Project Name: FR 90 RD – Seed Task Order Page 1
Table of Contents
PART I – THE SCHEDULE
SECTION A—PROJECT GENERAL INFORMATION
A.1 CONTACT INFORMATION:
A.2 THE GOVERNMENT REQUIRES THE PERFORMANCE OF THE WORK DESCRIBED
IN THESE DOCUMENTS
PART I – SCHEDULE OF ITEMS
SECTION B – SUPPLIES, SERVICES, AND PRICES
B.1 SCHEDULE OF ITEMS
SCHEDULE NOTES:
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SCOPE OF CONTRACT
C.2 PROJECT LOCATION
C.3 MAGNITUDE OF CONSTRUCTION PROJECT
C.7 APPLICABLE SPECIFICATIONS
C-8 SUBMITTALS
C-9 PRODUCTS SAMPLES AND/OR SUBMITTALS ............... Error! Bookmark not defined.
C.21 TECHNICAL SPECIFICATIONS
SECTION D--PACKAGING AND MARKING
SECTION E--INSPECTION AND ACCEPTANCE ......................................... Error! Bookmark not defined.
SECTION F--DELIVERIES OR PERFORMANCE
F.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
(APR 1984)
F.4 OTHER REQUIREMENTS
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 CLAUSES
G.2 GOVERNMENT-FURNISHED PROPERTY
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 SUPPLEMENTAL INFORMATION
H.5 LANDSCAPE PRESERVATION – SPILL PREVENTION
H.6 EROSION CONTROL AND POLLUTION ........................... Error! Bookmark not defined.
H.12 SPECIAL EQUIPMENT CLEANING REQUIREMENTS
H.14 USE OF PREMISES
H.18 FISH REQUIREMENTS
H.19 DEWATERING AND REWATERING
H.20 HEAVY EQUIPMENT
H.21 OTHER REQUIREMENTS
PART II--CONTRACT CLAUSES
Project Name: FR 90 RD – Seed Task Order Page 2
SECTION I--CONTRACT CLAUSES
I.1 CLAUSES
PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J--LIST OF ATTACHMENTS
J.1 ATTACHMENTS
PART IV--REPRESENTATIONS AND INSTRUCTIONS
SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND
OTHER STATEMENTS OF OFFERORS OR RESPONDENTS
SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR RESPONDENTS . 22
SECTION M--EVALUATION FACTORS FOR AWARD
M.1 PROVISIONS
M.2 PROPOSAL EVALUATION
Project Name: FR 90 RD – Seed Task Order Page 3
PART I – THE SCHEDULE
SECTION A—PROJECT GENERAL INFORMATION
A.1 CONTACT INFORMATION:
Sarah Rockey 360-497-1113 COR Telephone No.
Melissa Jolley 509-310-3117 Technical Contact Telephone No.
A.2 THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE
DOCUMENTS
FY23 Forest Road 90 Roadway Repairs Gifford Pinchot National Forest Mount St Helens National Volcanic Monument Skamania County, Washington
Project Name: FR 90 RD – Seed Task Order Page 4
PART I – SCHEDULE OF ITEMS
SECTION B – SUPPLIES, SERVICES AND PRICES
B.1 SCHEDULE OF ITEMS
Contract Line-Item No. 0001 FR 90; MP 5.6, 5.8, 7.0, 8.8, 14.1B (Base)
Item No. Description Pay Unit Est Qty Unit Price Total Price
15101 Mobilization Lump Sum All $ $
15201 Construction Survey and Staking Method 1 Lump Sum All $ $
15401 Contractor Testing Lump Sum All $ $
15713 Soil Erosion and Pollution Control Lump Sum All $ $
15761 Dewatering Structure Each 2 $ $
20101 Clearing And Grubbing, Disposal Method F, Compaction Method N/A Lump Sum ALL $ $
20302 Removal of Corrugated Metal Pipe, Disposal Method A, Compaction Method B Each 2 $ $
20304 Removal of Existing Asphalt, Disposal Method A
Square Yard* 3080.0 $ $
20401 Roadway Excavation, Compaction Method B, Tolerance Class D Cubic Yard* 3270 $ $
20412 Select Borrow, Compaction Method B Cubic Yard* 2975 $ $
25104 Keyed Riprap, Class 2 Cubic Yard* 10 $ $
30201 Aggregate Base, Method 2 Cubic Yard* 1368 $ $
40304 Asphalt Concrete, Washington State DOT, Type II Ton* 672.00 $ $
60201 24-Inch Pipe Culvert, Aluminized Steel, Gage 16, Compaction Method B Foot* 112 $ $
60501 Standard Underdrain System Foot* 856 $ $
60705 Removing, Cleaning, and Resetting Spillway Culvert Pipe Each 1 $ $
62552 Seeding and Mulching, Dry Method Lump Sum ALL $ $
63309 Remove and Reset Sign Each 3 $ $
63401A Pavement Marking, Type B, Yellow Foot* 2234
63401B Pavement Marking, Type B, White Foot* 2234
63501 Temporary Traffic Control Lump Sum All
Total Cost $ *Denotes Contract Quantity
Project Name: FR 90 RD – Seed Task Order Page 5
Contract Line-Item No. 0002
FR 90; MP 7.6 (Option 1)
