Design-Build (DB) Statement of Work (SOW)
BONNEVILLE POWER ADMINISTRATION (BPA) FRESH AIR INTAKE RELOCATION &
ELEVATOR MODERNIZATION
U.S. General Services Administration Public Buildings Service
Scope of Work for
INDEPENDENT COMMISSIONING AGENT SERVICES
PROJECT IDENTIFICATION
Project Name: BPA Elevator Renovation and Fresh Air Intake Modifications
Project Number: VOR00020
Region: 10
Building Name: BPA Building (OR0058PE)
Building Address: 905 11th Ave. NE, Portland, OR 97232
The General Services Administration (GSA) is seeking the services of a qualified commissioning agent and is providing this SCOPE OF SERVICES for a qualified Commissioning Agent (CxA) for the Bonneville Power Administration GSA Project # VOR00020.
GSA is committed to commissioning this facility to ensure that commissioned systems are well designed, complete and functioning properly upon project completion, meet the energy efficiency requirements which are an integral part of this project, are economical to operate and maintain, and that GSA staff has adequate system documentation and training.
BACKGROUND
The Bonneville Power Administration Headquarters is approximately 702,000 gross sq ft, seven story building owned by the GSA and co-operated by GSA and BPA. The current project is to relocate the current fresh air intakes from the street level to avoid intentional or accidental contamination of the fresh air supply.
OBJECTIVES
The objective of commissioning is to provide independent (from DB contractor) documented confirmation that a facility fulfills the functional and performance requirements of GSA, the occupants (GSA clients) and operators. To reach this goal it is necessary for the commissioning process to establish and document GSA project requirements and criteria for system function, performance, and maintainability (design intent); and to also verify and document compliance with these criteria throughout design, construction and start-up. In addition, complete operation and maintenance (O&M) manuals, as well as training on system operation, should be provided to the building operators to ensure the building continues to operate as intended.
The Commissioning Agent (CxA) will be involved throughout the project from the design development through the construction phase. Note: The term “Commissioning Agent” is sometimes referred to as the “Commissioning Authority” or "Commissioning Provider". The primary role of the CxA during the overall design phase is to develop detailed commissioning specifications and review the design to ensure it meets GSA and client objectives. During construction, the CxA develops and coordinates the execution of a testing plan, which includes observing and documenting systems’ performance to ensure that the systems are functioning in accordance with GSA and client project requirements and the contract documents. The CxA is not responsible for design or general construction scheduling, cost estimating, or construction management, but may assist with problem-solving or resolving non-conformance issues or deficiencies.
SCOPE OF WORK
The CxA shall be responsible for carrying out the following tasks. (The proposer is free to suggest changes and improvements to the following task list, but for this proposal it is assumed that the listed tasks will be completed.) This scope of work includes Design Development Phase (DD), Construction Documents Phase (CD), Construction Phase, and Warranty Phase services.
DD Phase
1. Assemble commissioning team, hold a scoping meeting and identify responsibilities.
2. Develop a draft design-phase commissioning plan.
3. Schedule commissioning meetings as needed with project manager and design team.
4. Review GSA project requirements documentation for clarity and completeness.
5. Perform focused review of the DD plans and specs as per CMa SOW .
CD Phase
1. Coordinate the commissioning work during design.
2. Develop and/or update the design phase commissioning plan.
3. Perform focused reviews of the design, drawings and specifications at 35% Design Phase and 95% Design Phase stages. Issue a report at each review. Meet with GSA and the designers to resolve comments. Document comment resolution and issue an updated report. Check comment resolution in subsequent reviews.
4. Assist and review the development and updating of the Design Record documentation by the DB contractor’s design team members at each design submission. The Design Record consists of GSA Project Requirements and Design Intent.
