The file "Ghiglione_EPA_Compiled SWPPP_Final.pdf" appears to be a Stormwater Pollution Prevention Plan (SWPPP) related to the Ghiglione Bridge replacement project for the Federal Highway Administration. The document is associated with a specific federal contract opportunity (Solicitation Number: 69056725B000009) for replacing the Ghiglione Bridge in Alaska. While the specific details of the SWPPP are not fully visible in the provided context, SWPPPs typically outline comprehensive strategies for managing stormwater runoff, preventing pollution, and ensuring environmental compliance during construction activities. The project is being conducted by the Department of Transportation Federal Highway Administration, indicating a federal infrastructure improvement initiative focused on bridge replacement and environmental protection measures.

View the file

Other files for this federal contract opportunity

Other files attached to AK PRA DENA 10(36), Replace Ghiglione Bridge, newest first.
File Type Posted
BidTabulation_AK PRA DENA 10(36).pdf PDF
BidSum_AK PRA DENA 10(36).pdf PDF
QA_11_24_2025.pdf PDF
QA_11_21_2025.pdf PDF
QA_11_18_2025.pdf PDF
QA_11_13_2025.pdf PDF
Amendment A002.pdf PDF
QA_11_12_2025.pdf PDF
QA_11_05_2025.pdf PDF
Amendment A001.pdf PDF
Geotech Report No 11-19 Ghiglione Final Foundation Report.pdf PDF
DENA01036_XS.pdf PDF
BHIM Nov 2022.pdf PDF
Hydraulic Design Narrative for Construction.pdf PDF
AK PRA DENA 10(36) - Physical Data - GOV Furnished Pipe Pile Info.pdf PDF
DENA01036_SUP.pdf PDF
DENA01036_VA.pdf PDF
DENA01036_HA.pdf PDF
9830-011P - Ghiglione Bridge As-Built Plans.pdf PDF
Physical Data_AK PRA DENA 10.zip ZIP file
FLH Bridge oversized or overload vehicle permit request form August 2023.pdf PDF
Ghiglione_ControlSheet.xlsx XLSX spreadsheet
Toklat Pit_Scrape Material Photos.pdf PDF
9830-011P - Ghiglione Bridge Inspection 2024.pdf PDF
WEF Nov. 2022.pdf PDF
DENA01036_EW.pdf PDF
IFB 69056725B000009.pdf PDF
dena01036_plans.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Stormwater Pollution Prevention Plan

SWPPP

For:

Federal Highway Administration Western Federal Lands Highway Division

Table of Contents

SWPPP TABS

TAB 1: SWPPP Narrative

TAB 2: NPDES Permit (Construction General Permit)

TAB 3: NOI, EPA Acknowledgement, Other Applicable Correspondence

TAB 4: Delegation of Authority

TAB 5: Site Maps (Indicate Wetlands, Waters, other Waterbodies)

TAB 6: Erosion/Sediment Control Plan Sheets (Plan Set and BMP Typical Details)

TAB 7: Revegetation Plan (if applicable)

TAB 8: SWPPP Amendment Log

TAB 9: Inspection Reports

TAB 10: Corrective Action Log

TAB 11: Water Quality Monitoring, Reporting Requirements, and Reports

TAB 12: Training Certificates and SWPPP Training Log

TAB 13: Government-Selected Waste, Borrow, Staging Sites (Indicate BMPs at Each Site)

TAB 14: Grading and Stabilization Log

TAB 15: Hazardous Spill Plan or Spill Prevention, Control, and Countermeasures (SPCC)

TAB 16: Endangered Species Act (ESA) & Cultural Resources (Section 106) Documentation

TAB 17: Quality Assurance Checklist

TAB 18: NPDES Notice of Termination (NOT)

Tab 1 - SWPPP Narrative

Revise and update as needed per SCR 107 and SCR 157

Stormwater Pollution Prevention Plan (SWPPP) Replace Ghiglione Bridge – AK PRA DENA 10(36) i

Construction Stormwater Pollution Prevention Plan Template To be covered under the U.S. Environmental Protection Agency’s (EPA) Construction General Permit (CGP), all construction operators are required to develop a “Stormwater Pollution Prevention Plan” (or “SWPPP”) prior to submitting a Notice of Intent (NOI) for permit coverage.

EPA created this SWPPP Template to help you develop a SWPPP that is compliant with the minimum requirements of Part 7 of EPA’s 2022 Construction General Permit (“2022 CGP”), and is customizable to your specific project and site.

Note: Permit was modified in 2025 to include coverage for Lands of Exclusive Federal Jurisdiction

– Permit is found at 2022 Construction General Permit (CGP) | US EPA (Modified 2022 CGP).

Any reference in the SWPPP to the 2022 CGP, is referencing the Modified 2022 CGP.

Instructions for Using the SWPPP Template

Each section of the SWPPP Template includes instructions and space for your project and site information. Read the instructions for each section before you complete that section. Specific instructions on what information to include is indicated in each text field in blue text. Click on the blue text and the instructions will disappear once you start typing. The SWPPP Template is an editable document file so that you can easily add tables and additional text and delete unneeded or non-applicable fields. Note that some sections may require only a brief description while others may require several pages of explanation.

The following tips for using this template will help ensure that you meet the minimum permit requirements:

• Read the 2022 CGP (as modified) thoroughly before you begin preparation of your SWPPP to ensure that you have a working understanding of the permit’s underlying requirements. You will also need to consult Part 9 of the permit to determine if your State or Tribe has included additional requirements that affect you.

• Complete the SWPPP prior to submitting your NOI for permit coverage. This is required in Parts 1.4 and 7.1.

• If you prepared a SWPPP under a previous version of EPA’s CGP, you must update your SWPPP to ensure that the 2022 CGP requirements are addressed prior to submitting your

NOI.

• If there is more than one construction operator for your project, consider coordinating development of your SWPPP with the other operators.

• Once EPA has provided your site with coverage under the CGP, include your NOI, your authorization email, and a copy of the CGP as attachments to the SWPPP. See Appendices B and C of the SWPPP Template.

