorbent toweling. The remainder of the surface penetrant is then removed with a solvent-dampened lint-free cloth or towel. The surface of the component shall not be flushed with solvent and the cloth or towel shall not be saturated with solvent. The component and cloth or toweling
E1417/E1417M − 13
5Copyright ASTM International Provided by IHS under license with ASTM Licensee=NSWC Crane/9963650103, User=Lax, Philip
Not for Resale, 07/01/2016 09:01:59 MDTNo reproduction or networking permitted without license from IHS shall be observed under appropriate illumination to ensure adequate removal of the surface penetrant. Over-removal of the surface penetrant shall require the component to be cleaned and reprocessed. The surface shall be dried by blotting with a lint-free, dry cloth or towel, or by evaporation. Method C can also be used for water-washable penetrants using water or solvent for removal of excess penetrant.
7.3.4 Method D Process—Hydrophilic post emulsifiable
penetrant shall be removed with a water prerinse, application of the hydrophilic emulsifier and then a postrinse.
7.3.4.1 Rinse—The water prerinse shall be applied for the
minimum amount of time required to achieve removal of the bulk surface penetrant. The rinse parameters of 7.3.1.1 or
7.3.1.2 shall apply.
(1) For spray application of the emulsifier, a water prerinse may be omitted.
7.3.4.2 Hydrophilic emulsifier shall be applied by
immersion, flowing, or spray. Hydrophilic emulsifier shall not be applied by brush. Foaming application of hydrophilic emulsifier is permissible when approved by the CEO.
(1) For immersion applications, the concentration, percent volume, shall be no higher than specified by the penetrant system supplier and shall not exceed that for which the system was qualified. While immersed, the emulsifier or part should be mildly agitated. Dwell time shall be the minimum required for adequate surface penetrant removal, but unless otherwise approved by the cognizant engineering organization, shall not exceed 2 minutes.
(2) For spray or flowing applications, the concentration shall not exceed 5 %. Spray applications may include fixed spray nozzles, spray wands, pump sprayers, or spray bottles provided the concentration is tested and meets the requirments of 7.8.2.6. Dwell time shall be the minimum required for adequate surface penetrant removal, but unless otherwise approved by the cognizant engineering organization, shall not exceed two minutes per surface area.
7.3.4.3 Postrinse—After the application and dwell of the
hydrophilic emulsifier, the component being examined shall be rinsed with water. The spray rinse parameters of 7.3.1.1, 7.3.1.2, and 7.3.1.4 shall apply. Evidence of over-removal shall require the part to be cleaned and reprocessed. Excessive background may be removed by additional (touchup) applica-tion of the hydrophilic emulsifier provided its maximum allowable dwell time is not exceeded. Additional rinsing of the touch-up area will be required after application and dwell of the hydrophilic emulsifier. If careful touch-up application of the hydrophilic emulsifier does not produce an acceptable background, the part shall be cleaned and reprocessed. Manual systems shall require the use of appropriate black light illumi-nation to ensure adequate penetrant removal.
7.4 Drying—The components shall be dried prior to the
application of dry developer, nonaqueous developer, or exami-nation without developer. The components should be drained of excess water but not dried before the application of aqueous soluble or suspendable developers. The components shall be dried after the application of aqueous developers.
7.4.1 Drying Parameters—Components shall be air dried at
room temperature or in a drying oven. Oven temperatures shall not exceed that specified in 6.6.2. Drying time shall only be that necessary to adequately dry the part. Components shall be removed from the oven immediately after drying. Components shall not be placed in the oven with pooled water or pooled aqueous solutions/suspensions.
7.5 Developing—Unless otherwise specified, developers
shall be utilized for penetrant examination. Type I penetrants that are qualified to AMS 2644 may be used without developer under either one of the following conditions: manufacturing examination of aluminum and magnesium castings classified by AMS 2175A as Class 3 or 4, or with the expressed approval of the cognizant engineering organization. Minimum and maximum penetrant bleedout times without developer shall be 10 min and 2 h respectively. When developer is used, compo-nents that are not inspected before the maximum bleedout time shall be cleaned and reprocessed. When developer is not used, components that are not inspected before the maximum bleed-out time shall be reprocessed.
