This document is an Invitation for Bidders (IFB) for the MT NP GLAC P HQ(1), GLAC HQ Parking Area Rehabilitation project. The solicitation is for the rehabilitation of the parking areas at the Glacier National Park Headquarters, including construction of new asphalt roads and parking lots, sidewalk replacement, storm drainage improvements, and other associated work.
There are two bid schedules, with only one to be awarded. The solicitation package includes the IFB, construction plans, physical data, and the Construction Contract Administration Document per FAR 36.211. Key details include a requirement for mobilization, construction survey and staking, quality control, testing, and a construction schedule. The project also includes soil erosion and sediment control, temporary and permanent traffic control, and pavement markings. The contracting agency is the Department of Transportation Federal Highway Administration.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DAVID ROEMER
Digitally signed by DAVID
ROEMER
Date: 2024.04.11 17:32:20 -06'00'
EL. 1234.56
BH TP
NO SCALE
θs Ø ∆c spiral central angle diameter curve central angle total central angle approach ahead average daily traffic abutment appr.
AH
ADT
abut.
between bearing bridge balance point bench mark back face back btwn brg.
br.
BP
BM
b.f.
BK
ctrs.
CS
cont.
constr. jt.
conn.
conc.
col.
CMP
clr.
cc or c. to c.
centers point of curve to spiral continuous construction joint connection concrete column corrugated metal pipe clear centerline center to center
W
RIP
DI
G W G WV
E
N 0
CP GPS
SEC. SEC.
36 31
36 31
N
T T
CUYD
culv.
CUFT
cubic yard(s) culvert cubic foot (feet) mon.
min.
MGAL
max.
matl.
M.P.
M.L.
monument minimum thousand gallon maximum material mile post main line
National Boundary
State Boundary
County Boundary
City Boundary
Township or Range Line
Section Line
Section Corner (Found, Projected)
Control Point (Terrestrial and GPS)
Gas & Water Meter; Gas & Water Valve
Flagpole; Fire Hydrant
Cooking Grate; Garbage Can; Picnic Table
Boulder; Well; Antenna; Grave
Above Ground Tank; Underground Tank
Spot Elevation; Coordinate Grid Tick
Material Source; Bore Hole; Test Pit
Treeline; Individual Trees
Spring or Seep
Section Line 4
Section Corner (Found, Projected) 4
Section Line 16
Section Corner (Found, Projected)16
Property Line
Parcel Number
National Park Boundary
National Forest Boundary
National Wildlife Refuge Boundary
BLM Lands Boundary
Indian Reservation Boundary
Existing Roadway (Paved, Gravel)
Railroad
Trail
Fiber Roll
Silt Fence
Sandbag
Intermittent Drainage or Small Creek
Large Creek or River
Lake, Pond or Reservior; Marshland
North Arrow
Slope Stake Limits Top of Cut
Toe of Fill
Construction Limits
Bottom of Ditch
Fence
Gate with Fence
Cattleguard
Guardrail
Concrete Barrier and Guard Wall
Retaining Wall wall face
Signs (single, double post; portable)
Delineators
Pipe Culvert (arrow shows flow)
Pipe Culvert with End Section
Pipe Culvert with Headwall
Pipe Culvert with Drop Inlet
Box Culvert
Underdrain
Overhead/Above Ground Utilities
Underground Utilities
Light, Support w/Anchor) Poles (Power, Telephone, Joint Use, Miscellaneous Utility Features
Building
Right-of-Way Line
Permanent Easement
Construction Easement
Riprap
- no symbol -
Section A-A
EXISTING PROPOSED
STEAM = steam, T = telephone, TV = CATV, W = water P = power, SA = sanitary sewer, SD = storm drain, SS = storm sewer, FM = force main, FO = fiber optic, G = gas, IRR = irrigation, O = oil, UP = transformer or junction box, WF = water fountain EM = electric meter, T = telephone pedestal, TV = CATV pedestal,
- no symbol -
DI
A A
NOTE:
1.
on the appropriate plan sheet.
Other symbols used in the plans will be shown in a legend
W west drwg(s).
dist.
diaph.
dia.
DHV
D exp. jt.
exc.
EW
EQ or eq.
EOP
emb.
elev.
El. 94.16 e.f.
e E expansion joint excavation edge of water equation edge of pavement embankment elevation elevation in feet each face superelevation rate east drawing(s) distance diaphragm diameter design hourly volume diameter galv.
ga.
galvanized gage (gauge) jt.
IE
ID
joint invert elevation inside diameter ftg.
flg.
fin.
f.f.
footing flange finish front face
LW
lt. or LT Ls
LPSM
long.
LNFT
lat.
L low water left length of spiral lump sum longitudinal linear foot (feet) latitude length of curve rte.
rt. or RT reqd.
reinf.
rdwy.
R/W R.
R route right required reinforcement roadway right-of-way range radius typ.
Ts
TS
thd.
TBM
T.
T typical tangent distance (spiraled curve) point of tangent to spiral thread temporary bench mark township tangent distance
VPI
vph V vertical point of intersection vehicles per hour design speed (velocity)
STS
struc.
stiff.
stgr.
std.
STA, Sta.
ST
SS
SRS
SQYD
SQFT
spa.
SLRY
shldr.
sect.
SC
SADT
S point of spiral to tangent spiral structural stiffener stringer standard station point of spiral to tangent point of spiral to spiral (no curve) point of spiral to reverse spiral square yard square foot spacing, spaces or spaced slurry unit shoulder section point of spiral to curve seasonal average daily traffic south
KSI
square inch thousand pounds per pvmt.
PT
PST
PSC
PSI
PSF
PS
POT
POS
POC
pl.
PI
PCS
PCC
PC
pavement point of tangent point of spiral to tangent point of spiral to curve pounds per square inch pounds per square foot point of tangent to spiral point on tangent point on spiral point on curve plate point of intersection point of curve to spiral point of compound curve point of curve
OHWM
OG
OD
o. to o.
o.c.
ordinary high water mark original ground outside diameter out to out on center
NC
N normal crown north
11/2001 DETAIL APPROVED FOR USE
6/2022
10/2014 10/2009 1/2007 9/2005 REVISED: 101-1 W
ABBREVIATIONS
PLAN SYMBOLS AND
:1
P
M
A p ri l
P la n S y m b o ls a n d A b b re v ia ti o n s c p w
-w o rk
\d \g la c -p
-h q p ln g e n .d g n
WFLHD DETAIL
DETAIL
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
PROJECT
NUMBER
SHEET
A.2
NPS PMIS No. 319138 & 319139
MT NP GLAC P HQ (1)
S o y e n C ir c le
N
RESUME PROJECT
MAINTENANCE AREA
VINT BLVD
PARKING AREA
EMPLOYEE
SUSPEND PROJECT
SUSPEND PROJECT
BEGIN PROJECT
Middle Fork
Flathead River
G r in n e ll D r
Vint Blvd
Mather Dr.
G o in g T o T h e S u n R o a d
Going To The Sun Road
M id d le F o rk F la th e a d R iv e r
O ld R iv e r
B ri dg e R d
O ld R iv e r B r id g e R d
West Glacier
C o lu m b ia F a ll s
.1 m il e s
E a st G la ci e r
P a rk V il la g e
.4 m il e ain t M ary 8 .9 M iles
Headquarters Rd.