While EPA has made every effort to ensure the accuracy of all instructions contained in the SWPPP Template, it is the permit, not the template, that determines the actual obligations of regulated construction stormwater discharges. In the event of a conflict between the SWPPP Template and any corresponding provision of the 2022 CGP, you must abide by the requirements in the permit. EPA welcomes comments on the SWPPP Template at any time and will consider those comments in any future revision of this document. You may contact EPA for CGP-related inquiries at cgp@epa.gov.

https://www.epa.gov/npdes/2022-construction-general-permit-cgp https://www.epa.gov/npdes/2022-construction-general-permit-cgp#2022cgpmodified https://www.epa.gov/npdes/2022-construction-general-permit-cgp mailto:cgp@epa.gov ii

For Construction Activities At:

Ghiglione Bridge – AK PRA DENA 10(36) Denali National Park, Mile Post 42 Denali Park Road

Denali Borough, Alaska 360-833-3338

SWPPP Prepared For:

Federal Highway Administration (FHWA) Western Federal Lands Highway Division (WFLHD)

4851 E. Blue Lupine Dr. Suite D Wasilla, AK 99654

360-833-3338 Jesse.harvey@dot.gov

To be completed by Contractor

Insert Company or Organization Name Insert Name

Insert Address Insert City, State, Zip Code Insert Telephone Number

SWPPP Prepared By:

FHWA, WFLHD

Cyrus Bullock

610 East Fifth Street Vancouver, WA 98661-3801

360-619-7964 Cyrus.bullock@dot.gov

SWPPP Preparation Date:

07/22/2025

Estimated Project Dates:

Project Start Date: 07/01/2026

Project Completion Date: 11/01/2027 iii iv

Contents

SECTION 1: CONTACT INFORMATION/RESPONSIBLE PARTIES

1.1 Operator(s) / Subcontractor(s)

1.2 Stormwater Team

SECTION 2: SITE EVALUATION, ASSESSMENT, AND PLANNING

2.1 Project/Site Information

2.2 Discharge Information

2.3 Nature of the Construction Activities

2.4 Sequence and Estimated Dates of Construction Activities

2.5 Authorized Non-Stormwater Discharges

2.6 Site Maps

SECTION 3: DOCUMENTATION OF COMPLIANCE WITH OTHER FEDERAL

REQUIREMENTS

3.1 Endangered Species Protection

3.2 Historic Property Screening Process

3.3 Safe Drinking Water Act Underground Injection Control Requirements ...19

SECTION 4: EROSION AND SEDIMENT CONTROLS AND DEWATERING PRACTICES ...20

4.1 Natural Buffers or Equivalent Sediment Controls

4.2 Perimeter Controls

4.3 Sediment Track-Out

4.4 Stockpiles or Land Clearing Debris Piles Comprised of Sediment or Soil ...26

4.5 Minimize Dust

4.6 Minimize Steep Slope Disturbances

4.7 Topsoil

4.8 Soil Compaction

4.9 Storm Drain Inlets

4.10 Constructed Site Drainage Feature

4.11 Sediment Basins or Similar Impoundments

4.12 Chemical Treatment

4.13 Dewatering Practices

4.14 Other Stormwater Controls

4.15 Site Stabilization

SECTION 5: POLLUTION PREVENTION CONTROLS

5.1 Potential Sources of Pollution

5.2 Spill Prevention and Response

5.3 Fueling and Maintenance of Equipment or Vehicles

5.4 Washing of Equipment and Vehicles

5.5 Storage, Handling, and Disposal of Building Products, Materials, and Wastes 42

5.6 Washing of Applicators and Containers used for Stucco, Paint, Concrete, Form Release Oils, Cutting Compounds, or Other Materials

5.7 Application of Fertilizers

v

5.8 Other Pollution Prevention Practices

SECTION 6: INSPECTION, MAINTENANCE, AND CORRECTIVE ACTION

6.1 Inspection Personnel and Procedures

6.2 Corrective Action

6.3 Delegation of Authority

SECTION 7: TURBIDITY BENCHMARK MONITORING FOR DEWATERING DISCHARGES

SECTION 8: CERTIFICATION AND NOTIFICATION

SWPPP APPENDICES

SECTION 1: CONTACT INFORMATION/RESPONSIBLE PARTIES

1.1 Operator(s) / Subcontractor(s)

Operator(s):

Federal Highway Administration, Western Federal Lands Highway Division (WFLHD) Jesse (David) Harvey 4851 E. Lupine Dr., Suite D Wasilla, AK 99654 360-833-3338 jesse.harvey@dot.gov Area of Control: Funding agency that approves all design and construction activities

[Repeat as necessary.]

Subcontractor(s):

Insert Company or Organization Name Insert Name Insert Address Insert City, State, Zip Code Insert Telephone Number Insert Fax/Email Insert area of control (if more than one operator at site)

Emergency 24-Hour Contact:

Insert Company or Organization Name Insert Name Insert Telephone Number

Instructions (see definition of “operator” at CGP Part 1.1.1):

― Identify all site operators who will be engaged in construction activities at the site and the areas of the site over which each operator has control (Part 7.2.1). Indicate respective responsibilities, where appropriate. Also include the 24-hour emergency contact.

― List subcontractors expected to work on-site. Notify subcontractors of stormwater requirements applicable to their work.

1.2 Stormwater Team

Instructions (see CGP Parts 6 and 7.2.2):

― Identify the individuals (by name and position) that you have made part of the project’s stormwater team pursuant to CGP Part 6.1, their individual responsibilities, and which members are responsible for inspections. At a minimum the stormwater team is comprised of individuals who are responsible for the design, installation, maintenance, and/or repair of stormwater controls; the application and storage of treatment chemicals (if applicable); conducting inspections as required in CGP Part 4.1; and taking corrective actions as required in Part 5.

― Each member of the stormwater team must have ready access to either an electronic or paper copy of applicable portions of the 2022 CGP and the SWPPP.