7.5.1 Dry Developers—Components shall be dry before the
developer is applied. Dry developer shall be applied in such a manner as to contact all surfaces to be inspected. Excess dry developer may be removed after the development time by light tapping or light air blow-off not exceeding 5 psi [34 kPa].
Minimum and maximum developer dwell times shall be 10 min and 4 h, respectively. Dry developers shall not be used with Type II penetrants.
7.5.2 Nonaqueous Developers—Components, or areas re-
quiring examination, shall be dry before application of the developer. Nonaqueous developer shall be applied by spraying.
For Type I penetrants, the developer shall be applied as a uniform thin coating over the entire surface to be inspected.
For Type II penetrants, the developer shall be applied over the entire surface to form a uniform, white coating to provide suitable color contrast for the penetrant indications. The uniformity and thickness of the developer coating is important for both types of penetrant systems. If the developer coating thickness is too heavy for Type I systems such that the metallic surface is completely masked, the component shall be cleaned and reprocessed. Unless otherwise specified, the minimum and maximum development times for nonaqueous developers are 10 min and 1 h respectively. For nonaqueous suspendable developer, the developer container shall be frequently agitated between applications.
7.5.3 Aqueous Developer—Aqueous soluble developers
shall not be used with Type II penetrants or Type I, Method A penetrants. Aqueous suspendable developers can be used with both Type I and Type II penetrants. Aqueous developers may be applied to the component after rinsing. Developers shall be applied by spray, flowing, or immersion. The applied developer shall not be allowed to puddle and shall completely cover all surfaces to be inspected. Components shall be air dried or oven dried to the requirements of 7.4.1. Minimum and maximum development times, after the component is dry, are 10 min and 2 h. Aqueous suspendable developers must be either constantly agitated to keep the particles from settling out of suspension or they must be thoroughly agitated prior to use to ensure that particles are in suspension.
E1417/E1417M − 13
6Copyright ASTM International Provided by IHS under license with ASTM Licensee=NSWC Crane/9963650103, User=Lax, Philip
Not for Resale, 07/01/2016 09:01:59 MDTNo reproduction or networking permitted without license from IHS
7.6 Examination—The interpretation area shall meet the
appropriate requirements of 7.8.4.5. Components shall be interpreted before the maximum developing time, and if required by specific procedures, monitored periodically during the developing time. Components not interpreted before the maximum developing time shall be cleaned and reprocessed.
7.6.1 Type I Processes—Inspector’s vision shall be dark
adapted for a minimum of 1 min prior to examining compo-nents. Longer times for more complete adaptation should be used if necessary. Inspectors shall not wear photochromic or permanently darkened lenses while processing or reviewing parts under black light. Black lights shall meet the require-ments of 7.8.4.1. All areas of fluorescence shall be interpreted.
Components with no indications or only nonrelevant indica-tions shall be accepted. Components with relevant indications shall be evaluated with respect to the applicable acceptance criteria. Components with excessive background fluorescence shall be cleaned and reprocessed.
7.6.2 Type II Processes—All indications shall be inter-
preted. Components with no indications or only nonrelevant indications shall be accepted. Components with relevant indi-cations shall be evaluated with respect to the applicable acceptance criteria. Components with excessive background shall be cleaned and reprocessed.
7.6.3 Evaluation—All indications found during the exami-
nation shall be evaluated in accordance with specified accep-tance criteria.
7.6.3.1 Indication Verification—If allowed by the specific
procedure, indications may be evaluated by wiping the indica-tion with a solvent-dampened swab or brush, allowing the area to dry, and redeveloping. Redevelopment time shall be at least ten minutes, except nonaqueous redevelopment shall be three minutes minimum. If no indication reappears, the original indication is considered false. This procedure may be per-formed twice for any given original indication.
