FARM II Attachment L-6 Relevancy Matrix.xlsx

XLSX spreadsheet 40 KB Posted

Attached to
Facilities Acquisitions for Restoration and Modernization (FARM II) Federal contract opportunity
Solicitation number
FA9101-21-R-0001
Issued by
Department of the Air Force Materiel Command Test Center

About this file

This document includes a request for proposal for the Facilities Acquisitions for Restoration and Modernization II contract along with details about the related federal contract opportunity. The Air Force Materiel Command Test Center is soliciting proposals for an indefinite-delivery indefinite-quantity multiple award contract for mechanical, electrical, and instrumentation, data, and control systems design-build, construction, and two-phase design/build services at the Arnold Engineering Development Complex in Tennessee and its geographically separated units. The total estimated value of the contract(s) is $300 million over five years with a minimum guarantee of $1,000. The government intends to award a minimum of two and target of four contracts. Proposals are due by July 13, 2021. Work will primarily be performed at Arnold Air Force Base in Tennessee along with geographically separated units located in California, Maryland, Florida, New Mexico, and Ohio. Major work includes mechanical, electrical, instrumentation, data and control systems, and design/build projects to support research, development, test, and evaluation missions.

View the file

Other files for this federal contract opportunity

Other files attached to Facilities Acquisitions for Restoration and Modernization (FARM II), newest first.
File Type Posted
FARM II Attachment 7 Seed Project SOW_dwgs_29July2021.pdf PDF
FA9101-21-R-0001 SF 30 Amend 0004.pdf PDF
FARM II Attachment 1 Statement of Work_28July2021.pdf PDF
FARM II Attachment 7 Seed Project SOW_dwgs_28July2021.pdf PDF
FA9101-21-R-0001 SF 30 Amend 0003.pdf PDF
FA9101-21-R-0001 SF 30 Amend 0002.pdf PDF
RU632035.02_B_MultiSheet.pdf PDF
FARM ll FA9101-21-R-0001 RFP Q and A_20Jul21.pdf PDF
FA9101-21-R-0001 SF 30 Amend 0001.pdf PDF
FARM II Site Visit Sign-In Sheet.pdf PDF
FARM ll FA9101-21-R-0001 RFP Q and A_24Jun21.pdf PDF
FARM II Attachment 1 Statement of Work.pdf PDF
FARM II Attachment 7 Seed Project SOW_dwgs.pdf PDF
FARM II Atch L-2 Past and Present Performance Questionnaire.pdf PDF
FARM II Attachment L-7 Pricing Sheet.xlsx XLSX spreadsheet
FARM ll FA9101-21-R-0001 RFP Q and A.xlsx XLSX spreadsheet
FARM II RFP Cover Letter .pdf PDF
FARM ll Attachment 3 Wage Determination.pdf PDF
FARM II Atch L-3 PPQ Cover Letter.pdf PDF
FARM II Attachment L-5 Subcontractor Consent Letter.pdf PDF
FARM II Attachment 9 Section M.pdf PDF
FARM II Attachment L-1 PPI Tool.pdf PDF
Attachment L-8 Agenda for Seed Project Site Visit.pdf PDF
FA9101-21-R-0001 SF 1442.pdf PDF
FARM ll Attachment 2 Scheduled GFP.pdf PDF
FARM Il Attachment 8 Section L.pdf PDF
FARM II Attachment L-4 Client Authorization Letter.pdf PDF
PPI tool.zip ZIP file
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Prime