― Each member of the stormwater team must understand the requirements of the 2022 CGP and their specific responsibilities with respect to those requirements, including the information in Part 6.2.

― For projects that receive coverage under the 2022 CGP on or after February 17, 2023, to be considered a qualified person under Part 4.1 to conduct inspections under Part 4, you must, at a minimum, either:

Have completed the EPA construction inspection course developed for this permit and have passed the exam; or Hold a current valid construction inspection certification or license from a program that, at a minimum, covers the following:

o Principles and practices of erosion and sediment control and pollution prevention practices at construction sites;

o Proper installation, and maintenance of erosion and sediment controls and pollution prevention practices used at construction sites; and o Performance of inspections, including the proper completion of required reports and documentation, consistent with the requirements of Part 4.

Note that if one of the following topics (e.g., installation and maintenance of pollution prevention practices) is not covered by the non-EPA training program, you may consider supplementing the training with the analogous module of the EPA course (e.g., Module 4) that covers the missing topic.

― Provide copies of training certificates in Tab 12. Training/Certification Log is found in Tab 12 of the SWPPP

― For projects that receive coverage under the 2022 CGP prior to February 17, 2023, any personnel conducting site inspections pursuant to Part 4 on your site must, at a minimum:

Be knowledgeable in the principles and practice of erosion and sediment controls and pollution prevention, Possess the appropriate skills and training in conditions at the construction site that could impact stormwater quality, and Possess the appropriate skills and training in the effectiveness of any stormwater controls selected and installed to meet the requirements of this permit.

https://www.epa.gov/npdes/construction-general-permit-inspector-training

Stormwater Team

To be completed by Contractor

Name and/or Position, and Contact

Responsibilities I Have Completed Training Required by CGP Part 6.2

I Have Read the CGP and Understand the

Applicable Requirements Jesse (David) Harvey Project Engineer 360-833-3338 Jesse.harvey@dot.gov

Provide support and ensure compliance of the SWPPP document and approve Contractor inspections

☒ Yes ☐ No

☒ Yes Date: Click here to enter a date.

Insert name of responsible person Insert Position Insert Telephone Number Insert Email

Insert Responsibility ☐ Yes

☐ Yes a date.

Insert name of responsible person Insert Position Insert Telephone Number Insert Email

Insert Responsibility ☐ Yes

☐ Yes a date.

[Insert or delete rows as necessary.]

Stormwater Team Members Who Conduct Inspections Pursuant to CGP Part 4

To be completed by Contractor

Name and/or Position and Contact

Training(s) Received

Date Training(s)

Completed

If Training is a Non-EPA Training, Confirm that it Satisfies the Minimum

Elements of CGP Part 6.3.b Insert name of responsible person Insert Position Insert Telephone Number Insert Email

Insert Responsibility

Date: Click here to enter a date.

☐ Principles and practices of erosion and sediment control and pollution prevention practices at construction sites

☐ Proper installation and maintenance of erosion and sediment controls and pollution prevention practices used at construction sites

☐ Performance of inspections, including the proper completion of required reports and documentation, consistent with the requirements of Part 4

Insert name of responsible person Insert Position Insert Telephone Number Insert Email

Insert Responsibility

Date: Click here to enter a date.

☐ Principles and practices of erosion and sediment control and pollution prevention practices at construction sites

☐ Proper installation and maintenance of erosion and sediment controls and pollution prevention practices used at construction sites

☐ Performance of inspections, including the proper completion of required reports and documentation, consistent with the requirements of Part 4

Insert name of responsible person Insert Position Insert Telephone Number Insert Email

Insert Responsibility

Date: Click here to enter a date.

☐ Principles and practices of erosion and sediment control and pollution prevention practices at construction sites

☐ Proper installation and maintenance of erosion and sediment controls and pollution prevention practices used at construction sites

☐ Performance of inspections, including the proper completion of required reports and documentation, consistent with the requirements of Part 4

[Insert or delete rows as necessary.]

SECTION 2: SITE EVALUATION, ASSESSMENT, AND PLANNING

2.1 Project/Site Information

Project Name and Address

Project/Site Name: Replace Ghiglione Bridge – AK PRA DENA 10(36) Street/Location: Denali National Park, Mile Post 42 Denali Park Road City: Denali Borough State: Alaska ZIP Code: 99755 County or Similar Government Division: Denali Borough

Project Latitude/Longitude

Latitude: 63.5564º N (decimal degrees)

Longitude: - 149.7542 º W (decimal degrees)

Latitude/longitude data source: ☐ Map ☐ GPS ☒ Other (please specify): Google Earth

Horizontal Reference Datum: ☐ NAD 27 ☐ NAD 83 ☒ WGS 84

Additional Site Information

Is your site located on Indian country lands, or on a property of religious or cultural significance to an Indian Tribe? ☐ Yes ☒ No

If yes, provide the name of the Indian Tribe associated with the area of Indian country (including the name of Indian reservation if applicable), or if not in Indian country, provide the name of the Indian Tribe associated with the property: Insert Text Here

Instructions (see “Project/Site Information,” Section IV of Appendix H – NOI Form and Instructions):

― In this section, compile basic site information that will be helpful when you file your NOI.

2.2 Discharge Information

Does your project/site discharge stormwater into a Municipal Separate Storm Sewer System (MS4)?

Are there any waters of the U.S. within 50 feet of your project’s earth disturbances?

☐ Yes ☒ No

☒ Yes ☐ No

Instructions (see “Discharge Information,” Section V of Appendix H – NOI Form and Instructions):

― In this section, include information relating to your site’s discharge. This information corresponds to the “Discharge Information” section of the NOI form.

― List all of the stormwater points of discharge from your site. Identify each point of discharge with a unique 3-digit ID (e.g., 001, 002).

― For each unique point of discharge you list, specify the name of the first receiving water that receives stormwater directly from the point of discharge and/or from the MS4 that the point of discharge discharges to. You may have multiple points of discharge that discharge to the same receiving water.