5. Develop a draft construction phase commissioning plan.
6. Write full commissioning specifications for all commissioned equipment, which will be inserted into the construction contract specification package; coordinate this with the DB contractor’s design team for content and format. One or more of the following documents can be used as a guide for content, rigor and format: 1) Model Commissioning Plan and Guide Specifications, USDOE/FEMP; Portland Energy Conservation Inc (PECI). 2) The HVAC Commissioning Process, ASHRAE Guideline 1-1996. The PECI document can be downloaded free at http://www.peci.org.
7. The commissioning specification for the construction contract will include general commissioning requirements common to all systems and assemblies and a detailed description of the responsibilities of all parties, details of the commissioning process; reporting and documentation requirements, including formats; alerts to coordination issues, deficiency resolution; construction checklist and startup requirements; the functional testing process; specific functional test requirements, including testing conditions and acceptance criteria for each piece of equipment being commissioned.
The specifications will clearly indicate party responsible for witnessing and documenting startup of each commissioned system. The specifications will be clear as to who is writing, directing, conducting and documenting functional tests and regulatory-required tests. This may vary between systems, especially between electrical and mechanical. Provide language to enhance current contract specifications to ensure comprehensive controls submittals, full control contractor accountability for documented point-to-point checkout and commissioning participation, comprehensive test, adjusting and balancing, full contractor documentation of start-up and training and O&M manual documentation.
8. Review the project specifications and provide comments and additional language, as needed, to the controls contractor qualifications, controls submittal requirements, test/adjust/balance specification, training requirements and operations and maintenance and system manual requirements.
9. Coordinate a controls integration meeting where the constructors, electrical and mechanical engineers, GSA representative, and the Commissioning Agent discuss integration issues between equipment, systems and disciplines to ensure that integration issues and responsibilities are clearly described in the specifications.
10. Review the recommendations from constructability reviews for commissioning and O&M issues.
11. Development of measurement and verification plan to be utilized after construction is complete to ensure systems and their associated energy use is compliant with projected energy use anticipated during design period.
Bid Phase
1. Attend pre-bid meeting to note commissioning related questions for possible amendment to bid package.
Construction Phase
Construction phase commissioning will be deferred until the mechanical design is developed.
1. Perform the tasks and functions in the specifications ascribed to the Commissioning Agent.
2. Coordinate and direct the commissioning activities in a logical, sequential and efficient manner using consistent protocols and forms, centralized documentation, clear and regular communications and consultations with all necessary parties, frequently updated timelines and schedules and technical expertise.
3. Coordinate the commissioning work with the contractor and construction manager, to ensure that commissioning activities are being incorporated into the total project schedule.
4. Revise, as necessary, the construction phase commissioning plan developed during design, including scope and schedule.
5. Plan and conduct commissioning meetings as needed and distribute minutes to CMa.
6. Request and review additional information required to perform commissioning tasks, including O&M materials, contractor start-up and checkout procedures. Before startup, gather and review the current control sequences and interlocks and work with contractors and design engineers until sufficient clarity has been obtained, in writing, to be able to write detailed testing procedures.
7. Review normal Contractor submittals applicable to systems being commissioned for compliance with commissioning needs, concurrent with the CMa reviews.
8. Review applicable/relevant requests for information and change orders for impact on commissioning activities.
9. Review coordination drawings to ensure that trades are making a reasonable effort to minimize interferences which may affect Cx activities and/or future operations activities.
10. Write and distribute construction checklists for commissioned equipment.
11. Develop an enhanced start-up and initial systems checkout plan with contractors for selected equipment.
12. Perform site visits, as necessary, to observe component and system installations. Attend selected planning and job-site meetings to obtain information on construction progress. Review construction meeting minutes for revisions/substitutions relating to the commissioning process. Assist in resolving any discrepancies.
13. Witness HVAC ducting pressure test and flushing, sufficient to be confident that proper procedures were followed. Include testing documentation in the Commissioning Record.
14. Witness any ductwork testing and cleaning sufficient to be confident that proper procedures were followed. Include documentation in the Commissioning Record.
15. Document construction checklist completion by reviewing completed construction checklists and by selected site observation.