Name of Prime ContractorReference 1Reference 2Reference 3Reference 4Reference 5
Management Subfactor
M-2.2.1.1.1.Teaming and Subcontractor Management
M-2.2.1.1.2.Quality Management System
M-2.2.1.1.3.Qualified Personnel
Technical Capabilities (SOW 1.2)
Mechanical
M1Air duct, expansion joints, and control/process valves (≥ 36” Ø and 150 psig)
M2High pressure duct/piping & valves (typ. 4" to 8"Ø, ≥ 4000 psig)
M3Large pressure vessels (≥ 2000 psig; ≥ 10K gallons)
M4Desiccant bed air dryers (≤ 300 psia & ≥ 200 lb/s)
M5Turning vanes for large air ducting (up to 50-ft Ø; 0.5-160 psia)
M6Cooling water/raw water pumps (300-50,000 gpm; 30-4,000 hp), filters/strainers, control/process valves,and distribution lines (typ. 6” to 90” Ø)
M7Hydraulic systems with high flow and pressure requirements (20-200 gpm (typ. 2 pumps @ 100 gpm ea) and 2500 psig)
M8Large steam distribution systems (60 kpph boilers, and piping up to 14" Ø)
M9Chillers and refrigeration equipment (300-5000 refrigeration tons)
M10Large heat exchangers: air to air; water to air; shell and tube, etc. (∆T up to 325 °F)
Electrical
E1Interior & exterior lighting for industrial buildings
E2Medium voltage gas insulated switchgear (≤ 13.8kV)
E3Unit substations (typical 6.9/2.4kV)
E4Motor Control Centers (≤ 600V)
E5Transformers (≤ 161/13.8kV)
E6Uninterruptable Power Supply (UPS)
E7Ducting/vaults/ cables (13.8kV & 6.9kV)
E8Motor exciters
E9Oil circuit breakers (typical 3000 amp & 550kV BIL)
E10Power panels/conduit/wiring (≤ 480V)
E11Variable frequency drives for motors (≥ 600V & ≤ 69kV)
ID&C
I1PLC-based industrial control systems
I2High Speed (< 10ms Loop Time) facility control systems
I3Controls software development and modification
I4Secure control systems
I5Data logging system design and integration
I6Control systems instrumentation design and integration

&"Times New Roman,Bold"ATTACHMENT L-6 RELEVANCY MATRIX &"Times New Roman,Regular"FARM II

FA9101-21-R-0001

Attachment 8

Partners

Name of Partner (Subcontractor/Joint Venture)Reference 1Reference 2Reference 3
Management Subfactor
M-2.2.1.1.1.Teaming and Subcontractor Management
M-2.2.1.1.2.Quality Management System
M-2.2.1.1.3.Qualified Personnel
Technical Capabilities (SOW 1.2)
Mechanical
M1Air duct, expansion joints, and control/process valves (≥ 36” Ø and 150 psig)
M2High pressure duct/piping & valves (typ. 4" to 8"Ø, ≥ 4000 psig)
M3Large pressure vessels (≥ 2000 psig; ≥ 10K gallons)
M4Desiccant bed air dryers (≤ 300 psia & ≥ 200 lb/s)
M5Turning vanes for large air ducting (up to 50-ft Ø; 0.5-160 psia)
M6Cooling water/raw water pumps (300-50,000 gpm; 30-4,000 hp), filters/strainers, control/process valves,and distribution lines (typ. 6” to 90” Ø)
M7Hydraulic systems with high flow and pressure requirements (20-200 gpm (typ. 2 pumps @ 100 gpm ea) and 2500 psig)
M8Large steam distribution systems (60 kpph boilers, and piping up to 14" Ø)
M9Chillers and refrigeration equipment (300-5000 refrigeration tons)
M10Large heat exchangers: air to air; water to air; shell and tube, etc. (∆T up to 325 °F)
Electrical
E1Interior & exterior lighting for industrial buildings
E2Medium voltage gas insulated switchgear (≤ 13.8kV)
E3Unit substations (typical 6.9/2.4kV)
E4Motor Control Centers (≤ 600V)
E5Transformers (≤ 161/13.8kV)
E6Uninterruptable Power Supply (UPS)
E7Ducting/vaults/ cables (13.8kV & 6.9kV)
E8Motor exciters
E9Oil circuit breakers (typical 3000 amp & 550kV BIL)
E10Power panels/conduit/wiring (≤ 480V)
E11Variable frequency drives for motors (≥ 600V & ≤ 69kV)
ID&C
I1PLC-based industrial control systems
I2High Speed (< 10ms Loop Time) facility control systems
I3Controls software development and modification
I4Secure control systems
I5Data logging system design and integration
I6Control systems instrumentation design and integration

&"Times New Roman,Bold"ATTACHMENT L-6 RELEVANCY MATRIX &"Times New Roman,Regular"FARM II