― Next, specify whether any waters of the U.S. that you discharge to are listed as “impaired” as defined in Appendix A, and the pollutants causing the impairment.

Identify any Total Maximum Daily Loads (TMDL) that have been completed for any of the waters of the U.S. that you discharge to and the pollutants for which there is a TMDL.

For more information on impaired waters and TMDLs, including a list of TMDL contacts and links by State, visit https://www.epa.gov/tmdl.

― Finally, indicate whether any receiving water that you discharge to is designated as a Tier 2, Tier 2.5, or Tier 3 water and if so, what the designation is (2, 2.5, or 3). A list of Tier 2, 2.5, and 3 waters located in the areas eligible for coverage under this permit can be found at https://www.epa.gov/npdes/construction-general-permit-resources-tools-and-templates.

https://www.epa.gov/sites/production/files/2017-02/documents/2017_cgp_final_appendix_a_-_definitions_508.pdf https://www.epa.gov/tmdl https://www.epa.gov/npdes/construction-general-permit-resources-tools-and-templates https://www.epa.gov/npdes/construction-general-permit-resources-tools-and-templates

For each point of discharge, provide a point of discharge ID (a unique 3-digit ID, e.g., 001, 002), the name of the first receiving water that receives stormwater directly from the point of discharge and/or from the MS4 that the point of discharge discharges to, and the following receiving water information, if applicable:

Point of Discharge

ID

Name of receiving water that receives stormwater discharge:

Is the receiving water impaired (on the CWA 303(d) list)?

If yes, list the pollutants that are causing the impairment:

Has a TMDL been completed for this receiving waterbody?

If yes, list TMDL Name and ID:

Pollutant(s) for which there is a

TMDL:

Is this receiving water designated as a Tier 2, Tier 2.5, or Tier 3 water?

If yes, specify which Tier (2, 2.5, or 3)?

[001] Unnamed Creek (AKA Ghiglione drainage)

☐ Yes ☒ No ☐ Yes ☒ No ☐ Yes ☒ No [INSERT "Tier 2", "Tier 2.5", or "Tier 3"]

[002] Insert Text Here

☐ Yes ☐ No ☐ Yes ☐ No ☐ Yes ☐ No [INSERT "Tier 2", "Tier 2.5", or "Tier 3"]

[003] Insert Text Here

☐ Yes ☐ No ☐ Yes ☐ No ☐ Yes ☐ No [INSERT "Tier 2", "Tier 2.5", or "Tier 3"]

[004] Insert Text Here

☐ Yes ☐ No ☐ Yes ☐ No ☐ Yes ☐ No [INSERT "Tier 2", "Tier 2.5", or "Tier 3"]

[005] Insert Text Here

☐ Yes ☐ No ☐ Yes ☐ No ☐ Yes ☐ No [INSERT "Tier 2", "Tier 2.5", or "Tier 3"]

[006] Insert Text Here

☐ Yes ☐ No ☐ Yes ☐ No ☐ Yes ☐ No [INSERT "Tier 2", "Tier 2.5", or "Tier 3"]

[Include additional rows or delete as necessary.]

2.3 Nature of the Construction Activities

General Description of Project Provide a general description of the nature of your construction activities, including the age or dates of past renovations for structures that are undergoing demolition:

Remove existing seismically deficient bridge and replace it with an earthquake ready bridge.

If you are conducting earth-disturbing activities in response to a public emergency, document the cause of the public emergency (e.g., mud slides, earthquake, extreme flooding conditions, widespread disruption in essential public services), information substantiating its occurrence (e.g., State disaster declaration or similar State or local declaration), and a description of the construction necessary to reestablish affected public services:

N/A

Business days and hours for the project: To be completed by Contractor

Size of Construction Site

Size of Property 2.1 acres

Total Area Expected to be Disturbed by Construction Activities

1.3 acres

Maximum Area Expected to be Disturbed at Any One Time, Including On-site and Off-site Construction Support Areas

5 acres

Instructions (see CGP Parts 1.2.1.c and 7.2.3):

― Provide a general description of the nature of the construction activities at your site.

― Describe the size of the property (in acres or length in miles if a linear construction site), the total area expected to be disturbed by the construction activities (to the nearest quarter acre or quarter mile if a linear construction site), and the maximum area expected to be disturbed at any one time.

― A description of any on-site and off-site construction support activity areas covered by this permit;

― Indicate the type of construction site, whether there will be certain demolition activities, and whether the predevelopment land use was for agriculture.

― Provide a list and description of all pollutant-generating activities (e.g., paving operations; concrete, paint, and stucco washout and waste disposal; solid waste storage and disposal; and dewatering operations) and indicate for each activity the associated pollutants or pollutant constituents (e.g., sediment, fertilizers, pesticides, paints, caulks, sealants, fluorescent light ballasts, contaminated substrates, solvents, fuels) which could be discharged in stormwater from your construction site.

― Describe the construction support activities covered by this permit (see Part 1.2.1.c of the permit).

Size of Construction Site

[Repeat as necessary for individual project phases.]

Type of Construction Site (check all that apply):

☐ Single-Family Residential ☐ Multi-Family Residential ☐ Commercial ☐ Industrial

☐ Institutional ☒ Highway or Road ☐ Utility ☐ Other ____________________________ Will you be discharging dewatering water from your site? ☐ Yes ☒ No If yes, will you be discharging dewatering water from a current or former Federal or State remediation site? ☐ Yes ☐ No

Pollutant-Generating Activities

List and describe all pollutant-generating activities and indicate for each activity the associated pollutants or pollutant constituents that could be discharged in stormwater from your construction site. Take into account where potential spills and leaks could occur that contribute pollutants to stormwater discharges, and any known hazardous or toxic substances, such as PCBs and asbestos, that will be disturbed during construction.