Item No. Description Pay Unit Est Qty Unit Price Total Price
15101 Mobilization Lump Sum All $ $
15201 Construction Survey and Staking Method 1 Lump Sum All $ $
15401 Contractor Testing Lump Sum All $ $
15713 Soil Erosion and Pollution Control Lump Sum All $ $
15761 Dewatering Structure Each 1 $ $
20101 Clearing and Grubbing, Disposal Method F, Compaction Method N/A Lump Sum ALL $ $
20302 Removal of Corrugated Metal Pipe, Disposal Method A, Compaction Method B
Each 2 $ $
20304 Removal of Existing Asphalt, Disposal Method A Square Yard* 728.0 $ $
20401 Roadway Excavation, Compaction Method B, Tolerance Class D Cubic Yard* 780 $ $
20412 Select Borrow, Compaction Method B Cubic Yard* 828 $ $
25104 Keyed Riprap, Class 2 Cubic Yard* 2 $ $
30207 Aggregate Base, Method 2 Cubic Yard* 324 $ $
40304 Asphalt Concrete, Washington State DOT, Type II Ton* 158.00 $ $
60201 24-Inch Pipe Culvert, Aluminized Steel, Gage 16, Compaction Method B Foot* 104 $ $
60501 Standard Underdrain System Foot* 251 $ $
60705 Removing, Cleaning and Resetting Spillway Culvert Pipe Each 2 $ $
62552 Seeding And Mulching, Dry Method Lump Sum ALL $ $
63309 Remove and Reset Sign Each 1 $ $
63401A Pavement Marking, Type B, Yellow Foot* 534 $ $
63401B Pavement Marking, Type B, White Foot* 534 $ $
63501 Temporary Traffic Control Lump Sum ALL $ $
Total Cost $
Project Name: FR 90 RD – Seed Task Order Page 6
Contract Line-Item No. 0002 Cont.
FR 90; MP 4.7 (Option 2)
15101 Mobilization Lump Sum All $ $
15201 Construction Survey and Staking Method 1 Lump Sum All $ $
15401 Contractor Testing Lump Sum All $ $
15713 Soil Erosion and Pollution Control Lump Sum All $ $
20101 Clearing And Grubbing, Disposal Method F, Compaction Method N/A Lump Sum All $ $
20304 Removal Of Existing Asphalt, Disposal Method A Square Yard* 298.0 $ $
20401 Roadway Excavation, Compaction Method B, Tolerance Class D Cubic Yard* 290 $ $
20412 Select Borrow, Compaction Method B Cubic Yard* 178 $ $
25104 Keyed Riprap, Class 2 Cubic Yard* 1 $ $
30207 Aggregate Base, Method 2 Cubic Yard* 246 $ $
40304 Asphalt Concrete, Washington State DOT, Type II Ton* 65.00 $ $
60501 Standard Underdrain System Foot* 95 $ $
61705 Replacement Guardrail, Type 1, Class B Foot* 50 $ $
61707 Remove And Reset Guardrail Foot* 382 $ $
62552 Seeding And Mulching, Dry Method Lump Sum All $ $
63401A Pavement Marking, Type B, Yellow Foot* 218 $ $
63401B Pavement Marking, Type B, White Foot* 218 $ $
63501 Temporary Traffic Control Lump Sum All $ $
Total
Total Total Price
Base Item Total $
Option 1 Total $
Option 2 Total $
Total (add all 3 lines) $
Project Name: FR 90 RD – Seed Task Order Page 7
SCHEDULE NOTES:
1. See Project Submittals FSSS 153.07 for all items that are incidental to Pay Item(s).
2. All volume unit pay items are measured in-place. All reference to quantities of excavated materials, backfill and embankment materials refer to original (prior to excavation) volumes.
3. Items labeled as optional are not required to be exercised by the government. If exercised, the contractor will be required to perform the optional work in accordance with the terms and conditions of this contract.
4. One award will be made from this solicitation, contractors must submit pricing for all items.
5. Pay Item 15101 Mobilization: Includes fire protection and equipment cleaning. A two-day notice is required to USFS for equipment inspections. Road construction equipment operating in known areas of noxious weed infestations shall be cleaned prior to leaving the area.
6. Pay Item 15201 Construction survey and staking: Tolerance and precision class in accordance with FSSS Table 152-1, Schedule A.
7. Pay Item 20101 Clearing and grubbing: Remove all trees, brush, downed timber, and other vegetation that are within the clearing and grubbing limits. Limb to 20' above traveled way surface. Grub deep enough to remove stumps, roots, buried logs, moss, turf, or other vegetative debris. Grub pits, channel changes and ditches within clearing and grubbing limits.