7.6.3.2 Discontinuity Removal—When allowed by the spe-
cific examination procedure, discontinuity(ies) may be re-moved by an approved procedure such as sanding, either powered or manual, or grinding to determine the depth and extent of the discontinuity(ies). After the mechanical operation, the area shall be cleaned, etched (if permitted), and reexam-ined. The process used for reexamination shall be at least as sensitive as the original process.
7.6.4 Sizing—If the acceptance criteria are written in terms
of indication sizes, the indication size shall be measured. If the acceptance criteria is written in terms of discontinuity or flaw sizes, the discontinuity shall be measured.
7.6.4.1 Indication Sizing—When sizing indications for judg-
ment against appropriate acceptance criteria, the penetrant indication shall be carefully evaluated under appropriate light-ing (white light for visible dye penetrant and black light for fluorescent penetrant), after the required development or rede-velopment time as applicable. Measure the indication size at its largest dimension with a measuring device and the appropriate light that meets the requirements of 6.6.1.
7.6.4.2 Discontinuity Sizing—When sizing discontinuities
for judgment against appropriate acceptance criteria, the area may be carefully wiped with a solvent-dampened cotton swab or brush, ensuring rapid evaporation so that the area for examination is not flooded with solvent. Immediately measure the discontinuity using a measuring or comparison device and the appropriate light that meets the requirements of 6.6.1.
7.7 Postcleaning—Components shall be cleaned after ex-
amination to remove developers and other examination mate-rial residues if these are detrimental to subsequent operations or the components’ intended function.
7.8 Quality Control Provisions—This section provides the
controls necessary to ensure that the penetrant system, mate-rials and equipment provide an acceptable level of perfor-mance. The frequencies of the required checks in Table 1 are based on a facility operating daily. For facilities operating less frequently, the frequency of daily and weekly checks and those required at the start of each shift may be reduced accordingly, but must be performed prior to processing of parts. Monthly and quarterly checks shall be performed at the same frequency as for full-time operations. The NDT facility may perform these process control operations or contract for their perfor-mance with an independent, laboratory. Records of tests, TABLE 1 Required Tests and Frequency
Tests Frequency Paragraph
Penetrant ContaminationA Daily 7.8.2.1 Penetrant Brightness Quarterly 7.8.2.2 Water Content— Water-Based Penetrant (Method A)
Weekly 7.8.2.3
Water Content— Non-Water-Based Penetrant (Method A)
Monthly 7.8.2.4
Lipophilic Emulsifier Water ContentB Monthly 7.8.2.5 Hydrophilic Emulsifier Immersion, Spray, or Flowing ConcentrationB
Weekly 7.8.2.6
Dry Developer ConditionB Daily 7.8.2.7 Aqueous Developer Contamination— Soluble and Suspendable
Daily 7.8.2.8
Aqueous Developer Concentration— Soluble and Suspendable
Weekly 7.8.2.9
Penetrant System PerformanceC Daily 7.8.3 Water-Washable Penetrant Removability As required per 7.8.3 7.8.3.2
Emulsifier Removability As required per 7.8.3
7.8.3.3
Comparative Penetrant Sensitivity As required per 7.8.3
7.8.3.4
Black Light IntensityB Daily 7.8.4.1 Black Light Integrity Weekly 7.8.4.1 Special UV lighting Daily 7.8.4.2 Battery Powered UV-A lights Prior to and after use 6.7.4.1, 7.8.4.2(1) Visible Light Intensity Weekly 7.8.4.3 Light Meter CalibrationB Semi-annually 7.8.4.4 Examination Area CleanlinessA Daily 7.8.4.5 Examination Area Ambient Light Intensity Quarterly 7.8.4.5 Water Wash Pressure CheckA Start of each working shift 7.8.4.6
Water Pressure Gage CalibrationB Semi-annually 7.8.4.6 Water Wash Temperature CheckA Start of each working shift 7.8.4.6
Water Temperature Gage CalibrationB Semi-annually 7.8.4.6 Drying Oven CalibrationB Quarterly 7.8.4.7 Air Pressure Gauge Check Start of each working shift 7.8.4.9
Air Pressure Gauge Calibration Semi-annually 7.8.4.9 A Need not be recorded.
B The maximum time between verifications or checks may be extended when substantiated by technical data and approved by the Cognizant Engineering Organization.
C Not required for Method C examinations.
E1417/E1417M − 13
7Copyright ASTM International Provided by IHS under license with ASTM Licensee=NSWC Crane/9963650103, User=Lax, Philip
Not for Resale, 07/01/2016 09:01:59 MDTNo reproduction or networking permitted without license from IHS except as noted in Table 1, shall be maintained and available for audit by the customer, the cognizant engineering organization, or regulatory agencies. Penetrant materials that are provided ready-for-use and do not require mixing to a concentration, and are not recovered, or reused, or both, such as materials packaged in aerosol containers, closed drums or materials poured into containers for use and are not reused are not subject to the in-use penetrant requirements of 7.8.2.
7.8.1 New Material Conformance—Prior to being placed
into use, the conformance of materials to the requirements of AMS 2644 shall be verified, usually by a certified report from the supplier. Use of materials not conforming to AMS 2644 shall require approval by the cognizant engineering organiza-tion prior to use and shall be allowed only when materials conforming to AMS 2644 are inadequate for the particular application.
7.8.2 Material Checks (In-Use)—The applicable tests speci-
fied in 7.8.2.1 through 7.8.2.9 shall be conducted on in-use materials at the intervals specified in Table 1. Operators shall be alert to any changes in performance, color, odor, consistency, or appearance of all in-use penetrant materials and shall conduct the appropriate checks and tests if they have reason to believe the quality of the penetrant may have deteriorated. Penetrant examination shall be conducted only after acceptable quality of materials has been established.
7.8.2.1 Penetrant Contamination—The in-use penetrant ma-
terials shall be viewed as specified in Table 1 to determine if any of the following conditions are evident: precipitates, waxy deposits, white coloration, surface scum, or any other evidence of contamination or breakdown. When any of the above conditions are determined to be detrimental, the material shall be discarded or otherwise corrected, as appropriate.
7.8.2.2 Penetrant Brightness—Brightness tests of in-use
fluorescent penetrants shall be conducted at the intervals specified in Table 1. Tests shall be in accordance with Test Method E1135 with a representative sample of the unused penetrant serving as the reference. Brightness values less than 90 % of the unused penetrant brightness are unsatisfactory and the in-use penetrants shall be discarded or otherwise corrected, as appropriate.
7.8.2.3 Water Content of Water-Based Water-Washable
Penetrants—The water content of water-based Method A penetrants shall be checked at the intervals specified in Table 1 using a refractometer. The water content must be maintained according to the manufacturer’s recommendation.
7.8.2.4 Water Content of Non-Water-Based Water-Washable
Penetrants—Water content of non-water-based Method A pen-etrants shall be checked at the intervals specified in Table 1 in accordance with Test Method D95, Test Method D6304, or Karl Fischer Method as described in Annex A1. If the water content of the in-use penetrant exceeds 5 %, the penetrant shall either be discarded or sufficient unused penetrant added to reduce the water content to below 5 %.
7.8.2.5 Lipophilic Emulsifier Water Content—Water content
of lipophilic emulsifiers shall be checked at the intervals specified in Table 1 in accordance with Test Method D95, Test Method D6304, or the Karl Fischer method as described in Annex A1. If the in-use emulsifier exceeds the water content of the original (un-used) emulsifier by more than 5 % it shall be discarded or corrected, as appropriate.
7.8.2.6 Hydrophilic Emulsifier Concentration—
Concentration of the emulsifier solution shall be checked at initial makeup, during additions and at the intervals specified in Table 1 using a refractometer. A longer period may be used if a plan justifying this extension is prepared by the NDT facility and approved by the CEO. Refractometer values obtained shall be compared to actual values obtained from known concentra-tions of emulsifier. For immersion applications, the concentration, as percent of volume, shall be no higher than that specified by the penetrant system supplier and shall not exceed that for which the system was qualified. For spray or flowing applications, the concentration shall not exceed 5 %.
7.8.2.7 Dry Developer Condition—Recycled or reused dry
developer shall be checked as specified in Table 1 to check for fluorescence and to ensure it is fluffy and not caked. Caked dry developer is unsatisfactory and shall be replaced. To check for fluorescence, apply a thin layer of in-use developer to a 4-in.
[10-cm] or greater flat test panel using the same method of application used for production parts, and observe under a black light. Dry developer exhibiting ten or more fluorescent specks in a 4-in. [10-cm] diameter circle is unsatisfactory and shall be replaced. The test panel selected shall be non-fluorescent and non-reflective and have a working surface color which provides a good contrast with the developer powder.
7.8.2.8 Aqueous Developer Contamination—Soluble and
suspendable aqueous developers shall be checked as specified in Table 1 for fluorescence and coverage. Immerse a clean aluminum panel, about 3 by 10 in. [8 by 25 cm] in the in-use developer, dry it, and observe it under a black light. Observed fluorescence or failure to uniformly wet the panel is unsatis-factory and the developer shall be discarded or otherwise corrected, as appropriate.
7.8.2.9 Aqueous Developer Concentration—Soluble and
suspendable aqueous developer concentration shall be main-tained and checked with a hydrometer or in accordance with the manufacturer’s instructions at the intervals specified in Table 1. Concentration shall be in accordance with the manu-facturer’s recommendation and shall be replaced or corrected accordingly.
7.8.3 Penetrant System Performance—The penetrant sys-
tem’s overall performance shall be checked as specified in Table 1. The check shall be performed by processing a known defect standard through the system using in-use penetrant, emulsifier (if used) and developer and appropriate processing parameters. The resulting indications will then be compared to the indications obtained using unused penetrant, emulsifier (if used) and developer. This comparison may be made with records of previously obtained indications or with a similar known defect standard processed with unused materials from a hold-out sample. When required by the CEO or when the sensitivity or performance of the in-use materials falls below the performance of the unused materials, the in-use materials shall be checked in accordance with paragraphs 7.8.3.2 through
7.8.3.4 as appropriate, prior to conducting any further penetrant
E1417/E1417M − 13
8Copyright ASTM International Provided by IHS under license with ASTM Licensee=NSWC Crane/9963650103, User=Lax, Philip
Not for Resale, 07/01/2016 09:01:59 MDTNo reproduction or networking permitted without license from IHS examinations. Unacceptable materials shall be discarded or otherwise corrected in accordance with the manufacturer’s instruction.
7.8.3.1 Known Defect Standards—The known defect stan-
dard used shall be approved by the cognizant engineering organization. The user shall establish and document effective cleaning procedures based on the manufacturer’s instructions, if applicable. The user shall ensure that cleaning of the standards between uses is adequate and that physical changes in the standard that make it unrepresentative of the indications found using the hold-out sample are detected.
7.8.3.2 Water-Washable (Method A) Penetrant
Removability—When required in accordance with 7.8.3, the removability of water-washable (Method A) penetrants shall be tested using a AMS 2644-specified test panel or any other commercially available grit blasted panel. The test shall be performed using a sample of unused penetrant serving as a reference. Place a streak of the unused reference sample on one portion of a panel and a separate streak of the in-use penetrant on a separate area of the panel. Allow the panel to drain for five minutes and then wash the panel using the temperature, pressure and wash times in use on the examination line. Dry the panel, coat with developer, and examine under UV light.