Amendment 5 - Revised Page I-C-3.doc

DOC document 26 KB Posted

Attached to
Construction Management (CM) Services for the Phase 1B/1C Modernization of the Harry S Truman Building
Solicitation number
GS11P08MKC0038
Issued by

About this file

Amendment 5 - Revised Section C Page I-C-3

View the file

Other files

File Type Posted
AMENDMENT 5 - SF30.doc DOC document
Revised Supplemental Sheets _ Amendment 5.doc DOC document
AMENDMENT 4 - SF30.doc DOC document
Revised Section B_ Amendment 3.doc DOC document
AMENDMENT 3 - SF30.doc DOC document
Amendment 3 - Questions and Answers.doc DOC document
AMENDMENT 2 - SF30.doc DOC document
Amendment 2 - Questions and Answers.doc DOC document
Revised Section B_ Amendment 2.doc DOC document
AMENDMENT 1.doc DOC document
Section L.doc DOC document
Section G.doc DOC document
Section E.doc DOC document
Section F.doc DOC document
Section B.doc DOC document
Section C.doc DOC document
Section A.doc DOC document
Section M.doc DOC document
Section A-SF33.doc DOC document
Section I.doc DOC document
Section D.doc DOC document
Section K.doc DOC document
Coverpage.doc DOC document
Section J.doc DOC document
Section H.doc DOC document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Phase 1B & 1C Modernization

Revised Section C, Page I-C-3

August 14, 2008

· Bid Package-2: Wall Hardening, Blast Windows &

Progressive Collapse Mitigation

Actual Design Start:

05/2007

Estimated Design Complete:

07/2008

Estimated Construction Start:

11/2008

Estimated Construction Substantially Complete:

11/2009

- Bid Package-3/4: Shell and Tenant Improvements

- Bid Package-3/4: Optional Cafeteria & Kitchen

- Bid Package-3/4: Optional Security Pavilion

Actual Start:

09/2007

05/2009

09/2009

Estimated Construction Substantially Complete:

09/2010

Phase 1C: (Phase 1C will consist of one Bid Package)

Estimated Design Start:

06/2010

10/2011

05/2012

Estimated Construction Complete:

07/2014

C.1.3

Nature of Facilities and Work: The following is a representative list of types of spaces and work that may be included in the program:

Facilities: Executive Suites, Office Space, Conference and Training Rooms, Auditorium(s), File and Storage Rooms, Public Space, Data Center(s), Telecommunication Rooms, Audio/Visual Rooms, Mechanical Rooms, Cafeteria(s), Facilities/Operations Spaces, Personnel and Material Screening Facility, and Historic Common Spaces.

Work: Hazardous material abatement, Building and Systems Demolition, Construction of a security screening facility for construction materials and personnel, Construction of a temporary fire egress stair for DOS employees, Wall hardening, Progressive collapse mitigation, Blast window installation, Shell and Tenant build-out.

C.1.4.

Estimated Construction Cost Range:

Phase 1B: $60 Million to $80 Million

Phase 1C: $100 Million to $120 Million