8. Pay Item 20302 Removal of corrugated metal pipe: Includes excavation to remove culvert. Remove existing culvert and dispose off forest. Culvert replacements that have a centerline depth of 6' or greater requires approval of excavation and foundation by Contracting Officer prior to backfilling.
9. Pay Item 20304 Removal of existing asphalt: Remove existing asphalt and dispose off forest.
10. Pay Item 20401 Roadway excavation: Compact in 12" lifts. Geogrid, category 4, layered every 1' is required for all repairs deeper than 1' and is incidental to this pay item. Refer to FP-14 Section 207 Earthwork Geosynthetics for specifications on geogrid material.
11. Pay Item 20412 Select borrow: Commercial source.
12. Pay Item 25104 Keyed riprap: Commercial source.
13. Pay Item 30201 Aggregate base: Commercial source; WASH DOT base. Submit gradation certification to Contracting Officer at least 14 days prior to intended use.
14. Pay Item 40304 Asphalt concrete: Commercial source. Place asphalt in 2" compacted lifts. 1/2" dense graded HMAC, seal edges of cut with emulsified asphalt and blot with fine sand. Asphalt subgrade approval is required by Contracting Officer prior to pouring asphalt concrete. Tack coat required on full surface between existing road surface and new asphalt.
15. Pay Item 60201 Pipe culvert: Commercial source includes all bands, gaskets, and necessary hardware.
Submit culvert material certification to Contracting Officer for approval at least 7 days prior to intended use. Tolerance IAW FP-14 Section 152 Table 152-1.
16. Pay Item 60705 Removing, cleaning, and resetting spillway culvert pipe: Do not damage culvert.
17. Pay Item 62552 Seeding and mulching: Government furnished seed. Commercial source weed free mulch. Submit weed-free mulch certification to Contracting Officer for approval prior to intended use.
Seed and mulch all disturbed areas.
18. Pay Item 63501 Temporary traffic control: Submit a Temporary Traffic Control Plan to the Contracting Officer for approval at least 30 days prior to intended use. Provide temporary traffic control in accordance with the most recent edition of the "Manual for Uniform Traffic Control Devices". Any temporary closures require a 10-day advanced notice to USFS and approval by Contracting Officer.
Project Name: FR 90 RD – Seed Task Order Page 8
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
(The Below Clauses and Terms are Supplemental to the Base IDIQ)
C.1 DESCRIPTION OF WORK
The project consists of the following major items of work as Base Bid Items:
1. MP 5.6 - 204' long full asphalt replacement with a 65' Long full width 6' Deep - deep patch repair, and a 24" culvert replacement. Work involves clearing and grubbing, removal of existing asphalt, stabilization geogrid placement, installation of underdrain system, culvert replacement, riprap placement, select borrow, and asphalt resurfacing and striping.
2. MP 5.8 - 165' long full asphalt replacement with a 155' Long 3/4 width 4' Deep - deep patch repair.
Work involves clearing and grubbing, removal of existing asphalt, stabilization geogrid placement, installation of underdrain system, riprap placement, select borrow, and asphalt resurfacing and striping.
3. MP 7.0 - 168' long full asphalt replacement with a 55' Long half width 5' Deep - deep patch repair and a 100' Long 3/4 width 6' Deep - deep patch repair. Work involves clearing and grubbing, removal of existing asphalt, stabilization geogrid placement, installation of underdrain system, riprap placement, select borrow, asphalt resurfacing and striping, and resetting signs.
4. MP 8.8 - 280' long full asphalt replacement with an 85' Long full width 6' Deep - deep patch repair, a 156' Long 3/4 width 6' Deep - deep patch repair, and a 24" culvert replacement. Work involves clearing and grubbing, removal of existing asphalt, stabilization geogrid placement, installation of underdrain system, culvert replacement, spillway resetting, riprap placement, select borrow, asphalt resurfacing and striping, and resetting sign.
5. MP 14.1B - 280' long full asphalt replacement with a 53' Long half width 4' Deep - deep patch repair, a 20' Long full width 4' Deep - deep patch repair, and a 177' Long full width 2' Deep - deep patch repair. Work involves clearing and grubbing, removal of existing asphalt, stabilization geogrid placement, installation of underdrain system, riprap placement, select borrow, and asphalt resurfacing and striping.
The project consists of the following major items of work as Option Items:
1. MP 7.6 - 251' long full asphalt replacement with a 165' Long half width 4' Deep - deep patch repair, a 96' Long 3/4 width 6' Deep - deep patch repair, reset a culvert, and a 24" culvert replacement. Work involves clearing and grubbing, removal of existing asphalt, stabilization geogrid placement, installation of underdrain system, culvert replacements, spillway resetting, riprap placement, select borrow, asphalt resurfacing and striping, and resetting sign.
2. MP 4.7 - 105' long full asphalt replacement with a 95' Long half width 4' Deep - deep patch repair. Work involves clearing and grubbing, removal of existing asphalt, stabilization geogrid placement, installation of underdrain system, riprap placement, select borrow, asphalt resurfacing and striping, and guardrail reset and replace.
