This document is a Questions and Answers (Q&A) file for the AK PRA DENA 10(36) project to Replace Ghiglione Bridge. The file contains 17 technical questions from potential contractors, with responses from the project team dated 11/7/25. Key questions address project-specific details such as bridge construction requirements, access road limitations, vehicle delivery dates, work start dates, and environmental constraints. Many responses direct bidders to "Bid according to the plans" or indicate that specific questions will be addressed via future amendments.

Significant technical points include clarification on sole plate fabrication requirements, restrictions on clearing and work dates (no onsite work before 7/01/26), limitations on vehicle traffic between May 01 and September 21, and potential challenges with access roads and construction limits near wilderness boundaries. The project involves complex logistical considerations, including winter shutdowns, migratory bird protections, and specific equipment and access constraints in a potentially challenging terrain. The contracting agency will provide further details through planned amendments to address several of the contractors' specific inquiries.

View the file

Other files for this federal contract opportunity

Other files attached to AK PRA DENA 10(36), Replace Ghiglione Bridge, newest first.
File Type Posted
BidTabulation_AK PRA DENA 10(36).pdf PDF
BidSum_AK PRA DENA 10(36).pdf PDF
QA_11_24_2025.pdf PDF
QA_11_21_2025.pdf PDF
QA_11_18_2025.pdf PDF
QA_11_13_2025.pdf PDF
Amendment A002.pdf PDF
QA_11_05_2025.pdf PDF
Amendment A001.pdf PDF
9830-011P - Ghiglione Bridge As-Built Plans.pdf PDF
Physical Data_AK PRA DENA 10.zip ZIP file
FLH Bridge oversized or overload vehicle permit request form August 2023.pdf PDF
Ghiglione_ControlSheet.xlsx XLSX spreadsheet
Geotech Report No 11-19 Ghiglione Final Foundation Report.pdf PDF
DENA01036_XS.pdf PDF
BHIM Nov 2022.pdf PDF
Hydraulic Design Narrative for Construction.pdf PDF
Ghiglione_EPA_Compiled SWPPP_Final.pdf PDF
AK PRA DENA 10(36) - Physical Data - GOV Furnished Pipe Pile Info.pdf PDF
DENA01036_SUP.pdf PDF
DENA01036_VA.pdf PDF
DENA01036_HA.pdf PDF
Toklat Pit_Scrape Material Photos.pdf PDF
9830-011P - Ghiglione Bridge Inspection 2024.pdf PDF
WEF Nov. 2022.pdf PDF
DENA01036_EW.pdf PDF
IFB 69056725B000009.pdf PDF
dena01036_plans.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AK PRA DENA 10(36),

Replace Ghiglione Bridge

# General Technical Question Answer Date

1 X

Bridge drawing 7 of 29 (RG3147-G) requires that the sole plate be vulcanized to the elastomeric bearing pad. Section 555 – Steel Structures of the Special Contract Requirements requires structural steel fabrication to be completed by an IBR certified facility. Does this requirement pertain to the sole plates?

That requirement would not apply to the bearing sole plates.

11/4/25

2 X

What is the location that the owner furnished piling will need to be picked up from and do we need to figure on taking equipment to load the pile?

Your question will be addressed via an amendment.

11/7/25

3 X Do you have a gradation report for the scrape material in Toklat?

No gradation report is available for scrape material

11/7/25

4 X Does the NPS have any silty material that we can mix with the scrape to achieve the dirty specifications for the surfacing course?

Bid according to the plans 11/7/25

5 X

Is the July 1, 2026 start date based on when the Polychrome bridge will be completed, and could we start earlier if other lodging arrangements are made and we do not need to access Toklat?

Bid according to the plans 11/7/25

6 X Is it acceptable to install a temporary culvert over the creek for temporary crane/drilling access?

This is not currently permitted 11/7/25

7 X Can the access road be constructed wider than shown due to crane width being 24' wide?

Access road could be approved for widening as long as there were no additional impacts to the creek.

11/7/25

Check General or Technical

8 X

Section 637.03 (Page E-29) states to deliver vehicles to park headquarters on Notice to Proceed Date. Also states vehicles will not be operated during winter shutdowns. NTP date listed elsewhere as 1/05/26. No work is allowed on the project until 7/01/26. Why would vehicles be needed on 1/05/26 if they are just going to be parked at the headquarters until July? Please consider revising delivery dates on vehicles to some limited time before start of work date

Your question will be addressed via an amendment.

11/7/25

9 X

Section 107.10(e)(3) (Page E-24) does not allow clearing to take place between May 1 and July

31. Section 108.01(a)(1) states no onsite work before July 01, 2026. Clearing needs to be performed prior to any other work onsite. This essentially pushes start of work date back to August 01. With an August 01, 2026 start date, our schedule shows we cannot complete work prior to September 30,2027 while following the other work constraints on the job (winter shutdowns, snow removal dates, etc). Will owner allow clearing to take place subject to pre-inspectin for migratory birds? Who will pay the cost of this pre-inspection? Will owner allow clearing to take place prior to the May 01 date? If neither of these is allowable, we would request that the contract completion date be extended to allow for completion of work in spring 2028.

Your question will be addressed via an amendment.

10 X

Plan sheet D.2 shows 18’ wide access road on east side of creek to access Piers 1 and 2. Will similar access road be allowed on west side of creek to access Pier 3?

Bid According to plans. 11/7/25

11 X

Plan sheet D.2 shows Construction Limits relative to access to Piers 1/2/3. Using original ground contours, an access road to Pier 2 and Pier 3 that stays within the Construction Limits would be too steep for any equipment to use (well over 30% gradient). Can Construction Limits be extended to the Wilderness Boundary for the sole purpose of providing adequate access to Piers 2 and 3?

Bid according to plans. 11/7/25

12 X

With the potential for very limited access underneath the bridge for stripping operations, as well as the potential cost and time savings, will stay in place deck forms be allowed on this project?

Your question will be addressed via an amendment.

11/7/25

13 X

Section 108.01(c) (page E-29) Overweight vehicle restriction references that between May 01 and Sept 21, overweight vehicle traffic is not allowed between the hours of 6am and 10pm.

This section does not define what constitutes an overweight vehicle. Please clarify.

See SCR section 104.05 11/7/25

14 X

Bid schedule contains 850 Flagger Hours. I’m not finding any reference in the ITB that clarifies when we are allowed (either dates or times) to restrict traffic under flagger control. Please clarify.

Bid according to the plans, See SCR section’s 156 and 108.

15 X

Addendum #1 changes this date to 30 days prior to preconstruction conference. However, with NTP date of January 05 and start of work no earlier than July 01, it is likely the preconstruction conference happens far earlier than 30 days prior to July 01. Please review, consider changing vehicle requirements to “X” days in advance of start of onsite work

Your question will be addressed via an amendment.

11/7/25

16 X

I wanted to get clarification on the size of the wedge plates on drawing RG3147-L (bridge drawing 12 of 29). They are shown as tapering from 3.5” to 2.5” and are 15” long. There is a callout for “2” plate”. Is that the width?

Yes this is the width. 11/7/25

17 X

Could you give us the haul route that you anticipate for getting the scrape material from the mining area on the far side of the river over to the stockpile areas? If a river crossing is required, what are the environmental stipulations that are applicable?

See SCR 105.02(a)(1)(a), contractor to Submit planned Haul Route, If a river crossing is required, adhere to applicable permits.