This document is a Bid Tabulation Report for the Replace Ghiglione Bridge project (Project No. AK PRA DENA 10(36)) located in Denali National Park, Alaska. The solicitation (No. 69056725B000009) was opened on 11/25/2025 in Vancouver, WA, with three contractors submitting bids: Hamilton Construction Co., Tutka, LLC, and Granite Construction Company. The project involves two schedules - Schedule A (Base) and Schedule X (Option), with bids ranging from $8,598,635 to $12,407,468 for Schedule A, and $1,651,225 to $3,554,500 for Schedule X.
The bid includes a HUBZone price evaluation preference under Federal Acquisition clause 52.219-4, which adds a 10% factor to the price of the lowest responsive bid when submitted by a large business. For Schedule A, Hamilton Construction Co. submitted the lowest base bid at $8,598,635, while Tutka, LLC (a HUBZone small business) bid $9,374,068. The bid covers numerous line items including mobilization, construction survey, quality control, soil erosion control, roadway excavation, concrete work, structural steel, traffic control, and various equipment and labor services. The Engineer's Estimate was significantly higher than the submitted bids, suggesting potential cost savings for the government.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
In accordance with Federal Acquisition clause 52.219-4, Notice of Price Evaluation
Preference for HUBZone Small Business Concerns, a factor of 10% is added to the price of the lowest, responsive bidder when the low bid is submitted by a LARGE business.
For evaluation purposes, we consider only the apparent low bid and the lowest bid submitted by a HUBZone firm.
This calculation is for evaluation purposes only.
Award amounts will reflect the numbers in the "Bid Amount" column.
HUBZone
Schedule A and Option X Price Final
Business Evaluation
Evaluation- Schedule and Option X
Contractor
Total Base
Schedule A and
Option X Type Factor Price Rank
Hamilton Construction Co. $10,249,860.00 Large 1,024,986.00$ $11,274,846.00 1
Tutka, LLC $12,407,468.00 Hubzone Small n/a $12,407,468.00 2
Application of HUBZone Price Evaluation Preference to the Tabulation of Bids
Project No: AK PRA DENA 10(36)
Project Name: Replace Ghiglione Bridge
Solicitation No:69056725B000009
BID TABULATION REPORT
Project No. : AK PRA DENA 10(36) Project Name: Replace Ghiglione Bridge
Contractor Responsive? Base Schedule A Granite Construction Company $9,248,350.00 Tutka, LLC $9,374,068.00 Hamilton Construction Co. $8,598,635.00 Engineer's Estimate $12,044,890.00
Contractor Responsive? Total Base Schedule A and Option(s): X Granite Construction Company $12,802,850.00 Tutka, LLC $12,407,468.00 Hamilton Construction Co. $10,249,860.00 Engineer's Estimate $15,040,890.00
Contractor Responsive? Option: X Granite Construction Company $3,554,500.00 Tutka, LLC $3,033,400.00 Hamilton Construction Co. $1,651,225.00 Engineer's Estimate $2,996,000.00
Project No. : AK PRA DENA 10(36) Project Name: Replace Ghiglione Bridge
Division: Western Federal Lands