Project Name: FR 90 RD – Seed Task Order Page 9
C.2 PROJECT LOCATION
The project is located on the Gifford Pinchot National Forest, on Forest Road 9000000 between Milepost (MP) 4.6 and 14.2 in multiple locations. Located in Skamania County, Washington.
C.3 MAGNITUDE OF CONSTRUCTION PROJECT
The estimated price of construction is: Between $1,000,000 and $5,000,000.
C.4 PROSECUTION OF WORK
1. General:
The contractor shall conduct activities so that interference with the public is kept to a minimum.
Forest Road 9000000 is used for not only recreational access but also by residents and emergency services.
For daytime work: delays may not exceed 30 minutes at any one time followed by an open period of no less than 10 minutes. Radio communications are required with the Swift reservoir fish transport truck for any road delays M-F from 6 a.m. to noon. This is to ensure the fish are not loaded into the truck until just before a road opening period.
For nighttime work: a full, and continuous, road closure from 9:00 p.m. to 4:00 a.m. is allowed between MP 4.6 and MP 14.2. This nighttime work is authorized to start on a Sunday night at 9pm, or finish on a Friday morning at 4am.
The road must be open, and unrestricted in both directions, from Friday night through Sunday evening.
2. Timing Restrictions:
Spotted Owl restrictions: MP 5.6 and 5.8 have Spotted Owl work restrictions. From 03/1-07/15 short-term non-heavy equipment road work is allowed for up to five continuous hours once a day.
Unrestricted road work can occur from 07/16 to 02/28. Asphalt grinding is not deemed heavy equipment road work. Excavation is deemed heavy equipment road work. All other milepost locations do not have owl restrictions.
Allowable instream work window is from 07/16 to 08/15 and is for wet culvert replacements of the culverts at MP 5.6, MP 8.8 and Optional MP 7.6. If the culverts are dry, no work window restrictions are in place.
3. Transport & Delivery – Use of Roads by Contractor:
The Contractor is authorized to use all roads that are part of the construction project.
Coordinate planned transport and delivery dates with the Contracting Officer and Contracting Officers Representative. The Contractor shall notify the Contracting Officer a minimum of 3 working days before transporting any material.
Traffic Control Plan – Contractor is responsible for submitting a traffic control plan. See C.5 (d) for review requirements. Contractor shall perform no work that interferes or conflicts with traffic or existing access to the roadway surface until the required traffic control management plan is submitted and approved. Contractor shall not proceed with work on the project until all required
Project Name: FR 90 RD – Seed Task Order Page 10 signs and safety devises are in place and approved. During transport on US Forest Service roads, contractor shall provide sufficient traffic control in compliance with MUTCD standards and standard specification sections 156 & 635 in order to control and protect public traffic. Contractor shall be responsible for traffic control during the equipment & material transport on Forest Service land.
Overload Limit & Over-width Permits (As required)- All vehicles and equipment shall not exceed State legal highway loads and widths or posted limits without valid State and Forest Service overload, over-width permits. Forest Service overload permits for this project may be obtained by contacting the Gifford Pinchot National Forest Bridge Program Manager located at Forest Headquarters. See C.5 (e) for review requirements.
Please allow for 3 weeks processing time, overload and over-width vehicle shall not travel on Forest Service roads until the permit has been issued. Permit may be applied for in advance of the post-award conference.
4. Road Closure:
o See section C-4 (1) above for allowable road closure windows.
o Contractor may fill ditch line to provide temporary additional road width to allow traffic around work site. If water is visible or anticipated during construction, proper drainage shall be provided. Cost is considered incidental to temporary traffic control.
o Portable Changeable Message Sign (PCMS) boards will be placed 14 days prior to onsite work and will be removed on the last day of onsite work. PCMS boards will be required at the following locations: First location at FS90 MP 0.0 (or placed at the canal crossing pullout at MP 1.5), Second location at the junction of FS25 and FS90 (or placed on the Pine Creek Visitor Center property), Third location at the junction of Curly Creek Road and FS90. PCMS boards shall be placed behind a barrier or guardrail whenever possible but shall, at a minimum, provide 4 feet of lateral clearance to edge of traveled lane and be delineated by channelization devices.
Contractor will remove PCMS from the clear zone when not in use unless protected by barrier or guardrail. Message boards must meet MUTCD specifications. The contractor is responsible for safety and will be responsible for ensuring the MUTCD standards are met. Example of potential messages: Message one reads “Delays 90 M-F 6am-7pm” 2-3 seconds, Message two “9pm-4am closed 90 Sun-Fri” 2-3 seconds, Message three “Date to Date”.
o Contractor shall at all times be responsible for ensuring that necessary temporary traffic control devices remain in place for the duration of the project work. All temporary signs and barricades shall be removed from the project by the contractor after work is complete and approved by the CO. Removal of signs and barricades shall not occur before CO approval.
C.5 APPLICABLE SPECIFICATIONS AND MATRIAL CETIFICATIONS
1. Applicable Specifications:
References to Standard Specifications in the contract refer to the FOREST SERVICE STANDARD
SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY
PROJECTS, FP-14.