16. Document systems startup by reviewing start-up reports and by selected site observation.
17. Review and recommend approval of air systems balancing. This process may include spot testing and reviewing completed reports and by selected site observation.
18. Write step-by-step functional test procedures and documentation formats for all commissioned equipment and assemblies. monitoring.
EXCEPTION: a) regulated tests such as fire alarm, fire suppression, elevators and electrical equipment tests where detailed test and documentation requirements already exist in standards or codes, when required in other specification sections, and b) common contractor tests such as duct and piping tests and the contractors' initial equipment checkout tests.
For tests listed in a) and b) the existing written testing requirements and procedures in accepted or required standards or guidelines will suffice as the functional test procedures.
Refer to the Functional Testing Responsibility Table for clarification.
Coordinate functional testing for all commissioned systems and assemblies. Witness and document manual functional performance tests performed by the Contractor for all commissioned systems and assemblies. Refer to the Functional Testing Responsibility Table for more specific delineation. The functional testing shall include operating the system and components through each of the written sequences of operation, and other significant modes and sequences. Sensors and actuators shall be calibrated during construction check listing by the installing contractors, and spot-checked by the Commissioning Agent during functional testing. Analyze functional performance trend logs and monitoring data to verify performance. Coordinate retesting as necessary until satisfactory performance is achieved.
Functional testing shall be done using conventional manual methods, control system trend logs, and read-outs or stand-alone data loggers, to provide a high level of confidence in proper system function, as deemed appropriate by the CxA and GSA.
19. After manual testing and initial trouble shooting is complete, monitor system operation and performance for selected data points for up to two weeks by requesting trend logs from the Contractor from the building automation system. For needed system points not able to be trended by the building automation system by furnish and install temporary portable data loggers that will monitor up to 20 points. Analyze monitored data to verify operation and performance and issue a written report.
20. Not used
22. Coordinate and assist in development of test plans, execution and documentation of tests of commissioned equipment overseen by regulatory authorities and ensure that such tests meet the testing and documentation rigor desired by GSA. Testing and commissioning for these systems shall be per the requirements of those sections of the specifications and the governing codes and standards. The Commissioning Agent shall work with the D-B Contractor, CMa and GSA to ensure that these tests are scheduled and coordinated with the interfaces to other systems on the project as well as requirements of the authorities having jurisdiction.
23. Maintain a commissioning master issues log and a separate record of functional testing. Report all issues as they occur directly to CMa. Provide directly to CMa written progress reports and test results with recommended actions.
24. Review equipment warranties to ensure that GSA responsibilities are clearly defined.
25. Oversee and review the training of GSA operating personnel. Oversee the videotaping of this training where specified.
26. Review the preparation of the O&M manuals for commissioned equipment.
27. Compile a Commissioning Record, which shall include:
A. A brief summary report that includes a list of participants and roles, brief building description, overview of commissioning and testing scope, and a general description of testing and verification methods. For each piece of commissioned equipment, the report should contain the disposition of the Commissioning Agent regarding the adequacy of the equipment, documentation and training meeting the contract documents in the following areas:
1) Equipment meeting the equipment specifications,
2) Equipment installation,
3) Functional performance and efficiency,
4) Equipment documentation, and
5) Operator training.
B. All outstanding non-compliance items shall be specifically listed. Recommendations for improvement to equipment or operations, future actions, commissioning process changes, etc. shall also be listed. Each non-compliance issue shall be referenced to the specific functional test, inspection, trend log, etc. where the deficiency is documented.
C. Also included in the Commissioning Record shall be the issues log, commissioning plan, progress reports, submittal and O&M manual reviews, training record, test schedules, construction checklists, start-up reports and functional tests.
27. Compile a Systems Manual that consists of the following: GSA Project Requirements (by GSA); Design Narrative and Basis of Design (by designer); Performance Metrics, if completed during design; space and use descriptions, single line drawings and schematics for major systems (by designer); control drawings, sequences of control (by contractor); and a table of all set points and implications when changing them, schedules, instructions for operation of each piece of equipment for emergencies, startup and shutdown, instructions for energy savings operations and descriptions of the energy savings strategies in the facility, recommendations.