Pollutant-Generating Activity (e.g., paving operations; concrete, paint, and stucco washout and waste disposal; solid waste storage and disposal; and dewatering operations)

Pollutants or Pollutant Constituents (e.g., sediment, fertilizers, pesticides, paints, caulks, sealants, fluorescent light ballasts, contaminated substrates, solvents, fuels)

Clearing, Excavating, and Grading Sediment, Trash, Debris

Fill of roadway embankment, backfill at structures

Sediment, Nutrients, Oil and Grease

Vehicle use fueling and maintenance Oil, Grease, Trash, Debris, Other Pollutants

Structure construction/painting/cleaning pH, Oil, Grease, Trash, Debris, Other Pollutants

Concrete Washout and waste pH, Trash, Debris

Demolition and debris disposal pH, Oil, Grease, Trash, Debris, Heavy Metals, Other

Solid waste (trash and debris) Trash, Debris, Other Pollutants

[Include additional rows or delete as necessary.]

Construction Support Activities (only provide if applicable)

Describe any construction support activities for the project (e.g., concrete or asphalt batch plants, equipment staging yards, material storage areas, excavated material disposal areas, borrow areas):

Insert Description of Construction Support Activity: To be completed by Contractor

East Fork Cabin area (staging)

Pullout areas adjacent to project site (staging)

Toklat Pit (staging)

Toklat River Mining (material source)

5 Mile Pit (material source)

Igloo Pit (housing)

Contact information for construction support activity: To be completed by Contractor Insert Name Insert Telephone No.

Insert Email Insert Address And/Or Latitude/Longitude

2.4 Sequence and Estimated Dates of Construction Activities

Instructions (see CGP Part 7.2.3):

― Describe the intended construction sequence and duration of major activities.

― For each portion or phase of the construction site, include the following:

Commencement and duration of construction activities, including clearing and grubbing, mass grading, demolition activities, site preparation (i.e., excavating, cutting and filling), final grading, and creation of soil and vegetation stockpiles requiring stabilization;

Temporary or permanent cessation of construction activities in each portion of the site;

Temporary or final stabilization of exposed areas for each portion of the site. The dates for stabilization must reflect the applicable deadlines to which you are subject to in Part 2.2.14; and

Removal of temporary stormwater controls and construction equipment or vehicles, and cessation of any construction-related pollutant-generating activities.

― The construction sequence must reflect the following requirements:

Part 2.1.3 (installation of stormwater controls); and Parts 2.2.14 (stabilization deadlines).

Phase I

Insert General Discription of Phase Estimated Start Date of Construction Activities for this Phase

Insert Estimated Date

Estimated End Date of Construction Activities for this Phase

Insert Estimated Date

Estimated Date(s) of Application of Stabilization Measures for Areas of the Site Required to be Stabilized

Insert Estimated Date [Add additional dates as necessary]

Estimated Date(s) when Stormwater Controls will be Removed

Insert Estimated Date [Add additional dates as necessary]

Phase II Insert General Discription of Phase Estimated Start Date of Construction Activities for this Phase

Insert Estimated Date

Estimated End Date of Construction Activities for this Phase

Insert Estimated Date

Estimated Date(s) of Application of Stabilization Measures for Areas of the Site Required to be Stabilized

Insert Estimated Date [Add additional dates as necessary]

Estimated Date(s) when Stormwater Controls will be Removed

Insert Estimated Date [Add additional dates as necessary]

[Repeat as needed.]

2.5 Authorized Non-Stormwater Discharges

List of Authorized Non-Stormwater Discharges Present at the Site

Authorized Non-Stormwater Discharge Will or May Occur at Your Site?

Discharges from emergency fire-fighting activities ☐ Yes ☒ No Fire hydrant flushings ☐ Yes ☒ No Landscape irrigation ☐ Yes ☒ No Water used to wash vehicles and equipment ☐ Yes ☒ No Water used to control dust ☒ Yes ☐ No Potable water including uncontaminated water line flushings ☐ Yes ☒ No External building washdown (soaps/solvents are not used and external surfaces do not contain hazardous substances)

☐ Yes ☒ No

Pavement wash waters ☐ Yes ☒ No Uncontaminated air conditioning or compressor condensate ☐ Yes ☒ No

Instructions (see CGP Parts 1.2.2 and 7.2.5):

― Identify all authorized non-stormwater discharges. The authorized non-stormwater discharges identified in Part 1.2.2 of the 2022 CGP include:

Discharges from emergency fire-fighting activities;

Fire hydrant flushings;

Landscape irrigation;

Waters used to wash vehicles and equipment, provided that there is no discharge of soaps, solvents, or detergents used for such purposes;

Water used to control dust;

Potable water including uncontaminated water line flushings;

External building washdown, provided soaps, solvents and detergents are not used, and external surfaces do not contain hazardous substances as defined in CGP Appendix A (e.g., paint or caulk containing polychlorinated biphenyls (PCBs));

Pavement wash waters provided spills or leaks of toxic or hazardous materials have not occurred (unless all spilled material has been removed) and detergents are not used. You are prohibited from directing pavement wash waters directly into any receiving water, storm drain inlet, or constructed or natural site drainage features, unless the conveyance is connected to a sediment basin, sediment trap, or similarly effective control;

Uncontaminated air conditioning or compressor condensate;

Uncontaminated, non-turbid discharges of ground water or spring water;

Foundation or footing drains where flows are not contaminated with process materials such as solvents or contaminated ground water; and Uncontaminated construction dewatering water discharged in accordance with

Part 2.4.

Authorized Non-Stormwater Discharge Will or May Occur at Your Site?

Uncontaminated, non-turbid discharges of ground water or spring water ☐ Yes ☒ No Foundation or footing drains ☐ Yes ☒ No Uncontaminated construction dewatering water ☐ Yes ☒ No

(Note: You are required to identify the likely locations of these authorized non-stormwater discharges on your site map. See Section 2.6, below, of this SWPPP Template.)

2.6 Site Maps

Instructions (see CGP Part 7.2.4):

― Attach site maps in Tabs 5 and 6 of the SWPPP Binder. For most projects, a series of site maps is necessary and recommended. The first should show the undeveloped site and its current features. An additional map or maps should be created to show the developed site or, for more complicated sites, show the major phases of development.

