This document is a set of questions and answers related to a federal contract opportunity for the Glac HQ Parking Area Rehabilitation project. The project consists of two phases and involves the rehabilitation of a parking area. Key details include:

The bid bond requirement is 20% of the bid price or $3 million, whichever is less. The project has two bid schedules, A and B, with the same quantities for roadway aggregate and asphalt concrete pavement. However, the select borrow layer differs between the two schedules. The government will not provide .dwg plan files, but the parking lot models are available in the Physical Data. An amendment will be issued to address a discrepancy in the estimated price range and the requirement for a qualified Traffic Supervisor. The solicitation number is 69056724B000010, and the opportunity is being managed by the Department of Transportation Federal Highway Administration.

View the file

Other files

File Type Posted
Bid Tabulation_MT NP GLAC P HQ(1).pdf PDF
BidSum_MT NP GLAC P HQ(1).pdf PDF
Amendment A001.pdf PDF
QA 5_23_24.pdf PDF
ML_HQ2_YellowTop_XYZ.xlsx XLSX spreadsheet
IFB_69056724B000010_MT NP GLAC P HQ(1).pdf PDF
Profile_Vint_Blvd.pdf PDF
Vint_Blvd_RedTop_XYZ.xlsx XLSX spreadsheet
FLH Bridge oversized or overload vehicle permit request form.pdf PDF
WFLHD Construction Contract Administration_FY 23 V2.pdf PDF
Const_Limit_VintMaint_Area.pdf PDF
HZ_Vint_Blvd_Alignment.pdf PDF
Const_Stake_ML_HQ2.xlsx XLSX spreadsheet
Const_Limit_ML_HQ2.pdf PDF
MT_NP_GLAC_P_HQ(1)-Vint_Blvd_X-sections.pdf PDF
Glacier_HQ_controlsheet.xlsx XLSX spreadsheet
glac-p-hq1_-Planset.pdf PDF
glac-p-hq1-ORD_Quantity-Calcs-NB.pdf PDF
MT NP GLAC P HQ (1)_Amended Final Pavement Memo.pdf PDF
NPS HQ and Swiftcurrent Geotech Rpt.pdf PDF
Const_Stake_Vint_Blvd.xlsx XLSX spreadsheet
Vint_Blvd_Earthwork.pdf PDF
HZ_ML_HQ2_Alignment.pdf PDF
Physical Data.zip ZIP file
ML_HQ2_RedTop_XYZ.xlsx XLSX spreadsheet
Vint_Blvd_YellowTop_XYZ.xlsx XLSX spreadsheet
super_Vint_Blvd.xlsx XLSX spreadsheet
Const_Limit_VintBlvd.pdf PDF
Const_Limit_Emp_Pkng.pdf PDF
MT_NP_GLAC_P_HQ(1)-HQ Road_X-sections.pdf PDF
ML_HQ2_Earthwork.pdf PDF
ML_HQ2_BlueTop_XYZ.xlsx XLSX spreadsheet
Vint_Blvd_BlueTop_XYZ.xlsx XLSX spreadsheet
Profile_ML_HQ2.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No: MT NP GLAC P HQ(1), Project: Glac HQ Parking Area Rehabilitation, Phase 1 and Phase 2

# General Technical Question Answer Date

1 X

Under the FP‐14 156.09 states to have a qualified Traffic Supervisor to perform all the duties in the section but there is no pay item for that individual. Are you going to add that pay item or alter the specification for that section?

This will be addressed under Amendment A001 5/23/24

2 X

In the scr section it states “636.13 Add the following:

Measure conduits by the linear foot, including each conduit run placed in a singular trench.”

Are you stating that each individual conduit will be measured separately whether or not they are in the same trench?

Measure each conduit run separately 5/23/2024

3 X Is the bid bond required to be 10% or 20%?

Per FAR Clause 52.228‐1 Bid Guarantee (Sept 1996) on page C‐71 of the IFB, The amount of the bid guarantee shall be 20 percent of the bid price or

$3 million, whichever is less.

5/29/2024

4 X Estimated price range? There is a typo on page A‐6 of the ITB This will be addressed under Amendment A001 5/29/2024

5 X

Is it correct, schedule A and schedule B both have the same quantity of roadway aggregate method 2 6,200 ton?

Yes, Schedules A and B have the same pavement quantities – the only difference is in the select borrow layer of the pavement (under the roadway aggregate).

5/29/2024

6 X

Is it correct, schedule A and schedle B both have the same quantity of asphalt concrete pavement 2,900 ton?

Yes, Schedules A and B have the same pavement quantities – the only difference is in the select borrow layer of the pavement (under the roadway aggregate).

5/29/2024

7 X Are the .dwg plans files available for review for takeoff purposes? No, We don’t provide .dwg plans files. Please bid accordingly.

5/29/2024

8 X Are vectorized .pdf plan files available for review? The models of the parking lot are provided in

Physical Data.

5/29/2024