Schedule: A Schedule Type: Base Lead Designer:
Solicitation No. : 69056725B000009 Opened at: Vancouver, WA Opened by: Angy Liljedahl
State: AK County: Denali Federal Land: Denali National Park Bid Open Date and Time: 11/25/2025
Contract Awarded to: Award Date:
Contractor Comment Bid Amount Responsive Tutka, LLC, 2485 E Zak Circle, Suite A, Wasilla, AK, 99654
$9,374,068.00
Granite Construction Company, 585 West Beach Street, Watsonville, CA, 95076
$9,248,350.00
Hamilton Construction Co., PO BOX 659, Springfield, OR, 97477
$8,598,635.00
Engineer's Estimate $12,044,890.00
I certify that this Bid Tabulation reflects the offers received for this solicitation
Project No. : AK PRA DENA 10(36) Project Name: Replace Ghiglione Bridge Schedule: A Schedule Type: Base
Line Item Number
Pay Item Number Description Contractor Quantity Unit Unit Price Amount
A0010 15101-0000 MOBILIZATION Tutka, LLC $2,350,000.00 Granite Construction Company $900,000.00
Hamilton Construction Co. $859,000.00
Engineer's Estimate ALL LPSM LPSM $2,421,000.00
Signed:
Title: Contracting Officer
Date: 11/26/2025
A0020 15201-0000 CONSTRUCTION
SURVEY AND
STAKING
Tutka, LLC $150,000.00 Granite Construction Company $100,000.00
Hamilton Construction Co. $70,000.00
Engineer's Estimate ALL LPSM LPSM $224,000.00
A0030 15301-0000 CONTRACTOR
QUALITY CONTROL
Hamilton Construction Co. $500,000.00
Granite Construction Company $250,000.00
Tutka, LLC $250,000.00 Engineer's Estimate ALL LPSM LPSM $314,000.00
A0040 15401-0000 CONTRACTOR
TESTING
Tutka, LLC $200,000.00 Granite Construction Company $125,000.00
Hamilton Construction Co. $95,000.00
Engineer's Estimate ALL LPSM LPSM $134,000.00
A0050 15501-0000 CONSTRUCTION
SCHEDULE
Granite Construction Company $100,000.00
Tutka, LLC $20,000.00 Hamilton Construction Co. $15,000.00
Engineer's Estimate ALL LPSM LPSM $45,000.00
A0060 15705-0100 SOIL EROSION
CONTROL, SILT
FENCE
Tutka, LLC 550.000 $18.00 $9,900.00 Granite Construction Company 550.000 $15.00 $8,250.00
Hamilton Construction Co. 550.000 $12.50 $6,875.00
Engineer's Estimate 550.000 LNFT $35.00 $19,250.00
A0070 15705-1400 SOIL EROSION
CONTROL, FIBER
ROLL
Hamilton Construction Co. 2,500.000 $14.25 $35,625.00
Granite Construction Company 2,500.000 $10.00 $25,000.00
Tutka, LLC 2,500.000 $9.00 $22,500.00 Engineer's Estimate 2,500.000 LNFT $12.00 $30,000.00
A0080 15706-0200 SOIL EROSION
CONTROL, CHECK
DAM
Hamilton Construction Co. 4.000 $1,500.00 $6,000.00
Tutka, LLC 4.000 $1,500.00 $6,000.00 Granite Construction Company 4.000 $500.00 $2,000.00
Engineer's Estimate 4.000 EACH $1,200.00 $4,800.00
A0090 20101-0000 CLEARING AND
GRUBBING
Hamilton Construction Co. 1.400 $52,000.00 $72,800.00
Tutka, LLC 1.400 $40,000.00 $56,000.00
A0090 20101-0000 CLEARING AND
GRUBBING
Granite Construction Company 1.400 $10,000.00 $14,000.00
Engineer's Estimate 1.400 ACRE $25,000.00 $35,000.00
A0100 20301-1900 REMOVAL OF PIPE
CULVERT
Tutka, LLC 1.000 $10,000.00 $10,000.00 Granite Construction Company 1.000 $5,000.00 $5,000.00
Hamilton Construction Co. 1.000 $2,000.00 $2,000.00
