This is a blank construction cost estimate breakdown form template for federal contractors responding to the solicitation for backup generator installation at Kirtland Air Force Base. The form provides a standardized format for contractors to submit detailed cost estimates organized by labor, materials, equipment, and other direct costs across multiple line items and work categories.
The template is structured with separate breakdown sheets for General Requirements, F20 Selective Building Demolition, and G20/G40 Site Improvements and Site Electrical work. Contractors must itemize all direct costs in sufficient detail, including material unit costs and quantities, labor hours and rates, special equipment costs, and other direct costs. The form requires line-item totals that roll up to grand totals for material and labor costs, other direct costs, design costs, general conditions, overhead, profit, and final contract price. Supporting documentation must accompany the proposal, including verification of all cost or pricing data, books, records, and computations used in developing the estimate. The template includes detailed cost line items for specific construction components such as demolition work, concrete installation, electrical conduit and wiring, grounding systems, a 25-50 kW diesel generator set, automatic transfer switches, circuit breakers, and split ductless cooling/heating systems. The document references ASPR (Armed Services Procurement Regulations) requirements for cost or pricing data certification and indicates that this cost estimate breakdown is mandatory for contract negotiation and award.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Summary Sheet
| Controlled Unclassified Information (CUI) | |
| INSTRUCTIONS FOR COMPLETING CONSTRUCTION COST ESTIMATE BREAKDOWN FORM |
| Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to | |||||
| permit itemizing of all direct costs. | |||||
| Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples : square yards - SY, cubic yards - CY, square | |||||
| feet - SF, linear feet - LF, board feet - BF, each - EA, pound -LB). | |||||
| Col 3 Quantity. Contractor's estimate of quantity required in terms of unit of measure (column 2). Items and units of measure will be | |||||
| furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will | |||||
| be issued. Otherwise, the contractor is responsible for determining quantity estimates. | |||||
| Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1. | |||||
| Col 6, 7 and 8 Labor Costs. Enter in Col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. | |||||
| Enter in Col 7 the average rate per manhour (manday) and in Col 8 the total labor cost. | |||||
| Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1) which are special to the contract | |||||
| and of significant dollar value. | |||||
| Col 10 Line Total. Self-explanatory. | |||||
| NOTE: In addition to the other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last | |||||
| page as follows. | |||||
| Install Backup Generator, B1043 MHMV 080079 | |||||
| Controlled Unclassified Information | |||||
| MIN CONS | TOTAL | ||||
| TOTAL MATERIAL AND LABOR COSTS | $ |
TOTAL OTHER DIRECT COSTS $
DESIGN $
DESIGN COSTS $
TOTAL DIRECT COSTS $
GENERAL CONDITIONS $
OVERHEAD $
PROFIT $
NMGRT $
BOND $
TOTAL PRICE $
DATE : FIRM NAME :
TITLE : BY :
INSTRUCTIONS TO OFFERORS
| 1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and |
| estimated costs (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from |
| this proposal the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data |
| (see ASPR 3-807.3(e) and 3-807.4) |
| 2. In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit with this |
| form any additional data, supporting schedules, or substantiation which are reasonably required for the conduct of an appropriate review and |
| analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clear understanding of |
| a. The existing, verifiable data. |
| b. The judgmental factors applied in projecting from known data to the estimate, and |
| c. The contingencies used by the offeror in his proposed price. |
| In short, the offeror' s estimating process itself needs to be disclosed. |
| 3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate), |