K a li s p e ll m il e s
Glacier Route 1 Road
"ML HQ2" 200+20.33
"ML HQ2" 200+68.43
"HZ_Vint_Blvd" 102+52.39
"HZ_Vint_Blvd" 100+12.00
:1 p ri l
V ic in it y M a p p w
-w o rk
\d \g la c -p
-h q p ln g e n .d g n
VICINITY MAP
PROJECT
A.3
Sheet and Description
SECTION D SECTION E SECTION F SECTION G SECTION H
PLAN AND
PROFILE
APPROACH ROADS
AND PARKING
AREAS
SOIL EROSION
AND SEDIMENT
CONTROL
TEMPORARY
TRAFFIC CONTROL
PLAN
PERMANENT
TRAFFIC CONTROL
PLAN
ALLOWANCE Bid
Schedule
A0020 15101-0000 MOBILIZATION LPSM ALL
A0030 15201-0000 CONSTRUCTION SURVEY AND STAKING LPSM ALL
A0040 15301-0000 CONTRACTOR QUALITY CONTROL LPSM ALL
A0050 15301-0010 CONTRACTOR QUALITY CONTROL AND
ASSURANCE LPSM ALL
A0060 15401-0000 CONTRACTOR TESTING LPSM ALL
A0070 15501-0000 CONSTRUCTION SCHEDULE LPSM ALL
A0080 15705-1400 SOIL EROSION CONTROL, FIBER ROLL LNFT 4,140 460 4,600
A0090 15706-0200 SOIL EROSION CONTROL, CHECK DAM
(FIBER ROLL) EACH 3 3
A0100 15706-1100 SOIL EROSION CONTROL, INLET
PROTECTION TYPE A EACH 1 1
A0110 15706-1200 SOIL EROSION CONTROL, INLET
PROTECTION TYPE B EACH 2 2
A0120 20103-0000 CLEARING AND GRUBBING SQYD 432 4,009 259 4,700
A0130 20220-1000 REMOVAL, INDIVIDUAL TREE EACH 8 8
A0140 20301-0500 REMOVAL OF CATCH BASIN EACH 2 2
A0150 20301-1300 REMOVAL OF INLET GRATE EACH 2 2
A0160 20301-2400 REMOVAL OF SIGN EACH 3 3
A0170 20302-0300 REMOVAL OF CURB AND GUTTER,
CONCRETE LNFT 1,180 60 1,240
A0180 20303-3200 REMOVAL OF SIDEWALK, CONCRETE SQYD 620 30 650
A0190 20315-0000 SAWCUTTING PAVEMENT LNFT 257 13 270
A0200 20401-0000 ROADWAY EXCAVATION CUYD 304 4,944 552 5,800
A0210 20402-0000 SUBEXCAVATION CUYD 227 26 253
A0220 20435-2000 BACKFILL, GRANULAR CUYD 93 10 103
A0230 20702-0100 GEOTEXTILE FILTER, CLASS 1, TYPE A SQYD 10 10
A0240 20702-0800 GEOTEXTILE FILTER, CLASS 2, TYPE C SQYD 108 11 119
A0250 25101-0200 PLACED RIPRAP, METHOD A, CLASS 2 CUYD 2 1 3
A0260 30202-2000 ROADWAY AGGREGATE, METHOD 2 TON 489 5,264 447 6,200
A0270 31302-0400 AGGREGATE-TOPSOIL COURSE, 4-INCH
DEPTH SQYD 121 377 52 550
A0280 40301-0000 ASPHALT CONCRETE PAVEMENT TON 217 2,448 235 2,900
A0290 41201-0000 TACK COAT TON 1 5 1 7
A0300 60404-1000 CATCH BASIN, FLH TYPE 1 EACH 2 2
A0310 60405-0000 MANHOLE ADJUSTMENT EACH 7 7
A0320 60409-0200 INLET TOP, METAL FRAME AND GRATE,
FLH TYPE B EACH 2 2
A0330 60704-0000 CLEANING CULVERT IN PLACE EACH 2 2 4
MileStone: 100% FINAL Date Completed: 04/11/24 Report Date: 04/11/24
A M E N D
Line Item No.
Pay Item Number
SUMMARY OF QUANTITIES - Schedule A
-A pr
-2
:3
AM
Remarks and/or Determination of Estimated QuantityPay Item Description Unit
Estimated Quantities
C pw -w or k\ d0 gl ac -p
-h q1
-s um m ar y.
xl sm ]S he et
PROJECT
B.1MT NP GLAC P HQ (1)
SECTION D SECTION E SECTION F SECTION G SECTION H
PLAN AND
PROFILE
APPROACH ROADS
AND PARKING
AREAS
SOIL EROSION
AND SEDIMENT
CONTROL
TEMPORARY
TRAFFIC CONTROL
PLAN
PERMANENT
TRAFFIC CONTROL
PLAN
ALLOWANCE Bid
Schedule
A0340 60902-1000 CURB AND GUTTER, CONCRETE, 12-INCH
DEPTH LNFT 1,200 60 1,260
A0350 60915-1000 WHEELSTOP, CONCRETE EACH 41 41
A0360 61108-1000 ADJUST WATER VALVE EACH 9 9
A0370 61108-4000 ADJUST VALVE BOX (MONITORING WELL) EACH 1 1
A0380 61501-0600 SIDEWALK, EXPOSED AGGREGATE
COLORED CONCRETE SQYD 619 31 650
A0390 62502-0000 TURF ESTABLISHMENT (LAWN SEED) SQYD 34 230 16 280
A0400 62502-0000 TURF ESTABLISHMENT (GOVERNMENT
PROVIDED SEED) SQYD 323 3,499 188 4,010
A0410 63302-0000 SIGN SYSTEM SQFT 12 12
A0420 63316-1000 REMOVE AND RESET SIGN EACH 5 5
A0430 63318-1000 SNOW POLE HOLDER EACH 68 68
A0440 63401-0700 PAVEMENT MARKINGS, TYPE D, SOLID
(WHITE) LNFT 2,589 91 2,680
A0450 63405-1350 PAVEMENT MARKINGS, TYPE D,
STRAIGHT ARROW EACH 5 5
A0460 63502-0600 TEMPORARY TRAFFIC CONTROL,
BARRICADE TYPE 3 EACH 6 6
A0470 63502-1250 TEMPORARY TRAFFIC CONTROL, TUBULAR
MARKER, TYPE 42-INCH EACH 35 35
A0480 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING
LIGHT TYPE B EACH 6 6
A0490 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC
FENCE LNFT 1,400 1,400
A0500 63504-1000 TEMPORARY TRAFFIC CONTROL,
CONSTRUCTION SIGN SQFT 87 87
A0510 63610-1600 CONDUIT, 2-INCH, PVC LNFT 128 12 140
A0520 64620-0400 REMOVE AND RESET MAILBOX EACH 1 1
-A pr -2
:3
AM
MileStone: 100% FINAL Date Completed: 04/11/24 Report Date: 04/11/24
C pw -w or k\ d0 gl ac -p
-h q1
-s um m ar y.
xl sm ]S he et
2)
SUMMARY OF QUANTITIES - Schedule A
A M E N D
Line Item No.
Pay Item Number Pay Item Description Unit
Estimated Quantities
Remarks and/or Determination of Estimated Quantity
PROJECT
B.2MT NP GLAC P HQ (1)
SECTION D SECTION E SECTION F SECTION G SECTION H
PLAN AND
PROFILE
APPROACH ROADS
AND PARKING
AREAS
SOIL EROSION
AND SEDIMENT
CONTROL
TEMPORARY
TRAFFIC CONTROL
PLAN
PERMANENT
TRAFFIC CONTROL
PLAN
ALLOWANCE Bid
Schedule
B0020 15101-0000 MOBILIZATION LPSM ALL
B0030 15201-0000 CONSTRUCTION SURVEY AND STAKING LPSM ALL
B0040 15301-0000 CONTRACTOR QUALITY CONTROL LPSM ALL
B0050 15301-0010 CONTRACTOR QUALITY CONTROL AND
ASSURANCE LPSM ALL
B0060 15401-0000 CONTRACTOR TESTING LPSM ALL
B0070 15501-0000 CONSTRUCTION SCHEDULE LPSM ALL
B0080 15705-1400 SOIL EROSION CONTROL, FIBER ROLL LNFT 4,140 460 4,600
B0090 15706-0200 SOIL EROSION CONTROL, CHECK DAM
(FIBER ROLL) EACH 3 3
B0100 15706-1100 SOIL EROSION CONTROL, INLET
PROTECTION TYPE A EACH 1 1
B0110 15706-1200 SOIL EROSION CONTROL, INLET
PROTECTION TYPE B EACH 2 2
B0120 20103-0000 CLEARING AND GRUBBING SQYD 432 4,009 259 4,700
B0130 20220-1000 REMOVAL, INDIVIDUAL TREE EACH 8 8
B0140 20301-0500 REMOVAL OF CATCH BASIN EACH 2 2
B0150 20301-1300 REMOVAL OF INLET GRATE EACH 2 2
B0160 20301-2400 REMOVAL OF SIGN EACH 3 3
B0170 20302-0300 REMOVAL OF CURB AND GUTTER,
CONCRETE LNFT 1,180 60 1,240
B0180 20303-3200 REMOVAL OF SIDEWALK, CONCRETE SQYD 620 30 650
B0190 20315-0000 SAWCUTTING PAVEMENT LNFT 257 13 270
B0200 20401-0000 ROADWAY EXCAVATION CUYD 490 6,963 747 8,200
B0210 20402-0000 SUBEXCAVATION CUYD 227 26 253
B0220 20411-0000 SELECT BORROW TON 344 3,735 321 4,400
B0230 20435-2000 BACKFILL, GRANULAR CUYD 93 10 103
B0240 20702-0100 GEOTEXTILE FILTER, CLASS 1, TYPE A SQYD 10 10
B0250 20702-0800 GEOTEXTILE FILTER, CLASS 2, TYPE C SQYD 108 11 119
B0260 25101-0200 PLACED RIPRAP, METHOD A, CLASS 2 CUYD 2 1 3
B0270 30202-2000 ROADWAY AGGREGATE, METHOD 2 TON 489 5,264 447 6,200
B0280 31302-0400 AGGREGATE-TOPSOIL COURSE, 4-INCH
DEPTH SQYD 121 377 52 550
B0290 40301-0000 ASPHALT CONCRETE PAVEMENT TON 217 2,448 235 2,900
B0300 41201-0000 TACK COAT TON 1 5 1 7
B0310 60404-1000 CATCH BASIN, FLH TYPE 1 EACH 2 2
B0320 60405-0000 MANHOLE ADJUSTMENT EACH 7 7
B0330 60409-0200 INLET TOP, METAL FRAME AND GRATE,
FLH TYPE B EACH 2 2
B0340 60704-0000 CLEANING CULVERT IN PLACE EACH 2 2 4
-A pr -2
:3
AM
MileStone: 100% FINAL Date Completed: 04/11/24 Report Date: 04/11/24
C pw -w or k\ d0 gl ac -p
-h q1
-s um m ar y.
xl sm ]S he et
3)
SUMMARY OF QUANTITIES - Schedule B
A M E N D
Line Item No.