Sections 100 through 149, and other Standard Specifications, listed on the Specification List, are included in this solicitation by reference only. Specifications not on the list but referenced by other Standard Specifications, shall also be applicable to this document.
Project Name: FR 90 RD – Seed Task Order Page 11
The project Supplemental Specifications are also given on the Specification List but are physically attached in Section J. All requirements contained on the Specification List are hereby made a part of this solicitation and any resultant contract.
2. Product Substitution:
Any modification of other items, designs, materials, products or equipment (including Government- Furnished Property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.
C-6 SUBMITTALS
1. General Guidelines for Submittals:
Work requiring submittals shall not begin until submittals have been approved.
Submittals shall include:
Date and Revision Dates.
Project Name and Contract Number.
Names of Contractor, Subcontractor, Supplier, and Manufacturers.
Field Dimensions and Relation to Adjacent Structures.
Contractor's stamp, initialed or signed, certifying review of submittal, verification of field measurement and compliance with contract documents.
Samples:
Physical examples shall illustrate materials, equipment, or workmanship, and establish standards by which completed work shall be judged. Samples shall be of sufficient size and quantity to illustrate the functional characteristics of product or material, with integrally related parts and devices.
Manufacturer's requirements:
Supply manufacturer's catalog sheets or brochures with diagrams, schedules, or performance charts.
Illustrations shall be clearly marked to identify pertinent materials or models, dimensions, and clearances required. Supplement standard drawings to provide information unique to this project.
Approval or Rejection Time Allowance:
Submittals will be reviewed and either approved or rejected within the time designated in the table in section C.5(e). Review time begins from date of receipt by Contracting Officer or COR.
2. Material Certifications, Testing Reports & Other Submittals:
The following submittals of plans, details, specifications, designs, certificates, test reports, samples and test data shall be submitted on this project. See AGAR section 452.236-76 for timely submittal and approval by Contracting Officer.
Project Name: FR 90 RD – Seed Task Order Page 12
Note:
*Requirement for the above submittals to be transmitted to the governement before the Post Award Conference.
Allowalabel time for Governement Approval is in Working Days.
Time to submit to Government is in Calendar Days
C.7 CONSTRUCTION PLANS
Copies of the plans pertinent to this project have been attached in section J.
SECTION D--DELIVERIES OR PERFORMANCE
(Refer to Base IDIQ for Applicable Clauses and Terms)
SECTION E – INSPECTION AND ACCEPTANCE
Title Reference Time to Submit to Govt
# of Copies
Allowable Time for Governement Approval After Receipt by CO
Spill Prevention Control and Countermeasures (SPCC) Plan* Section H.2 14 days after
Award 1 7
Project Work Schedule* FAR 52.236-15 14 days after Award 1 7
Weather-Caused Suspensions of Work Plan* Base IDIQ 14 days after
Award 1 7
Fire Plan* J.1 14 days after Award 1 7
Erosion Control Plan Section H.3 14 days after Award 1 14
Road Oversize/ Overweight Permit(s) 36CFR261.12 & 261.54(c)
21 days before need 1 21
Traffic Control Plan Section C.4 30 days before need 1 30
Project Name: FR 90 RD – Seed Task Order Page 13
SECTION F--DELIVERIES OR PERFORMANCE
F.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
(APR 1984)
The Contractor shall be required to (a) commence work under this contract within _30_ calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than August 30th, 2024. The time stated for completion shall include final cleanup of the premises.
Night-time road closures are not allowed during hunting season.
Estimated Dates:
Award/Notice to Proceed: 07/12/2023.
Estimated Post Award Conference: 07/26/2023.
Estimated start work: 08/07/2023.
F.2 OTHER REQUIREMENTS
MAXIMUM WORKWEEK – CONSTRUCTION SCHEDULE (AGAR 452.236-75) (NOV 1996)
Within 14 working days after receipt of the notice to proceed, the Contractor must submit the following information in writing for approval:
(a) A proposed schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and
(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposed to carry out the work.
The maximum workweek that will be approved for daytime work is Monday through Friday, 6:00 a.m.
to 7:00 p.m.; with 30-minute delays and a minimum open period of no less than 10 minutes. Any proposed nighttime work can be done with a full, and continuous, road closure from 9:00 p.m. to 4:00 a.m. on Sunday night, Monday night, Tuesday night, Wednesday night or Thursday night. The road must be open, and unrestricted in both directions, from Friday night through Sunday evening.
Project Name: FR 90 RD – Seed Task Order Page 14
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 CLAUSES
452.215-73 POST AWARD CONFERENCE (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled and held within TBD days after the date of Notice to Proceed The conference will be held via Microsoft Teams.
G.2 GOVERNMENT-FURNISHED PROPERTY
The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the "Government Property" FAR clause contained elsewhere in the contract:
• Seed
• Waste Sites
Project Name: FR 90 RD – Seed Task Order Page 15
SECTION H--SPECIAL CONTRACT REQUIREMENTS
(The Below Clauses and Terms are Supplemental to the Base IDIQ.)