| and made available to the contracting officer or his authorized representative upon request. |
| 4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the |
| purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate |
| evaluation of such cost or pricing data, along with the computations and projections used herein. This right may be exercised in connection |
| with any negotiations prior to contract award. |
(Reverse of Construction Cost Estimate Breakdown Form)
&K3D3D3DControlled Unclassified Information (CUI)
Controlled Unclassified Information (CUI)
Recap
| Controlled Unclassified Information (CUI) | |||||
| CONSTRUCTION COST ESTIMATE BREAKDOWN | SHEET NO. | OF | |||
| CONTRACTOR | ADDRESS |
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | ||||||||||
| Install Backup Generator, B1043 MHMV 080079 | |||||||||||
| PURCHASE REQUEST NUMBER | MHMV 080079 | WORK LOCATION : | Kirtland AFB | ||||||||
| UNIT OF | MATERIAL COST | LABOR COST | $ | $ | |||||||
| LINE | ITEM | MEASURE | QUANTITY | $ | $ | $ | $ | OTHER | LINE | ||
| NO | RECAP | UNIT | TOTAL | MANHOURS | AVERAGE | TOTAL | DIRECT | TOTAL | |||
| RATE* | UNIT COSTS** | ||||||||||
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | ||
| MINOR CONSTRUCTION | |||||||||||
| 1 | General Requirements | ERROR:#DIV/0! | |||||||||
| 2 | F20 Selective Building Demolition | ERROR:#DIV/0! | |||||||||
| 3 | G20 Site Improvements G40 Site Electrical | ERROR:#DIV/0! | |||||||||
| Subtotal |
| TOTAL | ERROR:#DIV/0! | |
| (Construction Cost Estimate Breakdown Form ) |
&K3D3D3DControlled Unclassified Information (CUI)
Controlled Unclassified Information (CUI)
General Requirements
| Controlled Unclassified Information (CUI) | |||||
| CONSTRUCTION COST ESTIMATE BREAKDOWN | SHEET NO: General Requirements | OF | |||
| CONTRACTOR | ADDRESS |
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| Install Backup Generator, B1043 MHMV 080079 | ||||||||||
| PURCHASE REQUEST NUMBER | MHMV 080079 | WORK LOCATION : | Kirtland AFB | |||||||
| UNIT OF | MATERIAL COST | LABOR COST | $ | $ | ||||||
| LINE | ITEM | MEASURE | QUANTITY | $ | $ | $ | $ | OTHER | LINE | |
| NO | GENERAL REQ | UNIT | TOTAL | MANHOURS | AVERAGE | TOTAL | DIRECT | TOTAL | ||
| RATE* | UNIT COSTS** | |||||||||
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |
| MINOR CONSTRUCTION | ||||||||||
| 1 | Project Manager | |||||||||
| 2 | Field Superintendent | |||||||||
| 3 | Mob/Demob | |||||||||
| 4 | Field Verification | |||||||||
| 5 | Submittals | |||||||||
| 6 | As-Built Drawings | |||||||||
| 7 | Testing | |||||||||
| Subtotal |
(Construction Cost Estimate Breakdown Form )
&K3D3D3DControlled Unclassified Information (CUI)
Controlled Unclassified Information (CUI)
F20
| Controlled Unclassified Information (CUI) | |||||
| CONSTRUCTION COST ESTIMATE BREAKDOWN | SHEET NO:F20 | OF | |||
| CONTRACTOR | ADDRESS |
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| Install Backup Generator, B1043 MHMV 080079 | ||||||||||
| PURCHASE REQUEST NUMBER | MHMV 080079 | WORK LOCATION : | Kirtland AFB | |||||||
| UNIT OF | MATERIAL COST | LABOR COST | $ | $ | ||||||
| LINE | ITEM | MEASURE | QUANTITY | $ | $ | $ | $ | OTHER | LINE | |
| NO | F 20 | UNIT | TOTAL | MANHOURS | AVERAGE | TOTAL | DIRECT | TOTAL | ||
| RATE* | UNIT COSTS** | |||||||||
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |
| MINOR CONSTRUCTION | ||||||||||
| 1 | Demo Manual Transfer , flexible conduit and fittings, | EA | ||||||||
| 2 | Disconnect A/C from panel Remove conductors. | EA | ||||||||
| 3 | Building footings and foundations demolition, add for disposal, up to 5 miles, excludes disposal costs and dump fees | CY | ||||||||
| 4 | Building demolition, small buildings or single buildings, steel, includes 20 mile haul, excludes salvage, foundation demolition or dump fees | CF | ||||||||
| 5 | Minor site demolition, concrete, mesh reinforced, 6" thick, remove, excludes hauling | SY | ||||||||
| 6 | Air conditioner, split unit air conditioner, package unit, 3 ton, selective demolition | Ea. | ||||||||
| 7 | Air conditioner, split unit air conditioner, 3 ton, selective demolition | Ea. | ||||||||
| SubTotal |
| TOTAL | |
| (Construction Cost Estimate Breakdown Form ) |
Estimating and Project Management Teams should use scope of work, construction documents, best practices, and industry standards to complete bids.