Pay Item Number Pay Item Description Unit
Estimated Quantities
Remarks and/or Determination of Estimated Quantity
PROJECT
B.3MT NP GLAC P HQ (1)
SECTION D SECTION E SECTION F SECTION G SECTION H
PLAN AND
PROFILE
APPROACH ROADS
AND PARKING
AREAS
SOIL EROSION
AND SEDIMENT
CONTROL
TEMPORARY
TRAFFIC CONTROL
PLAN
PERMANENT
TRAFFIC CONTROL
PLAN
ALLOWANCE Bid
Schedule
B0350 60902-1000 CURB AND GUTTER, CONCRETE, 12-INCH
DEPTH LNFT 1,200 60 1,260
B0360 60915-1000 WHEELSTOP, CONCRETE EACH 41 41
B0370 61108-1000 ADJUST WATER VALVE EACH 9 9
B0380 61108-4000 ADJUST VALVE BOX (MONITORING WELL) EACH 1 1
B0390 61501-0600 SIDEWALK, EXPOSED AGGREGATE
COLORED CONCRETE SQYD 619 31 650
B0400 62502-0000 TURF ESTABLISHMENT (GOVERNMENT
PROVIDED SEED) SQYD 323 3,499 188 4,010
B0410 62502-0000 TURF ESTABLISHMENT (LAWN SEED) SQYD 34 230 16 280
B0420 63302-0000 SIGN SYSTEM SQFT 12 12
B0430 63316-1000 REMOVE AND RESET SIGN EACH 5 5
B0440 63318-1000 SNOW POLE HOLDER EACH 68 68
B0450 63401-0700 PAVEMENT MARKINGS, TYPE D, SOLID
(WHITE) LNFT 2,589 91 2,680
B0460 63405-1350 PAVEMENT MARKINGS, TYPE D,
STRAIGHT ARROW EACH 5 5
B0470 63502-0600 TEMPORARY TRAFFIC CONTROL,
BARRICADE TYPE 3 EACH 6 6
B0480 63502-1250 TEMPORARY TRAFFIC CONTROL, TUBULAR
MARKER, TYPE 42-INCH EACH 35 35
B0490 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING
LIGHT TYPE B EACH 6 6
B0500 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC
FENCE LNFT 1,400 1,400
B0510 63504-1000 TEMPORARY TRAFFIC CONTROL,
CONSTRUCTION SIGN SQFT 87 87
B0520 63610-1600 CONDUIT, 2-INCH, PVC LNFT 128 12 140
B0530 64620-0400 REMOVE AND RESET MAILBOX EACH 1 1
-A pr -2
:3
AM
MileStone: 100% FINAL Date Completed: 04/11/24 Report Date: 04/11/24
C pw -w or k\ d0 gl ac -p
-h q1
-s um m ar y.
xl sm ]S he et
4)
SUMMARY OF QUANTITIES - Schedule B
A M E N D
Line Item No.
Pay Item Number Pay Item Description Unit
Estimated Quantities
Remarks and/or Determination of Estimated Quantity
PROJECT
B.4MT NP GLAC P HQ (1)
LC
with tack coat between lifts
4-inch compacted depth, placed in two equal lifts, Asphalt concrete pavement, 8-inch compacted depth
Roadway aggregate, method 2
Select borrow, 6-inch compacted depth (Schedule B Only)
Existing ground
Existing ground course, 4-inch depth
Aggregate topsoil topsoil course, 4-inch depth
Aggregate
LC
with tack coat between lifts
4-inch compacted depth, placed in two equal lifts, Asphalt concrete pavement, 8-inch compacted depth
Roadway aggregate, method 2
Select borrow, 6-inch compacted depth (Schedule B Only)
Existing ground course, 4-inch depth
Aggregate topsoil course, 4-inch depth
Aggregate topsoil
Profile grade
VINT BLVD
"HZ_Vint_Blvd" 100+12.33 to 102+52.39
Shldr
2'
Travel way
10'
Travel way
10'
Shldr
2'
Varies
Varies
C o n s tr u c ti o n l im it s
C o n s tr u c ti o n l im it s limit
Turf establishment limit
Turf establishment
Existing ground
Profile grade
HEADQUARTERS ROAD
"ML_HQ2" 200+20.33 to 200+68.43
C o n s tr u c ti o n l im it s
C o n s tr u c ti o n l im it s
Travel way
9'
Travel way
9'
Shldr
1'
Shldr
1' limit
Turf estamlishment limit
Turf estamlishment
Varies Varies
�2% 2%�
E x is ti n g U ti li ty
�2% 2%�
E x is ti n g U ti li ty
:0
A p ri l
T y p ic a l S e c ti o n s o f p w
-w o rk \d
\g la c -p
-h q
-p ln -t y p
.d g n
TYPICAL SECTIONS
PROJECT
C.1
:1
A p r il
S u r v e y
C o n tr o l p w w o r k \d
\g la c p h q p ln p p .d g n
SURVEY CONTROL
PROJECT
D.1
NOTE:
Additional material needed for embankment construction (Item 20411-0000 Select Borrow, Item 20435-2000 Backfill Granular, Item 25101-0200 Placed Riprap Method A, Class 2).
Additional material that is sutable for use in embankment construction (Item 20402-0000 Subexcavation)
All volumes are in-place cubic yards (i.e. in situ or compacted in place).
3.
2.
1.
:1
A p r il
T a b u la ti o n o f q u a n ti ti e s o f p w w o r k \d
\g la c p h q p ln p p .d g n
(1 OF 3)
PROFILE QUANTITIES
TABULATION OF PLAN AND
PROJECT
D.2
:4
A p r il
T a b u la ti o n o f q u a n ti ti e s o f p w w o r k \d
\g la c p h q p ln p p .d g n
(2 OF 3)
PROFILE QUANTITIES
TABULATION OF PLAN AND
PROJECT
D.3
FOOTNOTE:
See Sheet E.8 for locations
[1]
:4
A p r il
T a b u la ti o n o f q u a n ti ti e s o f p w w o r k \d
\g la c p h q p ln p p .d g n
(3 OF 3)
PROFILE QUANTITIES
TABULATION OF PLAN AND
PROJECT
D.4
W V N
U T
S S
S I D
E W
A L
K P
A V
E D
D I
D I
L
ID
N constructed
Line to be limit
Construction
Construction limit
[2] underground gas
Existing sewer
Existing underground culvert in place
Cleaning
Edge of pavement underground power sewer
Existing underground
.0
R t
.3
9CP
23-HQ103
51.24' Lt
+11.27
64.44' Rt
+12.92
.9
L t
.5
.0
L t
.1
.3
L t
.2
.9
R t
.1
Profile grade
Existing ground
SCHEDULE A & B
BEGIN PROJECT SCHEDULE A & B
SUSPEND PROJECT
PAVEMENT CONNECTION DETAIL
NTS
.2
B e g in P r o je c t tack coat joint
4" Vertical saw cut,pavement
Existing
See Sheet C.1
Pavement structure, culvert in place
Cleaning
PI 100+96.71
Δ = 00°26'54" (RT)
R = 15,000.00' T = 58.70' L = 117.39'
PI 102+58.56
Δ = 00°14'10" (LT)
R = 25,000.00' T = 51.51' L = 103.02'
S24°37'21"E S24°10'26"E
P C
.0
P C
.0
P T
.4
'R
100+00 101+00 102+00
3,190 3,190
3,200 3,200
3,210 3,210
LP
.5
L
.3
H
.4
,1
.7
+0.00%
,1
.1
-0.71% -0.67%
.0
.3
.0
.0
.0
.9
9SSD = 915'
K = 41
50' VC
HLSD = INF'
K = 56
70' VC
HLSD = INF'
K = 41
50' VC
0.55%
SSSS
VINT BLVD
.7
.0
L t
.3
.0
L t
G R
IN
N E L D
R
IV
E
HEADQUARTERS
EMPLOYEE PARKING AREA
VINT BLVD
MAINTENANCE AREA
See Sheet E.7
50'R
.1
.0
R t
.1
.0
L t
.2
.0
' L t
VINT BLVD
"HZ_Vint_Blvd" 100+12.33
VINT BLVD
"HZ_Vint_Blvd" 102+52.39
E= 881,863.6001 N= 1,581,474.3454
E= 881,764.5179 N=1,581,693.3624
FOOTNOTE:
Protect existing utilities.
or coordinate repair with the CO as needed.
Determine culvert locations/depths. Protect
Protect existing trees not identified for removal.1.