H.1 SUPPLEMENTAL INFORMATION
Emergency Control:
The Contractor shall conduct operations to minimize disruptions to the public.
No planned disruption of utilities is anticipated.
H.2 EROSION CONTROL MEASURES
Measures may include, but not be limited to:
Install check dams and sediment fences as necessary to minimize the entry of silt-laden water into streams or other water bodies.
Seed and mulch all disturbed areas. Seed to be provided by Forest Service. Certified weed free straw mulch to be provided by contractor, 2 inches thick.
Submit the Erosion Control Plan on or before the date of the post-award conference.
H.3 LANDSCAPE PRESERVATION – SPILL PREVENTION
The Contractor shall prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112), including certification by a professional engineer registered in Washington State, and shall include the following:
1. Identify a project contact (name, phone number, address) that will be responsible for implementing the SPCC Plan measures.
2. List and describe any hazardous material that would be used at the project site, including:
• procedures for inventory, storage, handling, and monitoring
• notification procedures
• specific clean-up and disposal instructions for different products on site
• proposed methods for disposal of spilled material
• types and amounts of spill containment materials that will be available on-site at all times during project implementation
• employee training for spill containment
H.4 POLLUTION AND EROSION CONTROL
1. Alteration or disturbance of the stream bed, banks, and bank vegetation of the stream shall be minimized and limited to that necessary to construct the project.
2. Implement the following pollution and erosion control measures:
(a) Project Contact: Identify a project contact (name, phone number, address) that will be responsible for implementing pollution and erosion control measures.
(b) List and describe any hazardous material that would be used at the project site, including procedures for inventory, storage, handling, and monitoring; notification procedures; specific
Project Name: FR 90 RD – Seed Task Order Page 16 clean-up and disposal instructions for different products available on the site; proposed methods for disposal of spilled material; and employee training for spill containment.
(c) Temporarily store any waste liquids generated at the staging areas under cover on an impervious surface, such as tarpaulins, until such time they can be properly transported to and treated at an approved facility for treatment of hazardous materials.
(d) Procedures based on best management practices to confine, remove, and dispose of construction waste, including every type of debris, discharge water, concrete, cement, grout, washout facility, welding slag, petroleum product, or other hazardous materials generated, used, or stored on-site.
(e) Procedures to contain and control a spill of any hazardous material generated, used or stored on-site, including notification of proper authorities. Ensure that materials for emergency erosion and hazardous materials control are onsite (e.g., silt fence, straw bales, oil-absorbing floating boom whenever surface water is present).
(f) Best management practices to confine vegetation and soil disturbance to the minimum area, and minimum length of time, as necessary to complete the action, and otherwise prevent or minimize erosion associated with the action area.
(g) Place sediment barriers prior to construction around sites where significant levels of erosion may enter the stream directly or through road ditches. Temporary erosion controls will be in place before any significant alteration of the project site and will be removed once the site has been stabilized following construction activities.
(h) No uncured concrete or form materials will be allowed to enter the active stream channel.
(i) Steps to cease work under high flows, except for efforts to avoid or minimize resource damage.
H.5 SPECIAL EQUIPMENT CLEANING REQUIREMENTS
Cleaning of Off-Road Equipment used by the Contractor for contract work shall be conducted outside the boundary of any National Forest Service land prior to moving each piece of equipment onto the project. The Contractor shall notify the Forest Service prior to moving each piece of equipment onto the project. Upon request from the Forest Service, arrangements will be made for Forest Service to inspect each piece of equipment prior to it being placed into service. The Contractor shall use cleaning methods necessary to ensure equipment is free of all attached mud, dirt, and plant parts. If noxious weeds are present at a project site, cleaning may also be required before moving between locations within the same project. These measures will assist to prevent the introduction/spread of the seeds of noxious weeds onto National Forest land. "Off-road Equipment" includes all machinery other than log trucks, chip vans, pickup trucks or vehicles used to transport personnel on a daily basis. Any equipment that will be working instream, and has been utilized for instream work in the past year, must be thoroughly pressure washed with hot water prior to entering National Forest Service land to kill/remove aquatic invasive species. If possible, pressure wash all equipment that will be working instream at 140°F (60°C) or higher for minimum of five minutes or at 120°F or higher for a minimum of 30 minutes.
H.6 USE OF PREMISES
1. A storage site will be permitted at Pine Creek Visitor Center. The Forest Service assumes no liability for materials stored within the storage site. The Contractor will be allowed to erect a temporary fence to secure materials and equipment, however, the fence shall be removed and the site restored prior to final acceptance of the contract.
2. Permanent and temporary electrical power is not available on-site for construction use.
3. Sanitary facilities are not available and are to be provided by the Contractor.
Project Name: FR 90 RD – Seed Task Order Page 17
4. Water for construction is accessible from the Swift boat lauch (Swift Reservoir) or Pine Creek Visitor Center.
H.7 FISH REQUIREMENTS
No sites need fish removal during dewatering.