These maps must include the following features:

― Boundaries of the property and of the locations where construction will occur, including:

Locations where earth-disturbing activities will occur, noting any phasing of construction activities and any demolition activities;

Approximate slopes before and after major grading activities. Note any areas of steep slopes, as defined in CGP Appendix A;

Locations where sediment, soil, or other construction materials will be stockpiled;

Locations of any crossings of receiving waters;

Designated points where vehicles will exit onto paved roads;

Locations of structures and other impervious surfaces upon completion of construction; and Locations of on-site and off-site construction support activity areas covered by the permit (see CGP Part 1.2.1.c).

― Locations of any receiving waters, including wetlands, within your site and all receiving waters within one mile downstream of the site’s discharge point(s). Indicate which receiving waters are listed as impaired, and which are identified by your State, Tribe, or EPA as Tier 2, Tier 2.5, or Tier 3 waters.

― Any areas of Federally-listed critical habitat for endangered or threatened species within the action area of the site as defined in CGP Appendix A (Helpful resources: CGP Appendix D and www.epa.gov/npdes/construction-general-permit-cgp-threatened-and-endangered-species-eligibility).

― Type and extent of pre-construction cover on the site (e.g., vegetative cover, forest, pasture, pavement, structures).

― Drainage pattern(s) of stormwater and authorized non-stormwater before and after major grading activities.

― Stormwater and authorized non-stormwater discharge locations, including:

Locations where stormwater and/or authorized non-stormwater will be discharged to storm drain inlets, including a notation of whether the inlet conveys stormwater to a sediment basin, sediment trap, or similarly effective control; and

Locations where stormwater or allowable non-stormwater will be discharged directly to receiving waters, including wetlands (i.e., not via a storm drain inlet).

Locations where turbidity benchmark monitoring will take place to comply with Part 3.3, if applicable to your site.

― Locations of all potential pollutant-generating activities identified in Part 7.2.3g (note:

you should have those identified in Section 2.3 (Nature of the Construction Activities) in this SWPPP Template).

― Designated areas where construction wastes that are covered by the exception in Part 2.3.3e.ii (i.e., they are not pollutant-generating) will be stored.

http://www.epa.gov/npdes/construction-general-permit-cgp-threatened-and-endangered-species-eligibility http://www.epa.gov/npdes/construction-general-permit-cgp-threatened-and-endangered-species-eligibility

― Locations of stormwater controls, including natural buffer areas and any shared controls utilized to comply with the permit.

― Locations where polymers, flocculants, or other treatment chemicals will be used and stored.

SECTION 3: DOCUMENTATION OF COMPLIANCE WITH OTHER FEDERAL REQUIREMENTS

3.1 Endangered Species Protection

Eligibility Criterion Following the process outlined in Appendix D, under which criterion are you eligible for coverage under this permit?

☒ Criterion A: No ESA-listed species and/or designated critical habitat present in action area. Using the process outlined in Appendix D of the CGP, you certify that ESA-listed species and designated critical habitat(s) under the jurisdiction of the USFWS or NMFS are not likely to occur in your site’s “action area” as defined in Appendix A of the CGP.

Please Note: NMFS’ jurisdiction includes ESA-listed marine and estuarine species that spawn in inland rivers.

☒ Check to confirm you have provided documentation in your SWPPP as required by CGP Appendix D (Note: reliance on State resources is not acceptable; see CGP Appendix D).

Documentation: Endangered Species criterion eligibility is filed in TAB 16.

Instructions (see CGP Parts 1.1.5, 7.2.9.a, Appendix D, and the “Endangered Species Protection” section of the Appendix H – NOI Form and Instructions as well as resources available at www.epa.gov/npdes/construction-general-permit-cgp-threatened-and-endangered-species-eligibility):

Using the instructions in Appendix D of the permit, determine which criterion listed below (A-F) applies with respect to the protection of endangered species. To make this determination, you must use information from BOTH the National Marine Fisheries Service (NMFS) and U.S. Fish and Wildlife Service (USFWS). Both the NMFS and USFWS maintain lists of Endangered Species Act-listed (ESA-listed) species and designated critical habitat. Operators must consult both when determining their eligibility.

― Check only 1 box, include the required information, and provide a sound basis for supporting the criterion selected. Select the most conservative criterion that applies.

― Copies of the ESA compliance documentation should be placed in Tab 16 of the

SWPPP.

https://www.epa.gov/sites/production/files/2017-02/documents/2017_cgp_final_appendix_d_-_endangered_species_reqs_508.pdf

Following the process outlined in Appendix D, under which criterion are you eligible for coverage under this permit?

☐ Criterion B: Eligibility requirements met by another operator under the 2022 CGP. The construction site’s discharges and discharge-related activities were already addressed in another operator’s valid certification of eligibility for your “action area” under eligibility Criterion A, C, D, E, or F of the 2022 CGP and you have confirmed that no additional ESA-listed species and/or designated critical habitat under the jurisdiction of USFWS and/or NMFS not considered in the that certification may be present or located in the “action area.” To certify your eligibility under this criterion, there must be no lapse of NPDES permit coverage in the other CGP operator’s certification. By certifying eligibility under this criterion, you agree to comply with any conditions upon which the other CGP operator's certification was based. You must include in your NOI the NPDES ID from the other 2022 CGP operator’s notification of authorization under this permit and list any measures that you must comply with. If your certification is based on another 2022 CGP operator’s certification under criterion C, you must provide EPA with the relevant supporting information required of existing dischargers in Criterion C.

☐ Check to confirm you have provided documentation in your SWPPP as required by CGP Appendix D.