Engineer's Estimate 1.000 EACH $5,000.00 $5,000.00
A0110 20304-2000 REMOVAL OF
BRIDGE
Hamilton Construction Co. $665,000.00
Granite Construction Company $550,000.00
Tutka, LLC $450,000.00 Engineer's Estimate ALL LPSM LPSM $750,000.00
A0120 20401-0000 ROADWAY
EXCAVATION
Tutka, LLC 1,400.000 $50.00 $70,000.00 Granite Construction Company 1,400.000 $30.00 $42,000.00
Hamilton Construction Co. 1,400.000 $30.00 $42,000.00
Engineer's Estimate 1,400.000 CUYD $65.00 $91,000.00
A0130 20403-0000 UNCLASSIFIED
BORROW
(GOVERNMENT
FURNISHED)
Granite Construction Company 1,200.000 $100.00 $120,000.00
Tutka, LLC 1,200.000 $67.00 $80,400.00 Hamilton Construction Co. 1,200.000 $30.00 $36,000.00
Engineer's Estimate 1,200.000 CUYD $65.00 $78,000.00
A0140 20702-0300 GEOTEXTILE
FILTER, CLASS 1,
TYPE C (NON-
WOVEN)
Hamilton Construction Co. 1,100.000 $8.00 $8,800.00
Granite Construction Company 1,100.000 $5.00 $5,500.00
Tutka, LLC 1,100.000 $5.00 $5,500.00 Engineer's Estimate 1,100.000 SQYD $25.00 $27,500.00
A0150 21101-1000 ROADWAY
OBLITERATION,
METHOD 1
Hamilton Construction Co. 410.000 $47.00 $19,270.00
Tutka, LLC 410.000 $19.00 $7,790.00 Granite Construction Company 410.000 $15.00 $6,150.00
Engineer's Estimate 410.000 SQYD $130.00 $53,300.00
A0160 25101-0300 PLACED RIPRAP,
METHOD A, CLASS
3 (GOVERNMENT
FURNISHED)
Granite Construction Company 400.000 $150.00 $60,000.00
Tutka, LLC 400.000 $88.00 $35,200.00 Hamilton Construction Co. 400.000 $53.00 $21,200.00
Engineer's Estimate 400.000 CUYD $180.00 $72,000.00
A0170 25120-0200 RIPRAP DITCH,
METHOD A, CLASS
2 (GOVERNMENT
FURNISHED)
Tutka, LLC 470.000 $113.00 $53,110.00 Granite Construction Company 470.000 $75.00 $35,250.00
Hamilton Construction Co. 470.000 $53.00 $24,910.00
Engineer's Estimate 470.000 LNFT $85.00 $39,950.00
A0180 30201-2000 ROADWAY
AGGREGATE,
METHOD 2
(GOVERNMENT
FURNISHED)
Tutka, LLC 910.000 $83.00 $75,530.00 Granite Construction Company 910.000 $75.00 $68,250.00
Hamilton Construction Co. 910.000 $30.00 $27,300.00
Engineer's Estimate 910.000 CUYD $160.00 $145,600.00
A0190 55101-0200 CONCRETE FILLED
STEEL PIPE PILE, IN
PLACE (18-INCH X
0.5-INCH)
(GOVERNMENT
FURNISHED PILE)
Granite Construction Company 1,258.000 $1,250.00 $1,572,500.00
Tutka, LLC 1,258.000 $900.00 $1,132,200.00 Hamilton Construction Co. 1,258.000 $650.00 $817,700.00
Engineer's Estimate 1,258.000 LNFT $750.00 $943,500.00
A0200 55104-1000 DYNAMIC PILE
LOAD TEST
Granite Construction Company 5.000 $10,000.00 $50,000.00
Tutka, LLC 5.000 $9,000.00 $45,000.00 Hamilton Construction Co. 5.000 $5,250.00 $26,250.00
Engineer's Estimate 5.000 EACH $25,000.00 $125,000.00
A0210 55116-0000 SPLICE (18-INCH
DIAMETER)
Granite Construction Company 20.000 $5,000.00 $100,000.00
Tutka, LLC 20.000 $3,500.00 $70,000.00 Hamilton Construction Co. 20.000 $500.00 $10,000.00
Engineer's Estimate 20.000 EACH $3,000.00 $60,000.00
A0220 55201-0200 STRUCTURAL
CONCRETE, CLASS
A (AE)
Hamilton Construction Co. 230.000 $10,550.00 $2,426,500.00
Granite Construction Company 230.000 $10,000.00 $2,300,000.00