:5
A p ri l
V in t_ B lv d
P la p w
-w o rk \d
\g la c -p
-h q p ln p p .d g n
PROJECT
D.5
CURB
DAMAGED
TP
TP
CNP1 1
JB
G
W V
267080
S I D
E W
A L
K C
O N
C R
E T
E
Edge of pavement
N limit
Construction
Construction limit
Existing underground power power
Existing
.2
' L t
.8
Profile grade
Existing ground
PAVEMENT CONNECTION DETAIL
NTS
.3
R e s u m e P r o je c t tack coat joint
4" Vertical saw cut,pavement
Existing
See Sheet C.1
Pavement structure, SCHEDULE A & B
RESUME PROJECT
SCHEDULE A & B
SUSPEND PROJECT
gas phone
Existing underground
N59°36'33"E N63°48'26"E
PI 200+28.50
Δ = 04°11'52" (RT)
R = 777.00' T = 28.48' L = 56.93' e = ___
P C
.0
P T
.9
200+00 201+00
3,190 3,190
3,200 3,200
3,210 3,210
,2
.1
-0.52% +0.99%
.0
.4
L P
.1
HLSD = INF'
K = 33
50' VC3
,2 .8
Line to be constructed limit Construction
HEADQUARTERS ROAD
H E
A D
Q U
A R
T E
R
P L
O Y
E E
P A
R K
IN
G A
R E
A
.1
.0
L t
.1
.0
R t
.7
.0
L t
.3
.0
R T
.1
.0
R t
See Sheet E.7
VINT BLVD MAINTENANCE AREA
NOTE:
Protect existing trees not identified for removal.1.
FOOTNOTE:
Protect existing utilities.
[1]
HEADQUARTERS ROAD
"ML_HQ2" 200+20.33
E= 881,879.2635 N= 1,581,019.1828
HEADQUARTERS ROAD
"ML_HQ2" 201+68.43
E= 882,011.7638 N=1,581,085.3221
:4
A p ri l
H e a d q u a rt e rs
R o a d
P la n a n d
P ro fi le p w
-w o rk \d
\g la c -p
-h q p ln p p .d g n
PROJECT
D.6
Quantity includes 84 TON to be used as directed by CO. See Sheet E.8.
Quantity includes 168 TON to be used as directed by CO. See Sheet E.8.
:5
A p r il
T a b u la ti o n P a r k in g
A r e a Q u a n ti ti p w w o r k
\d
\g la c p h q p ln m is c .d g n
QUANTITIES
TABULATION OF PARKING AREA
PROJECT
E.1
See Utility Trench Details Sheet E.11
See Manhole and Valve Box Adjaustment Details Sheet E.11
:5
A p r il
T a b u la ti o n o f p a r k in g a r e a q u a n ti ti p w w o r k
\d
\g la c p h q p ln m is c .d g n
QUANTITIES
TABULATION OF PARKING AREA
PROJECT
E.2
Back of curbBOC=
Point of tangentPT=
Vertical Point of IntersectionVPI=Center of curveC.C.=
Edge of SidewalkEOS=Point of curvaturePC=
Back of SidewalkBOS=Edge of pavement EOP=
Abbreviations
All elevations are top of finished grade.1.
NOTE:
:5
A p r il
H e a d q u a r te r s E m p lo y r k in g
A r e a
S h e e t o f p w w o r k
\d
\g la c p h q p ln m is c .d g n
(SHEET 1 OF 2)
PARKING AREA
HEADQUARTERS EMPLOYEE
PROJECT
E.3
D I
D I
D I
S S
C N
P
D I
P
H O
N E V
A U
L T L
ID
D I
SS
SS
SS
R
20'R
R
R
R
R
'R
21'R 21 R
R
R
N
35 4
124 125
128 129
137 138
145 146 concrete 12" depth
Curb and gutter, limits
Construction
Construction limits
Construction limits
Construction limits aggregate colored concrete
Sidewalk, exposed aggregate colored concrete
Sidewalk, exposed aggregate colored concrete
Sidewalk, exposed
Remove reset mailbox
Removal, individual trees tree (approximate)
Removal, individual and gutter, concrete
Removal of curb individual trees
Removal, SD_PROFILE1 underground phone
Existing
Removal inlet grate
Removal of catch basin and grate, FLH type b
Inlet top, metal frame
Catch basin, type 1 adjustment - SSMH-41
Manhole adjustment - SSMH-42
Manhole in place
Cleaning culvert in place
Cleaning culvert valve No. 1 & 2
Adjust water underground water undergound telephone underground sewer
Existing and grate, FLH type b
Inlet top, metal frame
Catch basin, type 1
(monitoring well)
Adjust valve box
GPS
HQ102
CP
HQ107
CP
HQ106
CP
122A
122B
133A
R
B
B
A A
VINT BLVD
VINT BLVD MAINTANECE AREA
H
Q R
O A
D
GLACIER NATIONAL PARK
HEADQUARTERS BUILDING
40 8040 0
Scale in feet
NOTE:
Protect existing trees not identified for removal.1.
FOOTNOTE:
Protect existing utilities.
or coordinate repair with the CO as needed.
Determine culvert locations/depths. Protect
:4
A p r il
H e a d q u a r te r s E m p lo y e e P a r k in g
A r e a
S h e e t o f p w w o r k
\d
\g la c p h q p ln m is c .d g n
(SHEET 2 of 2)
EMPLOYEE PARKING AREA
HEADQUARTERS
PROJECT
E.4 placed in two equal lifts
4-inch compacted depth, Asphalt concrete pavement, 8-inch compacted depth
Roadway aggregate, method 2
Select borrow, 6-inch compacted depth (Schedule B Only)
Select borrow, 6-inch compacted depth (Schedule B Only)
8-inch compacted depth
Roadway aggregate, method 2 placed in two equal lifts
4-inch compacted depth, Asphalt concrete pavement, 12-inch depth
Curb and gutter, concrete, colored concrete, 4-inch depth
Sidewalk, exposed aggregate colored concrete, 4-inch depth
Sidewalk, exposed aggregate concrete, 12-inch depth
Curb and gutter, concrete, 12-inch depth
Curb and gutter, 12-inch depth
Curb and gutter, concrete, Existing ground
Existing ground
Existing ground
Existing ground
Existing ground
Minimize disturbace to vegitation.
8' 1.5'
43' 1.5'
1.5' 40.8'1.5'
8'
1.0%�
1.0%�
C o n s tr u c ti o n l im it s
C o n s tr u c ti o n l im it s
C o n s tr u c ti o n l im it s
C o n s tr u c ti o n l im it s
5'
5'
3'
3'
SECTION A-A
SECTION B-B
li m it s
C o n s tr u c ti
3' 3'Do not disturb existing vegetation li m it s
C o n s tr u c ti
1.5% Max�
1.5% Max� S a n it a ry S e w r
No Scale
:1
A p ri l
H e a d q u a rt e rs
E m p lo y e e P a rk in g
A re a S e c ti o p w
-w o rk \d
\g la c -p
-h q p ln m is c
.d g n
PARKING AREA SECTIONS
HEADQUARTERS EMPLOYEE
PROJECT
E.5
All elevations are top of finished grade.
1.
Vertical Point of IntersectionVPI=
Point of tangentPT=
Center of curveC.C.=
Point of curvaturePC=
Edge of pavement EOP=
Abbreviations
:0
A p r il
V in t
B lv d M a in te n a c e A r e a
S h e e t o f p w w o r k
\d
\g la c p h q p ln m is c .d g n
(SHEET 1 OF 3)
VINT BLVD MAINTENACE AREA
PROJECT
E.6
D I
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
P
H O
N E V
A U
L T L
ID
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
SS
SS
N
Edge of pavement
Preserve and protect
Existing fuel island.
201 202
Construction limits
Construction limits
HQ102
GPS
HQ108
CP
HQ101
GPS
Edge of pavement
Edge of pavement
Slope stake limits
SD_PROFILE2
dissipator
Energy adjustment - SSMH-40
Manhole
Adjust water valve No. 3-5 underground fiber optic
Existing
Construction limits
258259 257
264265266
268 269
Trails Storage BLDG 243
Roads Storage
BLDG 236
Roads Storage
BLDG 232
Existing Building
Existing
Building
Museum Storage
BLDG 1521
R
50'R
40 8040 0
Scale in feet
C
C
VINT BLVD
H E
A D
Q U
A R
T E
R S R
O A
D
NOTE:
Protect existing trees not identified for removal.1.
[1] Preserve and protect existing utilities.
:4
A p r il
V in t
B lv d M a in te n a c e A r e a
S h e e t o f p w w o r k
\d
\g la c p h q p ln m is c .d g n
(SHEET 2 OF 3)
MAINTENACE AREA
VINT BLVD
PROJECT
E.7
P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
E X
R A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
D I
S S
S S
E X
R
SS
SS
SS
SS
Pavement
Sawcutting
Pavement
Sawcutting
Pavement
Sawcutting
R
R
N
Do not disturb
Existing fuel island.
