This document is a Construction Contract Administration report that describes the Federal Highway Administration's (FHWA) procedures for definitizing equitable adjustments for change orders under construction contracts. It provides data on FHWA's past performance regarding the time required to definitize these equitable adjustments over the last 3 fiscal years. The report indicates there are no additional agency-specific policies or procedures beyond the requirements in FAR 36.211. The data shows the number of change order proposals definitized within various timeframes, with the majority falling within 91-180 days.
The related federal contract opportunity is an Invitation for Bids (IFB) for the MT NP GLAC P HQ(1), GLAC HQ Parking Area Rehabilitation project. The solicitation is issued by the Department of Transportation Federal Highway Administration. There are two bid schedules, with only one schedule to be awarded. The IFB, plans, physical data, and the Construction Contract Administration document per FAR 36.211 are provided as attachments.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WFLHD Construction Contract Administration
FAR 36.211 requires a description of the Federal Highway Administration’s (FHWA) procedures that apply to definitization of equitable adjustments for change orders under construction contracts. It also requires that FWHA furnish data on the agency’s past performance, for the prior 3 fiscal years, regarding the time required to definitize equitable adjustments for change orders under construction contracts.
Change orders as defined in FAR 2.101 are changes to the contract work pursuant to FAR 52.243-4, Changes.
There are no agency-specific additional policies and procedures that exist at this time.
The table below contains data regarding the definitization of equitable adjustments for change orders under construction contracts by fiscal year (FY).
Time to definitize after receipt of an adequate change order definitization proposal under construction contracts
Number of change order proposals definitized under construction contracts
FY 2021 FY 2022 FY 2023
0 to 30 days 1 1 0 31 to 60 days 1 0 3 61 to 90 days 0 0 3 91 to 180 days 5 1 4 181 to 365 days 0 0 3 366 or more days 2 0 0 After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance
0 0 0 https://www.acquisition.gov/far/part-52#FAR_52_243_4