Warranty Phase – not used
1.6 Qualifications
Extensive field experience. A minimum of five (5) years in this type of work is required.
5 years design experience in HVAC/R 5 years HVAC/R commissioning experience with projects of similar size and scope.
5 years construction experience with projects of similar size and scope Experienced in energy-efficient equipment design and control strategy optimization.
Direct experience in monitoring and analyzing system operation using energy management control system trending and stand-alone data logging equipment.
Excellent verbal and writing communication skills. Highly organized and able to work with both management and trade contractors.
Experienced in writing commissioning specifications.
A bachelor’s degree in mechanical or electrical engineering is strongly preferred, and P.E. certification is desired, however, other technical training, past commissioning, and field experience will be considered.
Membership in the Building Commissioning Association.
SYSTEMS AND ASSEMBLIES TO BE COMMISSIONED
The following systems and assemblies will be commissioned:
Design Build Statement of Work Bonneville Power Administration (BPA) Fresh Air Intake Relocation & Elevator Modernization 6 May 2015
BPA Portland VOR00020 CXSOW 09MAR2015 Page 1 of 9
1. Installed and altered ductwork
2. Installed exhaust fans
· End of SOW
Fairbanks VAK00011 CXSOW 3/2014 Page 9 of 10
EXHIBIT 1
FOCUSED DESIGN REVIEW SCOPE
The Commissioning Agent will perform a review of the design documents for the following issues at the phases checked for HVAC.
| Key: | SD: | Schematic Design Review | DD: | Design Development Review |
| DPD1: | Design Phase Document Review #1 | DPD2: | Design Phase Document Review #2 |
| Design Area |
| Review Description |
| SD |
| DD |
| DPD1 |
| DPD2 |
| Design narrative and design basis |
| Ensure that design narrative and basis of design are clear, complete, and meet the original GSA Project Requirements |
| x |
| x |
| x |
| Commissioning facilitation |
| Review to facilitate effective commissioning (see Exhibit 2). |
(sufficient accessibility, test ports, monitoring points, etc.)
| x |
| x |
| x |
| Energy efficiency |
| Review for adequacy of the effectiveness of building layout and efficiency of system types and components for building shell, HVAC systems and lighting systems. |
| x |
| x |
| Control system & control strategies |
| Review HVAC Strategies and Sequences of Operation for adequacy and efficiency. |
| x |
| x |
| x |
| Operations and maintenance (O&M) |
| Review for effects of specified systems and layout toward facilitating O&M (equipment accessibility, system control, etc.). |
| x |
| x |
| Indoor environmental quality |
| Review to ensure that systems relating to Thermal, Visual, Acoustical, Air quality comfort, Air distribution. Maximize comfort and are in accordance with GSA Project Requirements.. |
| x |
| x |
| O&M documentation |
| Verify adequate building O&M documentation requirements. |
| x |
| x |
| x |
| Training |
| Verify adequate operator training requirements. |
| x |
| x |
| x |
| Commissioning specifications |
| Verify that bid documents adequately specify building commissioning, including testing requirements by equipment type. |
| x |
| x |
| x |
| x |
| GSA design guideline or standard |
| Verify that the design complies with GSA’s own design guideline or standard. |
| x |
| x |
| Mechanical |
| Review the mechanical concepts/design for enhancements. |
| x |
| x |
| x |
| Functionality |
| Ensure the design maximizes the functional needs of the occupants. |
| x |
| x |
| x |
| Change Order Analysis |
| In the course of reviews, identify issues that are likely to cause change orders or RFI’s |
| x |
| x |
| Back Check |
| Verify that agreed upon actions from previous design reviews have been incorporated |
| x |
| x |
| Value Engineering Management |
| In the course of reviews, note areas where there could be cost savings without effecting owner objectives |
| x |
| x |
| x |