Rock swale
285 283
Edge of pavement
Edge of pavement
Slope stake limits
Construction limits
Construction limits Construction limits
Construction limits
Construction limits
207 208 209 210 211
SD_PROFILE3
by the CO.
shown, as directed approximate limits
Extend paving to adjustment - SSMH-61
Manhole adjustment - SSMH-58
Manhole adjustment - SSMH-49
Manhole adjustment - SSMH-50
Manhole
Adjust water valve No. 6
Adjust water valve No. 7-9 underground water
Existing
(4) Conduit, 2-inch, PVC
23-HQ211
CP
CP
23-HQ210
222 223
242244 243
246247
NTS
See Sheets E.9-10 structure, Pavement pavement
Existing tack coat joint
4" Vertical saw cut, PAVEMENT CONNECTION DETAIL tree (2)
Removal of individual
Slope stake limits
R
R
'R
R
Roads Storage
BLDG 232
Storage BLDG 231 Radio and Utilities
BLDG 220
Trails Storage
BLDG 243
Facilities Offices
BLDG 217
LE BLDG 210
R 3
R
R
R
R
R
75'
Construction limits
1"=40'
Campgrounds Storage
BLDG 243
Plumbing Shop
BLDG 208
40 8040 0
Scale in feet
D
D E
E F
F
NOTE:
Protect existing utilities.
Protect existing trees not identified for removal.
2.
1.
NOTE:
Protect existing trees not identified for removal.1.
[1] Preserve and protect existing utilities.
:0
A p r il
V in t
B lv d M a in te n a c e A r e a
S h e e t o f p w w o r k
\d
\g la c p h q p ln m is c .d g n
(SHEET 3 OF 3)
MAINTENACE AREA
VINT BLVD
PROJECT
E.8
Asphalt concrete pavement, Existing ground course, 4" depth
Aggregate topsoil method 2, 8-inch compacted depth
Roadway aggregate, Select borrow, 6-inch compacted depth (Schedule B Only) method 2, 4-inch compacted depth
Roadway aggregate, placed in two equal lifts
4-inch compacted depth, Asphalt concrete pavement, 8-inch compacted depth
Roadway aggregate, method 2, Select borrow, 6-inch compacted depth (Schedule B Only) placed in two equal lifts
4-inch compacted depth, Asphalt concrete pavement, 8-inch compacted depth
Roadway aggregate, method 2, Select borrow, 6-inch compacted depth (Schedule B Only)
Existing fuel island
Drip line
Drip line
Existing gravel
Existing gravel
SECTION C-C
C o n s tr u c ti o n l im it s
C o n s tr u c ti o n l im it s
1%�
�1.5% .5%�
SECTION D-D
C o n s tr u c ti o n l im it s
C o n s tr u c ti o n l im it s
F a c e o f b u il d in g
F a c e o f b u il d in g
No Scale
:1
A p ri l
V in t B lv d
M a in t
A re a S e c ti o n s
S h e e t o f p w
-w o rk \d
\g la c -p
-h q p ln m is c
.d g n
(SHEET 1 OF 2)
AREA SECTIONS
VINT BLVD MAINTENANCE
PROJECT
E.9
Asphalt concrete pavement, 8-inch compacted depth
Roadway aggregate, method 2, Select borrow, 6-inch compacted depth (Schedule B Only)
Drip line
Drip line
Existing gravelExisting gravel placed in two equal lifts
4-inch compacted depth, Asphalt concrete pavement, 8-inch compacted depth
Roadway aggregate, method 2, Select borrow, 6-inch compacted depth (Schedule B Only) placed in two equal lifts
4-inch compacted depth, Asphalt concrete pavement, 8-inch compacted depth
Roadway aggregate, method 2, Select borrow, 6-inch compacted depth (Schedule B Only)
Existing ground
Rock swale
4'
4' course, 4" depth
Aggregate topsoil course, 4" depth
Aggregate topsoil
�1.3 .5%�
SECTION E-E
F a c e o f b u il d in g
F a c e o f b u il d in g
�2.1%
�Varies
1.1%�
Varies�
SECTION F-F
C o n s tr u c ti o n l im it s
C o n s tr u c ti o n l im it s
4'
No Scale
:1
A p ri l
V in t B lv d
M a in t
A re a S e c ti o n s
S h e e t o f p w
-w o rk \d
\g la c -p
-h q p ln m is c
.d g n
(SHEET 2 OF 2)
AREA SECTIONS
VINT BLVD MAINTENANCE
PROJECT
E.10
Top of new pavement
Concrete collar
(2" min. - 12" max.)
rings as necesary
Concrete adjustingmanhole and grate
Existing base and subgrade
Compacted base and subgrade
Compacted
Concrete collar
Top of new pavement
Pull rope joint filler around conduit
Provide pre-molded
Finished grade
Conduit, 2-inch, pvc typ. both ends
90 deg. elbow, cap, typ., both ends
Threaded pvc conduit
CAUTION
LINE BELOW
BURIED __________
CAUTION
LINE BELOW
BURIED __________
Insert applicable text
Repeating text
Red text )
Detectable warning tape (5 mils thick, Granular backfill
Conduit, 2 -Inch, pvc (x4)
Pavement structure
Finished grade
Install warning tape (x 4)
12" 4" max.
6"
4" max.
MANHOLE ADJUSTMENT DETAIL VALVE BOX ADJUSTMENT DETAIL
24"
STUBOUT DETAIL
WARNING TAPE DETAIL
UTILITY TRENCH DETAIL
38"
Compacted backfill of Trench�
(typ.)(typ.)
6" 6"
Make final manhole adjustments before paving.
slope of street.
Slope manhole frame as required to match with sections of length required to match grade.
and barrel sections as necessary and replacing Adjust manholes downward by removing cone under frame.
Adjust manholes upward with adjusting rings required.
Adjust water valves upward or downward as types in the field before beginning work.
illustrations. Verify existing dimensions and Drawings of manholes and valves are only Existing manhole and valve types are varied.
NOTE:
6.
5.
4.
3.
2.
1.
No Scale ordering materials.
Obtain required warning tape text from CO before not allowd in trench.
Construction scrap material or trash of any kind
All conduits shall be scedule 40 PVC.
NOTE:
3.
2.
1.
No Scale
:2
A p ri l
M a n h o le a n d V a lv e B x d ju s tm e n t D e ta il p w
-w o rk
\d \g la c -p
-h q p ln m is c .d g n
UTILITY TRENCH DETAILS
ADJUSTMENT AND
MANHOLE & VALVE BOX
PROJECT
E.11
#5 rebar
Fill with silicone sealent.
" dia. hole,recess rebar 1".8
2 - #4 rebar
#6 rebar
#4 rebar
Placed riprap, class II class1, type A
Geotextile filter, Flowline material (curb) Bed course
Top of curb elevation colored concrete 4-inch depth
Sidewalk, exposed aggregate
4-inch compacted depth
Bed course material (sidewalk)
Granular backfill material
Original ground Subexcavation
Geotextile, class 2, type C
6'-0"
2'-0"
1'-0"1'-6"1'-0"
10"
CONCRETE WHEEL STOP
1% � � 1%
ENERGY DISSIPATOR
2'
1'
6"
12"
1'-6"
6"
"2
1"R
1"R
"2
12-INCH DEPTH
CURB AND GUTTER, CONCRETE
6"
Varies �
SIDEWALK, EXPOSED AGGREGATE
COLORED CONCRETE TYPICAL
1:1 1:
1 4'
4'
Cut slopeCut slope
2% � � 2% � VariesVaries �
ROCK SWALE TYPICAL
:4
A p ri l
M is c D e ta il p w
-w o rk
\d \g la c -p
-h q p ln m is c .d g n
MISCELLANEOUS DETAILS
PROJECT
E.12
604-1
STANDARD APPROVED FOR USE 6/2005
REVISED:
Standard 604-3 for Type B Frame and Grate.
See Standard 604-2 for Type A Frame and Grate and
2" unless otherwise shown.
#4 at 12"±.
TYPE 1
CATCH BASIN
3 " unless otherwise 4
3CONCRETE: Chamfer exposed edges
3'-5"
2.2
1.8
1.5
1.2
1.1
0.7
0.7
48"
42"
36"
30"
24"
18"
12"
5'-6"
5'-0"
4'-6"
4'-0"
4'-0"
3'-0"
3'-0"
6'-3"
5'-6"
4'-9"
4'-0"
3'-3"
2'-6"
2'-6"
6'-3"
5'-5"
5'-0"
4'-2"
3'-4"
2'-6"
2'-6"
INCHES
DIAMETER
SIZE
PIPE
CUYD
LB
LB
5"
1"
5"
1"
NO SCALE
3.
2.
1.
CURB SECTION
TYPICAL INSTALLATION
CURB AND GUTTER SECTION
TYPICAL INSTALLATION
INLET DETAIL
DITCH SECTION
TYPICAL INSTALLATION
Slop e as sta ked
Slope as staked
Sidewalk
Sidewalk
Pavement
Pavement
Roadway
The minimum concrete cover to the face of any bar is shown. Give all concrete surfaces a Class 1 finish.