&K3D3D3DControlled Unclassified Information (CUI)
Controlled Unclassified Information (CUI)
G20 40
| Controlled Unclassified Information (CUI) | |||||
| CONSTRUCTION COST ESTIMATE BREAKDOWN | SHEET : G20 40 | OF | |||
| CONTRACTOR | ADDRESS |
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| Install Backup Generator, B1043 MHMV 080079 | ||||||||||
| PURCHASE REQUEST NUMBER | MHMV 080079 | WORK LOCATION : | Kirtland AFB | |||||||
| UNIT OF | MATERIAL COST | LABOR COST | $ | $ | ||||||
| LINE | ITEM | MEASURE | QUANTITY | $ | $ | $ | $ | OTHER | LINE | |
| NO | G20 Site Improvements | UNIT | TOTAL | MANHOURS | AVERAGE | TOTAL | DIRECT | TOTAL | ||
| G40 Site Electrical | RATE* | UNIT COSTS** | ||||||||
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |
| MINOR CONSTRUCTION | ||||||||||
| 1 | Slab on grade, 6" thick, includes forms(4 uses), rebar, concrete placing and finishing | SF | ||||||||
| 2 | Structural concrete, thickened edge for slab on grade,reinforced, includes forms(4 uses), rebar, concrete placing and finishing | LF | ||||||||
| 3 | Security vehicle barriers, pipe bollards, steel, concrete filled/painted, 8" diam. | EA | ||||||||
| 4 | Structural concrete, in place, column, round, up to 1% reinforcing by area, 20" diameter, includes forms(4 uses), Grade 60 rebar, concrete (Portland cement Type I), placing and finishing | CY | ||||||||
| 5 | Medium-cable single cable, copper, XLP shielding, | MLF | ||||||||
| 6 | Generator set, diesel, 3 phase 4 wire, 277/480 V,25 kW, incl battery, charger, muffler, & day tank, excl conduit, wiring, & concrete | EA | ||||||||
| 7 | Automatic transfer switches, enclosed, 4 pole, 480 V, 150 A Bypass/Iso. SW | EA | ||||||||
| 8 | Wire, copper, stranded, 600 volt, 1/0, type THWN-THHN, normal installation conditions in wireway, conduit, cable tray | CLF | ||||||||
| 9 | Rigid galvanized steel conduit, 1-1/2" diameter, to 10' high, includes 11 couplings per 100' | LF | ||||||||
| 10 | Hole drilling, concrete wall, 8" thick, 1-1/2" pipe size, to 10' high | EA | ||||||||
| 11 | Rigid galvanized steel conduit, field bends, 45 Deg. to 90 Deg., 1-1/2" diameter | EA | ||||||||
| 12 | Wire, copper, stranded, 600 volt, #12, type THW, normal installation conditions in wireway, conduit, cable tray | CLF | ||||||||
| 13 | Rigid galvanized steel conduit, 3/4" diameter, to 10' H, incl 2 terminations, 2 elbows, 11 beam clamps, and 11 couplings per 100 LF | LF | ||||||||
| 14 | Insulated ground wire, copper, stranded, 1/0 | CLF | ||||||||
| 15 | Grounding rod, copper clad, 10' long, 3/4" diameter | EA | ||||||||
| 16 | Grounding coupling, bronze, 3/4" diameter | EA | ||||||||
| 17 | Grounding drive studs, 3/4" diameter | EA | ||||||||
| 18 | Ground clamp, bronze, 3/4" diameter | EA | ||||||||
| 19 | Wire, copper, stranded, 600 volt, #8, type THW, normal installation conditions in wireway, conduit, cable tray | CLF | ||||||||
| 20 | Rigid galvanized steel conduit, 3/4" diameter, to 10' H, incl 2 terminations, 2 elbows, 11 beam clamps, and 11 couplings per 100 LF | LF | ||||||||