Tutka, LLC 230.000 $8,500.00 $1,955,000.00 Engineer's Estimate 230.000 CUYD $12,500.00 $2,875,000.00
A0230 55401-1000 REINFORCING
STEEL
Tutka, LLC 20,200.000 $6.40 $129,280.00 Hamilton Construction Co. 20,200.000 $5.00 $101,000.00
Granite Construction Company 20,200.000 $4.50 $90,900.00
Engineer's Estimate 20,200.000 LB $7.00 $141,400.00
A0240 55401-2000 REINFORCING
STEEL, EPOXY
COATED
Tutka, LLC 44,500.000 $5.38 $239,410.00 Granite Construction Company 44,500.000 $5.00 $222,500.00
A0240 55401-2000 REINFORCING
STEEL, EPOXY
COATED
Hamilton Construction Co. 44,500.000 $5.00 $222,500.00
Engineer's Estimate 44,500.000 LB $8.00 $356,000.00
A0250 55502-0000 STRUCTURAL
STEEL, FURNISHED,
FABRICATED, AND
ERECTED
Granite Construction Company 137,000.000 $10.00 $1,370,000.00
Hamilton Construction Co. 137,000.000 $8.50 $1,164,500.00
Tutka, LLC 137,000.000 $4.11 $563,070.00 Engineer's Estimate 137,000.000 LB $10.00 $1,370,000.00
A0260 55601-1400 BRIDGE RAILING,
TIMBER, STEEL-
BACKED
Tutka, LLC 388.000 $700.00 $271,600.00 Granite Construction Company 388.000 $550.00 $213,400.00
Hamilton Construction Co. 388.000 $500.00 $194,000.00
Engineer's Estimate 388.000 LNFT $1,000.00 $388,000.00
A0270 56401-1000 BEARING DEVICE,
ELASTOMERIC
Hamilton Construction Co. 40.000 $3,250.00 $130,000.00
Tutka, LLC 40.000 $2,000.00 $80,000.00 Granite Construction Company 40.000 $1,500.00 $60,000.00
Engineer's Estimate 40.000 EACH $5,000.00 $200,000.00
A0280 60201-0800 24-INCH PIPE
CULVERT
Tutka, LLC 185.000 $450.00 $83,250.00 Hamilton Construction Co. 185.000 $300.00 $55,500.00
Granite Construction Company 185.000 $250.00 $46,250.00
Engineer's Estimate 185.000 LNFT $250.00 $46,250.00
A0290 61103-1600 24-INCH
ENCASEMENT PIPE,
POLYVINYL
CHLORIDE (PVC)
(PILE SLEEVE)
Hamilton Construction Co. 180.000 $3,000.00 $540,000.00
Tutka, LLC 180.000 $3,000.00 $540,000.00 Granite Construction Company 180.000 $2,500.00 $450,000.00
Engineer's Estimate 180.000 LNFT $2,500.00 $450,000.00
A0300 61707-2000 STRUCTURE
TRANSITION
RAILING, SBT
SYSTEM
Granite Construction Company 40.000 $1,000.00 $40,000.00
Hamilton Construction Co. 40.000 $850.00 $34,000.00
Tutka, LLC 40.000 $533.00 $21,320.00 Engineer's Estimate 40.000 LNFT $1,500.00 $60,000.00
A0310 62201-0300 DUMP TRUCK, 12
CUBIC YARD
MINIMUM
CAPACITY
Hamilton Construction Co. 40.000 $280.00 $11,200.00
Granite Construction Company 40.000 $215.00 $8,600.00
Tutka, LLC 40.000 $215.00 $8,600.00 Engineer's Estimate 40.000 HOUR $210.00 $8,400.00
A0320 62201-1000 WHEEL LOADER, 4
CUBIC YARD
MINIMUM RATED
CAPACITY
Hamilton Construction Co. 40.000 $380.00 $15,200.00
Granite Construction Company 40.000 $275.00 $11,000.00
Tutka, LLC 40.000 $215.00 $8,600.00 Engineer's Estimate 40.000 HOUR $210.00 $8,400.00
A0330 62201-1350 BULLDOZER, 200HP
MINIMUM
FLYWHEEL POWER
Hamilton Construction Co. 40.000 $500.00 $20,000.00
Granite Construction Company 40.000 $300.00 $12,000.00
Tutka, LLC 40.000 $225.00 $9,000.00 Engineer's Estimate 40.000 HOUR $220.00 $8,800.00
A0340 62201-2050 ROLLER Hamilton Construction Co. 40.000 $350.00 $14,000.00