T line
Gutter or ditch
H
Bend to clear pipe
All reinforcing steel d ia m e te r
P ip e
CONCRETE CATCH BASINS
STEEL
REINFORCING FRAME AND GRATE
TYPE A TYPE B
CONCRETE
ESTIMATED QUANTITIES
CONCRETE CATCH BASINS
DIAMETER
SIZE
PIPE
H
DEPTH
T
FRAME AND GRATE
TYPE A TYPE B
NOTE:
basin
Catch basin
Catch basin
Catch
:4
A p r il
C a tc h B a s in
T y p p w w o r k
\d
\g la c p h q p ln m is c .d g n
U.S. CUSTOMARY STANDARD
STANDARD
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
PROJECT
E.13
604-3
STANDARD APPROVED FOR USE 6/2005
REVISED: 6/2007
238 lbs. Increase or decrease weight by 19 lbs for
Estimated weight, frame and grate (2'-6" x 2'-6")
See Standard 604-1 for dimensions of T.
See Standard 604-1.
" bolt or approved equal.8 3for
"4
"4
" x 4" 2 s p a c e s a t
" (See Note 7)8 3at 2
" x 4" headed anchors2
"4 1 "4
"4
T - 1" (See Note 8)
"4
2"
" plates2
" x 32
Space
"4 1L3" x 1" x
" bolt8 3furnish
" dia. hole2 1Drill
" increment.8 3each 2
" x 4"2
"4
TYPE B
METAL FRAME AND GRATE
ty p s p a c e s a t d ia b a r
S p a c in g
(typ.)
"8 ty p
"2
22 equal spaces for"2
" Plate4
" x 4
" Plate2
" x 4 s p a c e s a t
" bolt8
Ferrule loop insert for
"8
2"8
2"8
2"4
1"4
" dia. bar8
"4
" x 2
L3" x 2
" Plate4
" x 4
" x 14 ty p
" dia. hole2
" dia. hole2 1 1" dia. hole p la te s ti f f e n e r s
S p a c in g
" x 2
L3" x 2
"4
L3" x 1" x
"4
" x 2
L3" x 2
"4
L3" x 1" x
" dia. hole2
1" dia. hole
" Plate4
" x 4
" Plate4
" x 2
"4
L4" x 1" x
"8
NO SCALE
FRAME AND GRATE DETAILS
FRAME CORNER DETAIL GRATE CORNER DETAIL
FRAME ANCHOR DETAIL
FRAME DETAIL
GRATE DETAILS
SECTION A-A
SECTION B-B
8.
7.
6.
5.
4.
3.
2.
1.
(typ.)
(typ.)
C-L2
FINISH: Galvanized after fabrication.
material thickness. Grind smooth all contact surfaces.
all joints with a minimum size fillet weld, based on
Specifications. Unless otherwise indicated seal weld
WELDING: Weld in conformance with the Standard full penetration butt weld.
HEADED CONCRETE ANCHORS: Weld to frame with a
THREADED CONCRETE ANCHORS: Ferrule loop inserts
BOLTS & WASHERS: ASTM A 307, Galvanized.
STRUCTURAL STEEL: AASHTO M 183 (ASTM A 36M).
Number of plates varies according to pipe diameter.
30°
(typ.)
AA
B
B
(trim angle to size)
T (See Note 8) headed anchor
TRAFFIC
and washer headed anchor
Direction of flow "4
"4
"8
2 "8
2 "8
2 2" "4
(typ.)
"8 x h e a d e d a n c h o r s
S p a c in g f r
" dia. hole2
" Plate2
" x 2
NOTE:
" Plate4
" x 4
" Plate4
" x 4
45°
:5
A p r il
M e ta l F r a m e a n d
G r te p w w o r k
\d
\g la c p h q p ln m is c .d g n
U.S. CUSTOMARY STANDARD
STANDARD
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
PROJECT
E.14
:0
A p r il
T a b u la ti o n o f S
E S
C Q u a n ti ti p w w o r k \d
\g la c p h q p ln e c .d g n
CONTROL QUANTITIES
SOIL EROSION AND SEDIMENT
TABULATION OF
PROJECT
F.1
D I
D I
I
D I
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
T u r f
E s ta b li s h m e n t G r a s s
T u r f
E s ta b li s h m e n t G o v e r n m e n t
P r o v id e d
E m p lo y e e P a r k in g A r e a
V in t
M a in te n a n c e A r e
N
Slope stake limit
Slope stake limit
Proposed edge of pavement
Fiber Rolls
Soil Erosion Control, Fiber Rolls
Soil Erosion Control, Construction limit
Slope stake limit
Construction limit
Inlet Protection, Type A
Soil Erosion Control, Fiber Rolls
Soil Erosion Control, Slope stake limit
Inlet Protection, Type B
Soil Erosion Control, Inlet Protection, Type B
Soil Erosion Control, Fiber Rolls
Soil Erosion Control, Proposed edge of pavement
Proposed edge of pavement
Construction limit
Check Dam (Fiber Roll)
Soil Erosion Control, See Sheet F.4 for details.
inlet protection, type A
Install soil erosion control, See Sheet F.6 for details.
Install soil erosion control, fiber rolls
LEGEND:
VINT BLVD
H E
A D
Q U
A R
T E
R S R
O A
D
See Sheet F.4 for details.
inlet protection, type B
Install soil erosion control, Turf establishment (lawn seed)
Turf establishment (government provided seed)
PARKING AREA
VINT BLVD AND EMPLOYEE
:5
A p r il
F
.2 V in t
B L
V p w w o r k \d
\g la c p h q p ln e c .d g n
(SHEET 1 of 2)
CONTROL PLAN
SOIL EROSION AND SEDIMENT
PROJECT
F.2
P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
E X
R A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
D I
E X
R
N
Slope stake limit
Slope stake limit
Construction limit
Fiber Rolls
Soil Erosion Control, Fiber Rolls
Soil Erosion Control, Construction limit
Fiber Rolls
Soil Erosion Control, edge of pavement
Proposed
Proposed edge of pavement
Proposed edge of pavement
Construction limit
Slope stake limit Construction limit
Fiber Rolls
Soil Erosion Control, Fiber Rolls
Soil Erosion Control, See Sheet F.6 for details.
Install soil erosion control, fiber rolls
LEGEND:
Construction limit
Turf establishment (government furnished seed)
VINT BLVD MAINTENACE AREA
:1
A p r il
F
.3 V in t
B L
V D
M a in te n a n c e A re p w w o r k \d
\g la c p h q p ln e c .d g n
(SHEET 2 of 2)
CONTROL PLAN
SOIL EROSION AND SEDIMENT
PROJECT
F.3 overlap onto curb
Gravel filled bags
Spillway 1-bag high
2-bags high. See Note 5
Gravel filled bags Spillway 1-bag high
Drop inlet
Back of curb
Face of curb
Drop inlet
2-bags high. See Note 5
Gravel filled bags Spillway 1-bag high
PLAN VIEW - INLET AT SAG
PLAN VIEW - INLET ON GRADE
Drop inlet grate
Accumulated sediment
Catch basin
Drop inlet grate
Spillway (beyond)(stacked tightly)
Gravel filled bags
Accumulated sediment
Drop inlet
Expansion restraint
Prefabricated filter insert
Lifting loops (2 each)
Dump straps (2 each) Drop inlet grate
Drop inlet grate
Back of curb
Face of curb
Fiber roll in full contact with the ground
Fiber roll
6.
5.
4.
3.
2.
1.
PLAN
DROP INLET PROTECTION (TYPE B)
GRAVEL BAG BERM
SECTION B-B
See Note 6
DROP INLET PROTECTION (TYPE C)
PREFABRICATED FILTER INSERT
DROP INLET PROTECTION (TYPE A)
FIBER ROLL
SECTION A-A
B
B
A
A
Flow Flow
Flow
Include a high-flow bypass in the insert.
and allow collected material removal without spillage.
Size the prefabricated filter insert (Type C) to fit the drop inlet fabric to the top of the fabric with clean, silt-free coarse next layer of bags on top of it. Extend the geotextile fabric a bags to the spillway elevation. Anchor the fabric by placing the the upstream face of the bags. Place fabric over the top of the fit is unachievable, install geotextile filter, class 2, type C along sediment flows between or underneath the bags. Where tight
Pack gravel filled bags tightly together end to end to ensure no
Maximum top of gravel bag spillway elevation = approved by the CO.
Select the inlet protection device to fit field conditions as
High-flow bypass 1" x 1" or 1" Ø wood stake. See Note 2
9" Ø (min.) fiber roll
Top of curve minus 1-inch.
x 18-inches.
Approximate finished dimension of gravel bags is 12-inches on center. Drive stakes 12-inches (min.) in undisturbed soil.
Install fiber rolls with stakes spaced no more than 24-inches aggregate between 2-inches and 3-inches in diameter.
minimum of 18-inches upstream of the bags. Cover geotextile
PROTECTION
TEMPORARY INLET
NOTE:
Flow Flow
WFLHD DETAIL
DETAIL APPROVED FOR USE 7/2016
157-2W
:5
A p r il
D e t
W p w w o r k
\d
\W
I n le t
P r o te c ti o n
.d g n
DETAIL
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
PROJECT
F.4
2.
1.