| 21 | Rigid galvanized steel conduit, field bends, 45 Deg. to 90 Deg., 3/4" diameter | EA | ||||||||
| 22 | Circuit breaker, 3 pole, 15 to 60 amp, type FA | EA | ||||||||
| 23 | Smart metering, in panel, three phase, 277/480 volt, 800 amp | Ea. | ||||||||
| 24 | Split ductless system, cooling / heating, wall mount, 1-1/2 ton cooling | Ea. | ||||||||
| 25 | Split ductless system, accessories for all split ductless systems, for tube / wiring kit, 50' kit | Ea. | ||||||||
| 26 | Split ductless system, accessories for all split ductless systems, for tube / wiring kit, 15' kit | Ea. | ||||||||
| Subtotal |
| TOTAL | |
| (Construction Cost Estimate Breakdown Form ) |
Estimating and Project Management Teams should use scope of work, construction documents, best practices, and industry standards to complete bids.
&K3D3D3DControlled Unclassified Information (CUI)
Controlled Unclassified Information (CUI)
639064093883749070
| Unit Cost Lines | ||||
| LineNumber | Line Source | SubContracted Ind. | Description | Unit |
| 260583100200 | U | Demo Manual Transfer , flexible conduit and fittings, | Ea. | |
| 260505201530 | U | Disconnect A/C from panel Remove conductors. | Ea. | |
| 024116174250 | Building footings and foundations demolition, add for disposal, up to 5 miles, excludes disposal costs and dump fees | C.Y. | ||
| 024116130500 | Building demolition, small buildings or single buildings, steel, includes 20 mile haul, excludes salvage, foundation demolition or dump fees | C.F. | ||
| 024113304220 | Minor site demolition, sidewalk, concrete, mesh reinforced, 6" thick, remove, excludes hauling | S.Y. | ||
| 033053404720 | Structural concrete, thickened edge for slab on grade (3500 psi), depth is added to and poured monolithically with slab, 12" wide x 12" deep, reinforced, includes forms(4 uses), Grade 60 rebar, concrete (Portland cement Type I), placing and finishing | L.F. | ||
| 347113172700 | U | Security vehicle barriers, pipe bollards, steel, concrete filled/painted, 8" diam. | Ea. | |
| 033053401300 | U | Structural concrete, in place, column, round, up to 1% reinforcing by area, 20" diameter, includes forms(4 uses), Grade 60 rebar, concrete (Portland cement Type I), placing and finishing | C.Y. | |
| 260513167000 | U | Medium-cable single cable, copper, XLP shielding, | M.L.F. | |
| 263623101500 | Automatic transfer switches, enclosed, 4 pole, 480 V, 150 A Bypass/Iso. SW | Ea. | ||
| 260519901600 | Wire, copper, stranded, 600 volt, 1/0, type THWN-THHN, normal installation conditions in wireway, conduit, cable tray | C.L.F. | ||
| 260533140580 | Rigid galvanized steel conduit, 1-1/2" diameter, to 10' high, includes 11 couplings per 100' | L.F. | ||
| 260533950150 | Hole drilling, concrete wall, 8" thick, 1-1/2" pipe size, to 10' high | Ea. | ||
| 260533131995 | Rigid galvanized steel conduit, field bends, 45 Deg. to 90 Deg., 1-1/2" diameter | Ea. | ||
| 260519900100 | Wire, copper, stranded, 600 volt, #12, type THW, normal installation conditions in wireway, conduit, cable tray | C.L.F. | ||
| 260533131770 | Rigid galvanized steel conduit, 3/4" diameter, to 10' H, incl 2 terminations, 2 elbows, 11 beam clamps, and 11 couplings per 100 LF | L.F. | ||