Granite Construction Company 40.000 $250.00 $10,000.00
Tutka, LLC 40.000 $180.00 $7,200.00 Engineer's Estimate 40.000 HOUR $290.00 $11,600.00
A0350 62201-2800 MOTOR GRADER, 8
FOOT MINIMUM
BLADE
Hamilton Construction Co. 40.000 $510.00 $20,400.00
Granite Construction Company 40.000 $300.00 $12,000.00
Tutka, LLC 40.000 $230.00 $9,200.00 Engineer's Estimate 40.000 HOUR $230.00 $9,200.00
A0360 62201-3400 HYDRAULIC
EXCAVATOR, 1
CUBIC YARD
MINIMUM
CAPACITY WITH
THUMB
ATTACHMENT
Hamilton Construction Co. 40.000 $640.00 $25,600.00
Granite Construction Company 40.000 $300.00 $12,000.00
Tutka, LLC 40.000 $250.00 $10,000.00 Engineer's Estimate 40.000 HOUR $360.00 $14,400.00
A0370 62301-0000 GENERAL LABOR Hamilton Construction Co. 40.000 $180.00 $7,200.00
Granite Construction Company 40.000 $175.00 $7,000.00
Tutka, LLC 40.000 $110.00 $4,400.00 Engineer's Estimate 40.000 HOUR $170.00 $6,800.00
A0380 62406-0100 PLACING
CONSERVED
TOPSOIL, 2-INCH
DEPTH
Tutka, LLC 0.700 $32,000.00 $22,400.00 Granite Construction Company 0.700 $15,000.00 $10,500.00
Hamilton Construction Co. 0.700 $4,550.00 $3,185.00
Engineer's Estimate 0.700 ACRE $20,000.00 $14,000.00
A0390 62515-1000 MULCHING, DRY
METHOD (Placing conserved mulch)
Tutka, LLC 1.300 $17,000.00 $22,100.00 Granite Construction Company 1.300 $10,000.00 $13,000.00
A0390 62515-1000 MULCHING, DRY
METHOD (Placing conserved mulch)
Hamilton Construction Co. 1.300 $4,900.00 $6,370.00
Engineer's Estimate 1.300 ACRE $10,000.00 $13,000.00 A0400 63302-0000 SIGN SYSTEM Hamilton
Construction Co. 17.000 $400.00 $6,800.00
Tutka, LLC 17.000 $320.00 $5,440.00 Granite Construction Company 17.000 $300.00 $5,100.00
Engineer's Estimate 17.000 SQFT $300.00 $5,100.00
A0410 63308-2000 OBJECT MARKER,
TYPE 2
Hamilton Construction Co. 4.000 $500.00 $2,000.00
Tutka, LLC 4.000 $350.00 $1,400.00 Granite Construction Company 4.000 $150.00 $600.00
Engineer's Estimate 4.000 EACH $250.00 $1,000.00
A0420 63502-0600 TEMPORARY
TRAFFIC CONTROL,
BARRICADE TYPE 3
Tutka, LLC 4.000 $800.00 $3,200.00 Hamilton Construction Co. 4.000 $500.00 $2,000.00
Granite Construction Company 4.000 $300.00 $1,200.00
Engineer's Estimate 4.000 EACH $380.00 $1,520.00
A0430 63502-0700 TEMPORARY
TRAFFIC CONTROL,
CONE
Hamilton Construction Co. 60.000 $100.00 $6,000.00
Tutka, LLC 60.000 $64.00 $3,840.00 Granite Construction Company 60.000 $50.00 $3,000.00
Engineer's Estimate 60.000 EACH $52.00 $3,120.00
A0440 63502-1600 TEMPORARY
TRAFFIC CONTROL,
WARNING LIGHT
TYPE B
Granite Construction Company 4.000 $100.00 $400.00
Hamilton Construction Co. 4.000 $100.00 $400.00
Tutka, LLC 4.000 $32.00 $128.00 Engineer's Estimate 4.000 EACH $500.00 $2,000.00
A0450 63504-1000 TEMPORARY
TRAFFIC CONTROL,
CONSTRUCTION
SIGN
Granite Construction Company 140.000 $50.00 $7,000.00
Hamilton Construction Co. 140.000 $40.00 $5,600.00
Tutka, LLC 140.000 $38.00 $5,320.00 Engineer's Estimate 140.000 SQFT $100.00 $14,000.00
A0460 63506-0500 TEMPORARY
TRAFFIC CONTROL,
FLAGGER
