FF&E_Phase_II_Schedule.pdf
PDF 133 KB Posted
- Solicitation number
- 2026-059
- Issued by
- Los Angeles County, California
About this file
This is a Furniture, Fixtures, and Equipment (FF&E) Phase II Schedule document related to a prequalification bid for custom furniture procurement at Mt. San Antonio College in California. The project involves furnishing a new four-story Technology and Health Building, a 273,000-square-foot facility that will consolidate 10 departments and 26 academic programs currently distributed across six separate locations, including modular buildings and existing technology facilities. The building will serve as the largest instructional facility of any community college in California. The furniture procurement is being conducted in phases, with this prequalification stage designed to evaluate contractors' qualifications, experience, licensing, and capability to perform the scope of work before they are invited to participate in the subsequent main project solicitation. Contractors must submit prequalification packets by the established deadline to be considered for approval and advancement to the formal bidding process.
The furniture design philosophy emphasizes creating a dynamic, forward-thinking educational environment with strategically selected and placed furnishings that showcase the identity of each program through visually distinct, branded spaces. The design prioritizes flexibility and student engagement, reflecting the character and purpose of the academic disciplines served. All project-related attachments, including drawings, specifications, and supporting documents provided during this prequalification phase, are for reference and informational purposes only and should not be interpreted as final bid documents or authorization to perform work. Only contractors that successfully meet the prequalification requirements and receive formal approval from Mt. San Antonio College will be invited to participate in the subsequent solicitation for the main FF&E procurement project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Prequalification_for_Purchase_of_Custom_Furniture_(FF&E)_Bid.pdf | ||
| Prequalification_Application_(rev_06-2026).pdf | ||
| Written_Specifications.pdf | ||
| CAD_x-1_arch_231128-hh.dwg | DWG drawing | |
| CAD_x-2_arch_231128-HH.dwg | DWG drawing | |
| CF1_SCE_Reception_Spec.pdf | ||
| CAD_1_Furn_Bid_2.dwg | DWG drawing | |
| CT1A_CT1B_Custom_Work_Table.pdf | ||
| CF2_Division_Reception_Spec.pdf | ||
| WT3_Work_Table.pdf | ||
| RB1_Residential_Bed.pdf | ||
| WT4A_WT4B__Work_Table.pdf | ||
| CAD_4_Furn_Bid_2.dwg | DWG drawing | |
| WT1A_WT1B_Work_Table.pdf | ||
| CAD_2_Furn_Bid_2.dwg | DWG drawing | |
| Furniture_Plan_Color_Coded.pdf | ||
| WT2_Work_Table.pdf | ||
| CAD_x-4_arch_231128_HH.dwg | DWG drawing | |
| Furniture_Log.pdf | ||
| MSR1_Sheet_Rack.pdf | ||
| Custom_Furniture_-_Standard.zip | ZIP file | |
| 00430_Payment_Bond_Revised_Sample.pdf | ||
| 00420_Performance_Bond_Revised_sample.pdf | ||
| Mt._SAC_-_Template_Field_Services_Contract.pdf |
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID 2026 – 059
CUSTOM FURNITURE PHASE II SCHEDULE
TECH & HEALTH BUILDING
Milestone Deliverables Duration Completion Date
1st Advertisement 4/27 – 5/1 April 24, 2026
2nd Advertisement 5/4 – 5/8 May 1, 2026
Pre-Proposal Zoom Meeting Friday, May 8 @ 9:00 a.m.
RFI’s Due By 2:00 p.m. 5/15 May 15, 2026
Bid Due Date At 2:00 p.m. 5/29 May 29, 2026
Submit for July Board 6/5 June 5, 2026
Board Meeting 7/8 July 8, 2026
Issuance of P.O. Mid - August August 14, 2026
Site Field Verification/Coordination 8/24 – 9/25 Date/Time - TBD
Lead Time August - November 14 Weeks
Commencement of Installation 12/4 – 12/18 2 Weeks
Punch Walk 12/18 Time - TBD
Project Closed Out 1/15/27 Date/Time - TBD