Documentation: Insert Text Here

☐ Criterion C: Discharges not likely to result in any short- or long-term adverse effects to ESA-listed species and/or designated critical habitat. ESA-listed species and/or designated critical habitat(s) under the jurisdiction of the USFWS and/or NMFS are likely to occur in or near your site’s “action area,” and you certify to EPA that your site’s discharges and discharge-related activities are not likely to result in any short- or long-term adverse effects to ESA-listed threatened or endangered species and/or designated critical habitat. This certification may include consideration of any stormwater controls and/or management practices you will adopt to ensure that your discharges and discharge-related activities are not likely to result in any short- or long-term adverse effects to ESA-listed species and/or designated critical habitat. To certify your eligibility under this criterion, indicate 1) the ESA-listed species and/or designated habitat located in your “action area” using the process outlined in Appendix D of this permit; 2) the distance between the site and the listed species and/or designated critical habitat in the action area (in miles); and 3) a rationale describing specifically how short- or long-term adverse effects to ESA-listed species will be avoided from the discharges and discharge-related activities. (Note: You must include a copy of your site map from your SWPPP showing the upland and in-water extent of your “action area” with your NOI.)

Following the process outlined in Appendix D, under which criterion are you eligible for coverage under this permit?

☐ Criterion D: Coordination with USFWS and/or NMFS has successfully concluded.

Coordination between you and the USFWS and/or NMFS has concluded. The coordination must have addressed the effects of your site’s discharges and discharge-related activities on ESA-listed species and/or designated critical habitat under the jurisdiction of USFWS and/or NMFS, and resulted in a written confirmation from USFWS and/or NMFS that the effects of your site’s discharges and discharge-related activities are not likely to result in any short- or long-term adverse effects. By certifying eligibility under this criterion, you agree to comply with any conditions you must meet for your site’s discharges and discharge-related activities to not likely result in any short- or long-term adverse effects. You must include copies of the correspondence with the participating agencies in your SWPPP and this NOI.

Following the process outlined in Appendix D, under which criterion are you eligible for coverage under this permit?

☐ Criterion E: ESA Section 7 consultation has successfully concluded. Consultation between a Federal agency and the USFWS and/or NMFS under section 7 of the ESA has concluded. Consultations can be either formal or informal, and would have occurred only as a result of a separate Federal action (e.g., during application for an individual wastewater discharge permit or the issuance of a wetlands dredge and fill permit), and the consultation must have addressed the effects of your construction activity’s discharges and discharge-related activities on all ESA-listed threatened or endangered species and all designated critical habitat under the jurisdiction of each Service, as appropriate, in your action area. The result of this consultation must be either:

i. A biological opinion currently in effect that determined that the action in question (taking into account the effects of your facility’s discharges and discharge-related activities) is likely to adversely affect, but is not likely to jeopardize the continued existence of listed species or result in the destruction or adverse modification of critical habitat. The biological opinion must have included the effects of your facility’s discharges and discharge-related activities on all the listed species and designated critical habitat in your action area under the jurisdiction of each Service, as appropriate. To be eligible under (i), any reasonable and prudent measures specified in the incidental take statement must be implemented;

ii. Written concurrence (e.g., letter of concurrence) from the applicable Service(s) with a determination that your facility’s discharges and discharge-related activities are not likely to adversely affect ESA-listed species and/or designated critical habitat. The concurrence letter must have included the effects of your facility’s discharges and discharge-related activities on all the ESA-listed species and/or designated critical habitat on your species list(s) acquired from USFWS and/or NMFS as part of this worksheet.

The consultation does not warrant reinitiation under 50 CFR §402.16; or, if reinitiation of consultation is required (e.g., due to a new species listing, critical habitat designation, or new information), the Federal action agency has reinitiated the consultation and the result of the consultation is consistent with the statements above. (Note: you must include any reinitiation documentation from the Services or consulting Federal agency with your

NOI.) -

Following the process outlined in Appendix D, under which criterion are you eligible for coverage under this permit?

☐ Criterion F: Issuance of section 10 permit. Potential take is authorized through the issuance of a permit under section 10 of the ESA by the USFWS and/or NMFS, and this authorization addresses the effects of the site’s discharges and discharge-related activities on ESA-listed species and designated critical habitat. You must include copies of the correspondence between yourself and the participating agencies in your SWPPP and your NOI.

3.2 Historic Property Screening Process

Appendix E, Step 1 Do you plan on installing any stormwater controls that require subsurface earth disturbance, including, but not limited to, any of the following stormwater controls at your site? Check all that apply below, and proceed to Appendix E, Step 2.

☐ Dike

☐ Berm

☐ Catch Basin

☐ Pond

☒ Constructed Site Drainage Feature (e.g., ditch, trench, perimeter drain, swale, etc.)

☒ Culvert

☐ Channel

☐ Other type of ground-disturbing stormwater control: Insert Specific Type of Stormwater Control

Instructions (see CGP Part 1.1.6, 7.2.9.b, Appendix E, and the “Historic Preservation” section of the Appendix H – NOI Form and Instructions):

Follow the screening process in Appendix E of the permit to determine whether your installation of subsurface earth-disturbing stormwater controls will have an effect on historic properties.

― Include documentation supporting your determination of eligibility. Place copies of 106 compliance documentation in Tab 16 of the SWPPP.

― To contact your applicable State historic preservation office, information is available at https://ncshpo.org/directory/ ― To contact your applicable Tribal historic preservation office, information is available at https://grantsdev.cr.nps.gov/THPO_Review/index.cfm https://ncshpo.org/directory/ https://nam04.safelinks.protection.outlook.com/?url=https%3A%2F%2Fgrantsdev.cr.nps.gov%2FTHPO_Review%2Findex.cfm&data=04%7C01%7Ckelly.davis%40erg.com%7C898fb93eab9d43e60b4508d9c16a30f9%7Ca17e3fab8d2346f287f33fceb7c6a000%7C1%7C0%7C637753484094895417%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000&sdata=i9ndRCbrdBzpRWqvylm79rzzgXSCirdp2J14QNx7h8Q%3D&reserved=0

(Note: If you will not be installing any subsurface earth-disturbing stormwater controls, no further documentation is required for Section 3.2 of the Template.)

Appendix E, Step 2 If you answered yes in Step 1, have prior professional cultural resource surveys or other evaluations determined that historic properties do not exist, or have prior disturbances at the site have precluded the existence of historic properties? ☐ YES ☒ NO If yes, no further documentation is required for Section 3.2 of the Template and you may provide the prior documentation in your SWPPP.

Insert references and information sources relied upon to determine that prior to your project, no historic properties exist at your site based on available information, including information that may be provided by your applicable SHPO, THPO, or other Tribal representative or references and information sources relied upon to determine that prior earth disturbances may have eliminated he possibility that historic properties exist on your site.

If no, proceed to Appendix E, Step 3.

Appendix E, Step 3 If you answered no in Step 2, have you determined that your installation of subsurface earth-disturbing stormwater controls will have no effect on historic properties? ☐ YES ☒ NO

If yes, provide documentation of the basis for your determination. Insert references to documents, studies, or other sources relied upon If no, proceed to Appendix E, Step 4.

Appendix E, Steps 4 and 5 If you answered no in Step 3, did the State Historic Preservation Officer (SHPO), Tribal Historic Preservation Office (THPO), or other Tribal representative (whichever applies) respond to you within 15 calendar days to indicate their views as to the likelihood that historic properties are potentially present on your site and may be impacted by the installation of stormwater controls that require subsurface earth disturbance? ☒ YES ☐ NO

If yes, describe the nature of their response:

☐ Written indication that no historic properties will be affected by the installation of stormwater controls. Insert copies of letters, emails, or other communication between you and the applicable SHPO, THPO, or other Tribal representative

☒ Written indication that adverse effects to historic properties from the installation of stormwater controls can be mitigated by agreed upon actions.

SHPO Concurrence Letter dated 8/22/2019, concurring with finding of Adverse Effect and Programmatic Agreement between NPS and the SHPO, signed by SHPO on 8/18/2020

☐ No agreement has been reached regarding measures to mitigate effects to historic properties from the installation of stormwater controls. Provide a description of any significant remaining disagreements regarding mitigation measures and insert copies of letters, emails, or other communication between you and the applicable SHPO, THPO, or other Tribal representative

☐ Other: Insert copies of letters, emails, or other communication between you and the applicable SHPO, THPO, or other Tribal representative

If no, no further documentation is required for Section 3.2 of the Template.

3.3 Safe Drinking Water Act Underground Injection Control Requirements

Do you plan to install any of the following controls? Check all that apply below.

☐ Infiltration trenches (if stormwater is directed to any bored, drilled, driven shaft or dug hole that is deeper than its widest surface dimension, or has a subsurface fluid distribution system)

☐ Commercially manufactured pre-cast or pre-built proprietary subsurface detention vaults, chambers, or other devices designed to capture and infiltrate stormwater flow

☐ Drywells, seepage pits, or improved sinkholes (if stormwater is directed to any bored, drilled, driven shaft or dug hole that is deeper than its widest surface dimension, or has a subsurface fluid distribution system)

If yes, insert copies of letters, emails, or other communication between you and the State agency or EPA regional office.

Instructions (see CGP Part 7.2.9.c):

― If you will use any of the identified controls in this section, document any contact you have had with the applicable State agency or EPA Regional Office responsible for implementing the requirements for underground injection wells in the Safe Drinking Water Act and EPA’s implementing regulations at 40 CFR Parts 144-147.

― For State UIC program contacts, refer to the following EPA website:

https://www.epa.gov/uic.

https://www.epa.gov/uic

SECTION 4: EROSION AND SEDIMENT CONTROLS AND DEWATERING PRACTICES

4.1 Natural Buffers or Equivalent Sediment Controls

Buffer Compliance Alternatives Are there any receiving waters within 50 feet of your project’s earth disturbances? ☒ YES ☐ NO

(Note: If no, no further documentation is required for Section 4.1 in the SWPPP Template.

Continue to Section 4.2.)

Check the compliance alternative that you have chosen:

☐ (i) I will provide and maintain a 50-foot undisturbed natural buffer.

(Note 1: You must show the 50-foot boundary line of the natural buffer on your site map.)

(Note 2: You must show on your site map how all discharges from your construction disturbances through the natural buffer area will first be treated by the site’s erosion and sediment controls. Also, show on the site map any velocity dissipation devices used to prevent erosion within the natural buffer area.)

General Instructions (See CGP Parts 2.2 and 7.2.6):

― Describe the erosion and sediment controls that will be implemented at your site to meet the requirements of CGP Part 2.2.

― Describe any applicable stormwater control design specifications (including references to any manufacturer specifications and/or erosion and sediment control manuals/ordinances relied upon).

― Describe any routine stormwater control maintenance specifications.

― Describe the projected schedule for stormwater control installation/implementation.

Instructions (see CGP Parts 2.2.1 and 7.2.6.b.i, and Appendix F):

This section only applies to you if discharge to a receiving water is located within 50 feet of your site’s earth disturbances. If this is the case, consult CGP Part 2.2.1 and Appendix F for information on how to comply with the buffer requirements.

― Describe the compliance alternative (CGP Part 2.2.1.a.i, ii, or iii) that you will implement to meet the buffer requirements, and include any required documentation supporting the alternative selected. For alternative 3, also include why it is infeasible for you to provide and maintain an undisturbed natural buffer of any size. For “linear construction sites” where it is infeasible to implement alternative 1, 2, or 3, also include a description of any buffer width retained and/or supplemental erosion and sediment controls installed. The compliance alternative selected must be maintained throughout the duration of permit coverage. However, if you select a different compliance alternative during your period of permit coverage, you must modify your SWPPP to reflect this change.

― If you qualify for one of the exceptions in CGP Part 2.2.1.b, include documentation related to your qualification for such exceptions.

☐ (ii) I will provide and maintain an undisturbed natural buffer that is less than 50 feet and is supplemented by additional erosion and sediment controls that achieve, in combination, the sediment load reduction equivalent to a 50-foot undisturbed natural buffer.

(Note 1: You must show the boundary line of the natural buffer on your site map.)

(Note 2: You must show on your site map how all discharges from your construction disturbances through the natural buffer area will first be treated by the site’s erosion and sediment controls.