D
D
E
E
CC
Overflow water
Filtered
DROP INLET PROTECTION (TYPE D1)
BLOCK AND GRAVEL
SECTION C-C
CURB INLET PROTECTION (TYPE D2)
BLOCK AND GRAVEL
SECTION D-D
CURB INLET PROTECTION (TYPE E)
INLET PROTECTION DEVICE
SECTION E-E
PLAN
Overflow
8" x 8" x 16" (nominal)
8" x 8" x 16" (nominal)
2" x 2" (nominal) wood frame
2" x 4" (nominal) wood stud
12" (min.)
Sheet 2 of 2
PROTECTION
TEMPORARY INLET
2"
18"
9"
12" (min.)
Wire mesh Concrete masonry unit
Curb and gutter
Curb inlet device, see Note 1
Inlet protection
Concrete masonry unit Wire mesh
Curb inlet
Curb inlet
Curb inlet
Accumulated sediment
Sediment laden runoff used to retain concrete blocks
Drop inlet with grate
Accumulated sediment
Filtered water laden runoff
Sediment
Wire mesh
Wire mesh
Gravel filter Gravel filter
NOTE:
Vary dimensions to fit field conditions.
Install device according to manufacturer's recommendations.
filter tubing filled with gravel or other prefabricated filter material.
Inlet protection device (type E) may consist of continuous see Note 1
Inlet protection device, Accumulated sediment Filtered water
157-2W
:4 p r il
D e t
W b p w w o r k
\d
\W
I n le t
P r o te c ti o n
.d g n
DETAIL
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
PROJECT
F.5
Se e N ote
6%
5%
4%
3%
2%
NO SCALE
6%
5%
4%
3%
2%
5%
4%
3%
2%
7.
6.
5.
4.
3.
2.
1.
Adjust check dam spacing based on site-specific conditions.
around the ends of the fiber roll.
Provide sufficient length to prevent water from flowing
Drive stakes into undisturbed soil of trench bottom.
stakes. Drive stakes at each end of the fiber roll and at
Install check dams in ditches perpendicular to the flowline.
installation.
Repair all rills or gullies and properly compact prior to functional requirements of the check dam device.
gravel bags as approved by the CO, to meet the
Construct check dams from fiber rolls, filter rock, or
MODERATE GRADES
CHECK DAM
CROSS SECTION
V-DITCH
CROSS SECTION
FLAT-BOTTOM DTICH
CROSS SECTION
CROSS SECTION
STAKING DETAIL
FIBER ROLL
PLAN
are similar for flat-bottom ditches
Check dam installation details
V-ditch design shown.
Flow line
GRADE
DITCH
(See Note 7)
CHECK DAM SPACING*
GRAVEL BAG
Gravel bag the ends. See Note 6 to prevent flow around
Curve ends upstream
Filter rock
Filter rock
FIBER ROLL CHECK DAM
GRAVEL BAG CHECK DAM
SPACING (max.)
CHECK DAM
See Note 5
NOTE:
GRADE
DITCH
SPACING (max.)
CHECK DAM
(See Note 7)
CHECK DAM SPACING
FILTER ROCK
GRADE
DITCH
(See Note 7)
CHECK DAM SPACING*
FIBER ROLL
SPACING (max.)
CHECK DAM
FILTER ROCK CHECK DAM
uphill side of fiber roll trench material on
Place excavated
Flow
F lo w on ditch grades steeper than 5%.
Do not use fiber roll check dams
* Spacing calculated based on on ditch grades steeper than 6%.
* Do not use gravel bag check dams
(FT)
(FT)
(FT)
Trench 2" (min.)
m in
Fiber roll 9" Ø (min.)
Trench 2" (min.)
-inch wood 8 1-inch x 18
1Stake fiber rolls in place with 1
Expose stakes 2-inches (min.) above top of fiber roll.
2-foot (max.) spacing.
m in
"6 m in m in .6
9" Ø minimum fiber roll.
157-15W
WFLHD DETAIL
:3 p r il
D e t
W p w w o r k
\d
\W
C h e c k
D a m
.d g n
DETAIL
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
PROJECT
F.6
Spacing Slope
STAKES REQUIRED
1:1
1:2
1:3
1:4 or flatter for each roll
Stakes required
FIBER ROLL SPACING
Fiber roll length
Fl ow
T o e o f fi ll s lo p e
ELEVATION
PLAN
disturbed areas
Runoff from
INSTALLATION BEYOND TOE OF SLOPE
INSTALLATION ALONG SLOPES
FIBER ROLL STAKING DETAIL
PROPERLY STAKED AND ENTRENCHED FIBER ROLL
Existing ground (typ.)
Fiber roll
Flow direction
Slope
Direction of runof f from distur bed area s sp ac in g ch ar t
S ee F ib er R ol l
Fiber roll ff o n ur f o n oi t c er i
D along contours
Install fiber rolls
Fiber roll
Slope
Fi ll slo pe
Direction of runoff ground
Existing soil to match ground level
Backfilled and compacted
Flow larger than fiber roll wood stakes. See Note 2.
Pay lim its
Pay lim its
SLOPE PROTECTION INSTALLATION
ALTERNATE FIBER ROLL JOINT DETAIL
FIBER ROLL LAPPING DETAIL
on uphill side of fiber roll
Place excavated material Stagger joints (typ.)
2.
1.
permanent installations. Do not crush fiber roll while staking.
roll is secure to slope. Live stakes may be used for and install fiber rolls
Step 1: Excavate trench Step 2: Backfill soil against fiber rolls
FIBER ROLL
(FT)
(FT)
2" (min.) Excavate trench 2"
1" x 1" or 1" Ø ove rlap
12" (m in.)
t o m in m in
1" x 1" Wood stake as specified in plans
3' min. or
3' (min.)
Drive stakes at each end and at 4-foot spacing until fiber fiber roll and space stakes at 4-foot max.
6-inches from fiber roll end angles towards the adjacent
Overlap fiber rolls 12-inch minimum. Drive stakes at
NOTE:
DETAIL APPROVED FOR USE 10/2014
7/2016 REVISED:
157-21W
:3 p r il
D e t
W p w w o r k
\d
\W
F ib e r R o ll
.d g n
DETAIL
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
PROJECT
F.7
SIDEWALKASPHALT
S
ID
E W
A L
K C
O N
C R
E T
E
SIDEWALK
CONCRETE
limits as directed by CO.
fence along contruction
Place construction
:5 p r il
T
T C
T A
B U
L A
T
IO
N O
F Q
U A
N T
IT
IE
p w w o r k \d
\g la c p h q p ln tt c .d g n
QUANTITIES
TEMPORARY TRAFFIC CONTROL
TABULATION OF
PROJECT
G.1 c o y e n C ir c le
PARKING AREA
EMPLOYEE
MAINTENANCE AREA
VINT BLVD
N
W20-1
WORK
ROAD
AHEAD
G20-2
ROAD WORK
END
W20-1
WORK
ROAD
AHEAD
G20-2
ROAD WORK
END
R11-2
ROAD
CLOSED
ROAD
CLOSED
Vint Blvd
G o in g T o T h e S u n R o a d
Mather Dr.
Headquarters Rd.
G r in n e ll D r
M id d le F o rk F la th e a d R iv e r
Going To The Sun Road
Glacier Route 1 Road
FOOTNOTE:
with warning light.
R11-2 mounted on type 3 barricade
:0 p r il
T
T C
P L
A N
P H
A S p w w o r k \d
\g la c p h q p ln tt c .d g n
PLAN PHASE 1
TEMPORARY TRAFFIC CONTROL
PROJECT
G.2 c o y e n C ir c le
PARKING AREA
EMPLOYEE
MAINTENANCE AREA
VINT BLVD
N
W20-1
WORK
ROAD
AHEAD
G20-2
ROAD WORK
END
W20-1
WORK
ROAD
AHEAD
G20-2
ROAD WORK
END
ROAD
ROAD
Vint Blvd
ROAD
CLOSED
G o in g T o T h e S u n R o a d
Mather Dr.
Headquarters Rd.
G r in n e ll D r
M id d le F o rk F la th e a d R iv e r
Going To The Sun Road
Glacier Route 1 Road
FOOTNOTE:
with warning light.
R11-2 mounted on type 3 barricade
:0 p r il
T
T C
P L
A N
P H
A S p w w o r k \d
\g la c p h q p ln tt c .d g n
PLAN PHASE 2
TEMPORARY TRAFFIC CONTROL
PROJECT
G.3
< 10
" dia. bolts 4
Attach sign panels with a minimum of 2 -a minimum lateral distance of 1' behind the face of lateral offset of 2' may be used. In areas with curbs, 6" x 6" or larger.
Use 7' minimum spacing between posts for sign posts and 6' minimum mounting height for secondary sign.
use 7' minimum mounting height for main sign
NO SCALE
See post detail (typ.)
Break-away holes.
See table for hole size parallel to sign face.
Field drill holes through post
Bottom of sign panel
Post�
Local tangent
S e e N o te m in
S e e N o te m in
See Note 4
6' - 12'
On tangent alignment
200'
NOTE:
90°
93°
WOOD POST SELECTION TABLE
X X
0.75X
H
H
X
0.2X0.6X 0.2X
Y
H
D
H
D
H
D
Long side of post
D
7.