H.8 DEWATERING AND REWATERING
1. A written dewatering plan shall be prepared prior to the start of the instream work that describes the method of bypass, location, and construction of coffer dams (which must be built with non-erosive materials), the number and size of pumps to be used, and backup plans in place in case of mechanical failure or unanticipated storm events. It is preferred that a bypass pump system is used instead of a hard pipe due to the size of the work area.
2. The dewatering system will be designed and installed to minimize erosion and sediment delivery to the stream, and to withstand all stream flows anticipated during the construction period.
3. Water will be routed downstream of the work site using a by-pass culvert/pump. The bypass discharge point shall be designed to minimize erosion and scour of the stream channel, banks, and vegetation.
4. Diversion sandbags can be filled with material mined from the floodplain as long as such material is replaced at end of project. Small amounts of instream material can be moved to help seal and secure diversion structures.
5. Wastewater from project activities within the dewatered area shall be routed to an area outside the bankfull channel to allow removal of fine sediment and other contaminants prior to infiltrating back into the stream.
6. Upon project completion, slowly re-water the construction site to prevent loss of surface water downstream as the construction site streambed absorbs water and to prevent a sudden release of suspended sediment. Monitor downstream during re-watering to prevent stranding of aquatic organisms below the construction site.
7. Any materials used to construct the dewatering system will be removed prior to the completion of the project.
H.9 HEAVY EQUIPMENT
1. The use of heavy equipment within the bankfull channel of the stream will be minimized where possible. Where such work is necessary, appropriate measures shall be taken to minimize damage to the stream banks and streambed. To the extent feasible, heavy equipment will work from the top of the bank, unless work instream would result in less damage to the aquatic ecosystem.
2. To prevent the introduction and spread of aquatic and terrestrial invasive plants and animals, accumulations of soil and debris shall be removed from the drive mechanisms (wheels, tires, tracks, etc.) and undercarriages of all heavy equipment prior to its working within the bankfull channel of the stream. Any equipment that will be working instream and has been utilized for instream work in the past year, must be thoroughly pressure washed with hot water prior to entering National Forest Service land to kill/remove aquatic invasive species. If possible, pressure wash all equipment that
Project Name: FR 90 RD – Seed Task Order Page 18 will be working instream at 140°F (60°C) or higher for minimum of five minutes or at 120°F or higher for a minimum of 30 minutes.
3. To prevent contamination, equipment used around any streams and wetlands shall be free of external petroleum-based products. Equipment shall be checked daily for leaks and any necessary repairs shall be completed prior to commencing work activities. All machinery fueling and maintenance involving petroleum products shall occur at a sufficient distance from stream channels, waterbodies, or wetlands to prevent delivery of potential contaminants. Spill containment equipment and material shall be on site.
H.10 OTHER REQUIREMENTS
1. Invasive Species Control All materials and equipment used in or near any waterbodies shall be free of aquatic invasive species and noxious weeds. Materials and equipment used at a project site at which aquatic invasive species are already established shall be decontaminated so that no viable aquatic invasive species are transported from the job site.
2. Stockpile Materials
Minimize clearing and grubbing activities when preparing staging, project, and or stockpile areas.
Any large wood, topsoil, and native channel material displaced by construction will be stockpiled for use during site restoration.
3. Temporary Access Roads For this project, only existing roadways will be used. Construction of new permanent roads is not permitted.
4. Timely Completion
Minimize time in which heavy equipment is in stream channels, riparian areas, and wetlands.
Complete earthwork (including drilling, excavation, dredging, filling and compacting) as quickly as possible. During excavation, stockpile native streambed materials above the bankfull elevation, where it cannot reenter the stream, for later use.
5. Site Restoration
Initiate rehabilitation – Upon project completion, rehabilitate all disturbed areas in a manner that results in similar or better than pre-work conditions through removal of project related waste, spreading of stockpiled materials (soil, large wood, trees, etc.), seeding, and mulching. *Note: The USFS will provide the native grass seed mix for all seeding activities.
Decompact soils – Decompact soil by scarifying the soil surface of travel paths, stream crossings, staging, and stockpile areas, as directed by USFS representative.
6. Other A copy of the Memorandum of Understanding between the Washington Department of Fish and Wildlife and the U.S. Forest Service-Region 6 (January 2012) shall be available on site at all times.
Project Name: FR 90 RD – Seed Task Order Page 19
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 CLAUSES
52.217-7 OPTION FOR INCREASED QUANTITY – SEPERATELY PRICED LINE ITEM
(MAR 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within _within 30 days of end of period of performance.
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds –
(1) To unsuccessful bidders as soon as practicable after the opening of bids, and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be _20__ percent of the bid price or $325,000.00_, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(f) Submit bid guarantee documents via electronic submission to Stevonne.fuller@usda.gov. It is the responsibility of the bidder to confirm documents have been received.
mailto:Stevonne.fuller@usda.gov
Project Name: FR 90 RD – Seed Task Order Page 20
PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER
ATTACHMENTS
SECTION J--LIST OF ATTACHMENTS
J.1 ATTACHMENTS
Title Pages
1. Forest Service Supplemental Specifications, FSSS 48
2. Forest Road 90 Roadway Repair Drawings 50
3. Fire Plan - Industrial Fire Precautions Schedule/Level (IFPL) 11
4. DOL Wage Determination WA20230001 MOD 02032023 47
Project Name: FR 90 RD – Seed Task Order Page 21
PART IV--REPRESENTATIONS AND INSTRUCTIONS
SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND
OTHER STATEMENTS OF OFFERORS OR RESPONDENTS
Project Name: FR 90 RD – Seed Task Order Page 22
SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR
RESPONDENTS
L-1 SITE VISIT (FAR 52.236-27)(CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) No pre-bid or site visit is planned. Site visits may be arranged during normal duty hours by contacting COR (Sarah Rockey) or GTM Melissa Jolley.
L.2 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
(Gifford Pinchot National Forest Goals (based on the GP Supervisor’s Office):
Goals for minority participation for each trade Goals for female participation for each trade
_ 3.8% _ ____6.9%_______
These goals are applicable to all the Contractor's construction work performed in the covered area.
If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action’s obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U. S. Department of Labor, within 10 working days following award of any
Project Name: FR 90 RD – Seed Task Order Page 23 construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the--
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is _Washington, Skamania County ________.
Project Name: FR 90 RD – Seed Task Order Page 24
SECTION M--EVALUATION FACTORS FOR AWARD
M.1 PROVISIONS
52.217-5 Evaluations of Options (JUL 1990)
M.2 PROPOSAL EVALUATION
Evaluation will be conducted in accordance with FAR 15.305 Proposal Evaluation as supplemented by information in this solicitation. The government will evaluate proposals and assess their relative qualities solely on the evaluation factors specified in this solicitation.
This solicitation serves as a seed task order in conjunction with the 2023 Road Construction Indefinite Delivery Indefinite Quantity (IDIQ) contract. Due to the technical evaluations being accomplished at the IDIQ level, the sole evaluation criteria for this solicitation is price.
Factor 1. Price The proposed price will be evaluated for reasonableness in accordance with FAR 15.404-1(b).
Note: All offerors must be able to meet the bonding requirements.
| PART I – THE SCHEDULE |
| SECTION A—PROJECT GENERAL INFORMATION |
| A.1 CONTACT INFORMATION: |
| A.2 THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS |
| PART I – SCHEDULE OF ITEMS |
| SECTION B – SUPPLIES, SERVICES AND PRICES |
| B.1 SCHEDULE OF ITEMS |
| SCHEDULE NOTES: |
| SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK |
| C.1 DESCRIPTION OF WORK |
| C.2 PROJECT LOCATION |
| C.3 MAGNITUDE OF CONSTRUCTION PROJECT |
| C.4 PROSECUTION OF WORK |
| C.5 APPLICABLE SPECIFICATIONS AND MATRIAL CETIFICATIONS |
| C-6 SUBMITTALS |
| C.7 CONSTRUCTION PLANS |
| SECTION D--DELIVERIES OR PERFORMANCE |
| SECTION E – INSPECTION AND ACCEPTANCE (Refer to Base IDIQ for Applicable Clauses and Terms) |
| SECTION F--DELIVERIES OR PERFORMANCE |
| F.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) |
| F.2 OTHER REQUIREMENTS |
| SECTION G--CONTRACT ADMINISTRATION DATA |
| G.1 CLAUSES |
| G.2 GOVERNMENT-FURNISHED PROPERTY |
| SECTION H--SPECIAL CONTRACT REQUIREMENTS |
| H.1 SUPPLEMENTAL INFORMATION |
| H.2 EROSION CONTROL MEASURES |
| H.3 LANDSCAPE PRESERVATION – SPILL PREVENTION |
| H.4 POLLUTION AND EROSION CONTROL |
| H.5 SPECIAL EQUIPMENT CLEANING REQUIREMENTS |
| H.6 USE OF PREMISES |
| H.7 FISH REQUIREMENTS |
| H.8 DEWATERING AND REWATERING |
| H.9 HEAVY EQUIPMENT |
| H.10 OTHER REQUIREMENTS |
| PART II--CONTRACT CLAUSES |
| SECTION I--CONTRACT CLAUSES |
| I.1 CLAUSES |
| PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS |
| SECTION J--LIST OF ATTACHMENTS |
| J.1 ATTACHMENTS |
| PART IV--REPRESENTATIONS AND INSTRUCTIONS |
| SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND |
| OTHER STATEMENTS OF OFFERORS OR RESPONDENTS |
| SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR RESPONDENTS |
| L-1 SITE VISIT (FAR 52.236-27)(CONSTRUCTION) (FEB 1995) |
| L.2 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) |
| SECTION M--EVALUATION FACTORS FOR AWARD |
| M.1 PROVISIONS |
| M.2 PROPOSAL EVALUATION |
File details come from the government source that posted it. Updated .