Tutka, LLC 850.000 $146.00 $124,100.00 Hamilton Construction Co. 850.000 $125.00 $106,250.00
Granite Construction Company 850.000 $100.00 $85,000.00
Engineer's Estimate 850.000 HOUR $140.00 $119,000.00
A0470 63704-0000 VEHICLE Hamilton Construction Co. 2.000 $57,500.00 $115,000.00
Tutka, LLC 2.000 $55,000.00 $110,000.00 Granite Construction Company 2.000 $50,000.00 $100,000.00
Engineer's Estimate 2.000 EACH $60,000.00 $120,000.00
A0480 63708-0000 CELLULAR PHONE
SERVICE
Tutka, LLC 18.000 $760.00 $13,680.00 Granite Construction Company 18.000 $500.00 $9,000.00
Hamilton Construction Co. 18.000 $75.00 $1,350.00
Engineer's Estimate 18.000 MO $5,000.00 $90,000.00
A0490 63713-0000 FIELD OFFICE
SERVICES
(INTERNET)
Tutka, LLC 18.000 $1,300.00 $23,400.00 Granite Construction Company 18.000 $500.00 $9,000.00
Hamilton Construction Co. 18.000 $75.00 $1,350.00
Engineer's Estimate 18.000 MO $5,000.00 $90,000.00
Project No. : AK PRA DENA 10(36) Project Name: Replace Ghiglione Bridge
Division: Western Federal Lands
Schedule: X Schedule Type: Option Lead Designer:
Solicitation No. : 69056725B000009 Opened at: Vancouver, WA Opened by: Angy Liljedahl
State: AK County: Denali Federal Land: Denali National Park Bid Open Date and Time: 11/25/2025
Contract Awarded to: Award Date:
Contractor Comment Bid Amount Responsive Granite Construction Company, 585 West Beach Street, Watsonville, CA, 95076
$3,554,500.00
Tutka, LLC, 2485 E Zak Circle, Suite A, Wasilla, AK, 99654
$3,033,400.00
Hamilton Construction Co., PO BOX 659, Springfield, OR, 97477
$1,651,225.00
Engineer's Estimate $2,996,000.00
I certify that this Bid Tabulation reflects the offers received for this solicitation
Signed:
Title:
Date:
Project No. : AK PRA DENA 10(36) Project Name: Replace Ghiglione Bridge Schedule: X Schedule Type: Option
Line Item Number
Pay Item Number Description Contractor Quantity Unit Unit Price Amount
X0020 15101-0000 MOBILIZATION Granite Construction Company $800,000.00
Tutka, LLC $370,000.00 Hamilton Construction Co. $71,250.00
Engineer's Estimate ALL LPSM LPSM $272,000.00
X0040 15301-0000 CONTRACTOR
QUALITY CONTROL Tutka, LLC $32,000.00
Contracting Officer
11/26/2025
X0040 15301-0000 CONTRACTOR
QUALITY CONTROL
Granite Construction Company $10,000.00
Hamilton Construction Co. $500.00
Engineer's Estimate ALL LPSM LPSM $67,000.00
X0060 15401-0000 CONTRACTOR
TESTING
Tutka, LLC $165,000.00 Granite Construction Company $50,000.00
Hamilton Construction Co. $45,000.00
Engineer's Estimate ALL LPSM LPSM $33,000.00
X0080 31402-0000 STOCKPILED
AGGREGATE
(SELECT BORROW)
Granite Construction Company 10,100.000 $25.00 $252,500.00
Tutka, LLC 10,100.000 $20.00 $202,000.00 Hamilton Construction Co. 10,100.000 $16.75 $169,175.00
Engineer's Estimate 10,100.000 CUYD $40.00 $404,000.00
X0100 31402-0000 STOCKPILED
AGGREGATE
(SURFACE COURSE
WITH BENTONITE,
TOKLAT SCRAPE)
Granite Construction Company 22,200.000 $110.00 $2,442,000.00
Tutka, LLC 22,200.000 $102.00 $2,264,400.00 Hamilton Construction Co. 22,200.000 $61.50 $1,365,300.00
Engineer's Estimate 22,200.000 CUYD $100.00 $2,220,000.00