6.
5.
4.
3.
2.
1.
In areas where lateral distance is limited, a minimum
D = Post embedment depth for average soil conditions.
Select post lengths to fit field conditions.
H1 and H2 = Overall post length.
per post.
In pedestrian locations, or in areas with obstructed views, the curb may be used.
by the CO.
State standards may be used as an alternative if approved
SINGLE POST SIGN TWO POST SIGN
SIGN INSTALLATION ANGLE
POST DETAIL
E d g e o f p a v e d s h o u ld e r
E d g e o f tr a v e le d w a y
(SQFT)
Other Shapes ≤ 48" Diamond ≤ 36"
Other Shapes ≤ 12' Diamond ≤ 48"
(INCH) (INCH) (INCH)
Diamond ≤ 48"
65 - 95
65 - 95
50 - 65
50 - 65
20 - 50
10 - 20
10 - 20
> 30'
> 17'
12' - 16'
> 13'
6 x 6
4 x 6
4 x 6
6 x 6
4 x 6
4 x 4
6 x 6
4 x 6
4 x 4
1.5
1.5
1.5
1.5
"X"
WIDTH AREA
OF POSTS
NUMBER POST SIZE D HOLE SIZE
635-14
6/2005 STANDARD APPROVED FOR USE
7/2022 REVISED:
WOOD POSTS
SIGN INSTALLATION
TEMPORARY TRAFFIC CONTROL
:0 p ri l
S T
N D
D
E T
A
IL
-1 p w
-w o rk \d
\g la c -p
-h q p ln tt c .d g n
FLH STANDARD
STANDARD
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
PROJECT
G.4
See detail sheet H.4
:1 p r il
Q u a n ti ti e s
S h e t] p w w o r k
\d
\g la c p h q p ln p tc
.d g n
TABULATION OF QUANTITIES
PROJECT
H.1
+ 9'
9'
9'
' 10.4'10.4'
24'19'
N solid, Type D (white)
Pavement markings, solid, Type D (white)
Pavement markings, Remove and reset
Sign 10
Remove and reset
Sign 9 remove and reset
Sign 7 remove and reset
Sign 8
20'
2' 4"
45°
EMPLOYEE PARKING AREA
LEGEND
Snow pole holder, see Sheet M.30 for details.
Removal of sign
Sign 1
FOOTNOTE:
[1] concrete gutter.
pavement marking to asphalt pavement. Do not apply markings to Total parking stall depth = 20' (1' gutter + 19' stripe). Apply 19'
[1]
4.6'
9'
40 8040 0
Scale in feet
:4
A p r il
E
M P
P a r k
S h e p w w o r k
\d
\g la c p h q p ln p tc
.d g n
(SHEET 1 OF 2)
STRIPING PLAN
PROJECT
H.2
P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
P
V C
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
A P P
R O
X
IM
A T E
E X
R
E X
R
S D
BLDG 208
Plumbing Shop
BLDG 217
Facilities Offices
BLDG 243
Campground Storage
LE BLDG 210
BLDG 243
Radio and Utilities
BLDG 231
Storage
9'
N solid, Type D (white)
Pavement markings, solid, Type D (white)
Pavement markings, Type D, Straight arrow (typ.)
Pavement markings, See Sheet E.11 for details
Concrete wheel stop
See Sheet E.11 for details
Concrete wheel stop Removal of sign
Sign 2
Removal of sign
Sign 3
R7-1R
Sign 4
R7-1L
Sign 5
47°
16'
16'
20'
20'
20' 9'
MAINTENANCE AREA
VINT BLVD
LEGEND
Snow pole holder, see Sheet M.30 for details.
2.
1.
NOTE:
current edition.
Symbols shall conform with the "Standard Highway Signs", Uniform Traffic Control Devices'' (MUTCD), current edition.
with the ''Manual onPlace symbol markings in accordance
(Area 12 SQFT)
WLANE-USE ARRO
THROUGH
14"12"14"
Ref-1
Sign 11
Ref-1
Sign 12 Ref-1
Sign 13
Ref-1
Sign 14
Ref-1
Sign 15
Ref-1
Sign 16
R=1.5"0.375" 0.375"
NO
PARKING
ANY
TIME
NO
PARKING
ANY
TIME
40 8040 0
Scale in feet
Background - White (Retroreflective)
Colors: Legend - Green (Retroreflective)
Ref-1
SIGN DETAIL
BACK-IN
PARKING
2.5"
2"
1.5"
2"
1.5"
ONLY 2"
2"
2"
2.5"
12"
BACK-IN
PARKING
ONLY
BACK-IN
PARKING
ONLY
BACK-IN
PARKING
ONLY
BACK-IN
PARKING
ONLY
BACK-IN
PARKING
ONLY
BACK-IN
PARKING
ONLY
VINT BLVD MAINTENANCE AREA
:4
A p r il
V
I N
T P a r k
S h e p w w o r k
\d
\g la c p h q p ln p tc
.d g n
(SHEET 2 OF 2)
STRIPING PLAN
PROJECT
H.3
Locations are approximate. Final locations to be set by CO.
concrete, 12-inch depth
Curb and gutter, steel pipe (holder)
" O.D. dia. std.2
Bedding material
See Snow Pole Holder Cap Detail.
" below top of pavement.8
" to8
Recess top of cap
2"
DETAIL
SNOW POLE HOLDER
DETAIL
SNOW POLE HOLDER CAP
" plate2 middle of the 3
" hole in the 8 drill
" O.D. dia. plate,2
" x 34 steel pipe (cap)
3" O.D. dia. std.
FOOTNOTE:
[1]
[1]
Subgrade
NOTE:
1. All welds are 1/4-inch fillet.
:1 p r il
S n o w p o le
D e ta il
S h e p w w o r k
\d
\g la c p h q p ln p tc
.d g n
DETAILS
SNOW POLE HOLDER
PROJECT
H.4
(inch)
8 x 12
8 x 10
6 x 10
6 x 8
6 x 6
4 x 6
4 x 4
Product of X-Y-Z in CUFT
6'-0"
5'-0"
5'-0"
4'-0"
4'-0"
4'-0"
3'-0"
"4
"4
"2
For all retroflectorized signs where W > 25'
6 ft 5 ft
7 ft 2 ft
V may be reduced by 1 foot in rural districts for
22 ft (max.)
X=14 ft (min.) to maximum
X=5 ft to 12 ft (max.)
X=4 ft (min.)
18 ft (max.)
X=10 ft (min.) to
" outside dia.) 4
(1 oversized washer " nonmetallic16
" oversized washer16 5" lock nut16
" bolt16
" bolt thru the post8
6" x 8" when located within the clear zone or if the post
SINGLE POST SIGNS
POST DETAIL
THREE POST SIGNS FOUR POST SIGNS
MINIMUM DISTANCE TO SIGN
SIGN INSTALLATION ANGLE
WOOD POST SELECTION TABLE
Direction of traffic flow
SIZE
POST NUMBER OF POSTS
1 2 3 4 D diameter and hole depth
Notch from curb
Offset (W)
Lateral
Height (V)
Mounting
TWO POST SIGNS
E d g e o f s h o u ld e r
E d g e o f t r a v e le d w a y
E d g e o f s h o u ld e r
E d g e o f t r a v e le d w a y
E d g e o f t r a v e le d w a y
E d g e o f s h o u ld e r
Location
Rural Districts
Residence Districts
Business or
See table for hole size post, parallel to sign face.
Field drill holes through a secondary sign mounted below another sign.
exceeds the limit for the largest post, use steel post installation.
Values shown are the maximum permitted. If the product of XYZ
E d g e o f t r a v e le d w a y
E d g e o f s h o u ld e r
Finish ground line
NO SCALE
CL post
Backfill material
W
0.15X0.35X0.35X0.15X ty p
Z
Y
H
H
H
V Y
Backfill material
W
0.125X0.25X0.25X0.25X0.125X
.5
Y Z
H
H
H
H ty p
D
V Y
V Y
H
Z ty p
D
Same post size
Same post size
Bottom of sign
Long side of post single post installations of post. Omit notch for
Saw cut notch full width
H
Same post size
Backfill material
(See Post Selection table)
Notch depth (where required)
W
Backfill material
Y
Z ty p
D
V Y
H
.5
Y
0.2X0.6X0.2X all around (typ.)
3" minimum all around (typ.)
3" minimum all around (typ.)
3" minimum all around (typ.)
3" minimum
NOTE:
SIGNS WITHOUT ANGLES
TYPICAL MOUNTING FOR
5.
4.
3.
2.
1.
of traveled way
Elevation at edge of traveled way
Elevation at edge of traveled way
Elevation at edge of traveled way
Elevation at edge rectangle enclosing all the signs.
- Multiple sign installations: X and Y are the dimensions of a dimensions of the signs.
- Single sign, or back to back signs: X and Y are the overall
For the purpose of post selection X and Y are as follows:
longest post.
Z is the height from ground line to mid-height of sign at the conditions. See Wood Post Selection Table below.
D is the minimum post embedment depth for average…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .