- Construction Management (CM) Services for the Phase 1B/1C Modernization of the Harry S Truman Building
- Solicitation number
- GS11P08MKC0038
About this file
Amendment 5 - Revised Section C Page I-C-3
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT 5 - SF30.doc | DOC document | |
| Revised Supplemental Sheets _ Amendment 5.doc | DOC document | |
| AMENDMENT 4 - SF30.doc | DOC document | |
| Revised Section B_ Amendment 3.doc | DOC document | |
| AMENDMENT 3 - SF30.doc | DOC document | |
| Amendment 3 - Questions and Answers.doc | DOC document | |
| AMENDMENT 2 - SF30.doc | DOC document | |
| Amendment 2 - Questions and Answers.doc | DOC document | |
| Revised Section B_ Amendment 2.doc | DOC document | |
| AMENDMENT 1.doc | DOC document | |
| Section L.doc | DOC document | |
| Section G.doc | DOC document | |
| Section E.doc | DOC document | |
| Section F.doc | DOC document | |
| Section B.doc | DOC document | |
| Section C.doc | DOC document | |
| Section A.doc | DOC document | |
| Section M.doc | DOC document | |
| Section A-SF33.doc | DOC document | |
| Section I.doc | DOC document | |
| Section D.doc | DOC document | |
| Section K.doc | DOC document | |
| Coverpage.doc | DOC document | |
| Section J.doc | DOC document | |
| Section H.doc | DOC document |
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Phase 1B & 1C Modernization
Revised Section C, Page I-C-3
August 14, 2008
· Bid Package-2: Wall Hardening, Blast Windows &
Progressive Collapse Mitigation
Actual Design Start:
05/2007
Estimated Design Complete:
07/2008
Estimated Construction Start:
11/2008
Estimated Construction Substantially Complete:
11/2009
- Bid Package-3/4: Shell and Tenant Improvements
- Bid Package-3/4: Optional Cafeteria & Kitchen
- Bid Package-3/4: Optional Security Pavilion
Actual Start:
09/2007
05/2009
09/2009
Estimated Construction Substantially Complete:
09/2010
Phase 1C: (Phase 1C will consist of one Bid Package)
Estimated Design Start:
06/2010
10/2011
05/2012
Estimated Construction Complete:
07/2014
C.1.3
Nature of Facilities and Work: The following is a representative list of types of spaces and work that may be included in the program:
Facilities: Executive Suites, Office Space, Conference and Training Rooms, Auditorium(s), File and Storage Rooms, Public Space, Data Center(s), Telecommunication Rooms, Audio/Visual Rooms, Mechanical Rooms, Cafeteria(s), Facilities/Operations Spaces, Personnel and Material Screening Facility, and Historic Common Spaces.
Work: Hazardous material abatement, Building and Systems Demolition, Construction of a security screening facility for construction materials and personnel, Construction of a temporary fire egress stair for DOS employees, Wall hardening, Progressive collapse mitigation, Blast window installation, Shell and Tenant build-out.
C.1.4.
Estimated Construction Cost Range:
Phase 1B: $60 Million to $80 Million
Phase 1C: $100 Million to $120 Million
C.1.5.
Abbreviations. The following abbreviations have been used throughout this solicitation.
I-C-3
GS11P08MKC0038