| 260526803790 | Insulated ground wire, copper, stranded, 1/0 | C.L.F. | ||
| 260526800100 | Grounding rod, copper clad, 10' long, 3/4" diameter | Ea. | ||
| 260526800170 | Grounding coupling, bronze, 3/4" diameter | Ea. | ||
| 260526800220 | Grounding drive studs, 3/4" diameter | Ea. | ||
| 260526800250 | Ground clamp, bronze, 3/4" diameter | Ea. | ||
| 260519900140 | Wire, copper, stranded, 600 volt, #8, type THW, normal installation conditions in wireway, conduit, cable tray | C.L.F. | ||
| 260533131770 | Rigid galvanized steel conduit, 3/4" diameter, to 10' H, incl 2 terminations, 2 elbows, 11 beam clamps, and 11 couplings per 100 LF | L.F. | ||
| 260533131992 | Rigid galvanized steel conduit, field bends, 45 Deg. to 90 Deg., 3/4" diameter | Ea. | ||
| 261316104800 | Circuit breaker, 3 pole, 15 to 60 amp, type FA | Ea. | ||
| 263213132010 | U | Generator set, diesel, 3 phase 4 wire, 277/480 V,25 kW, incl battery, charger, muffler, & day tank, excl conduit, wiring, & concrete | ||
| 260913301240 | Smart metering, in panel, three phase, 277/480 volt, 800 amp | Ea. | ||
| 230505100150 | Air conditioner, split unit air conditioner, package unit, 3 ton, selective demolition | Ea. | ||
| 230505100100 | Air conditioner, split unit air conditioner, 3 ton, selective demolition | Ea. | ||
| 238126105120 | Split ductless system, cooling / heating, wall mount, 1-1/2 ton cooling | Ea. | ||
| 238126107050 | Split ductless system, accessories for all split ductless systems, for tube / wiring kit, 50' kit | Ea. | ||
| 238126107030 | Split ductless system, accessories for all split ductless systems, for tube / wiring kit, 15' kit | Ea. | ||
| 238126107010 | Split ductless system, accessories for all split ductless systems, for ambient frost control, add | Ea. | ||
| Assembly Cost Lines | ||||
| LineNumber | Line Source | SubContracted Ind. | Description | Unit |
| A10301204520 | U | Slab on grade, 6" thick, light industrial, reinforced | S.F. |
638457567032311098
| Unit Cost Lines | |
| Description | Unit |
| Demo Manual Transfer , flexible conduit and fittings, | Ea. |
| Disconnect A/C from panel Remove conductors. | Ea. |
| Building footings and foundations demolition, add for disposal, up to 5 miles, excludes disposal costs and dump fees | C.Y. |
| Building demolition, small buildings or single buildings, steel, includes 20 mile haul, excludes salvage, foundation demolition or dump fees | C.F. |
| Minor site demolition, concrete, mesh reinforced, 6" thick, remove, excludes hauling | S.Y. |
| Structural concrete, thickened edge for slab on grade,reinforced, includes forms(4 uses), rebar, concrete placing and finishing | L.F. |
| Security vehicle barriers, pipe bollards, steel, concrete filled/painted, 8" diam. | Ea. |
| Structural concrete, in place, column, round, up to 1% reinforcing by area, 20" diameter, includes forms(4 uses), Grade 60 rebar, concrete (Portland cement Type I), placing and finishing | C.Y. |
| Medium-cable single cable, copper, XLP shielding, | M.L.F. |
| Generator set, diesel, 3 phase 4 wire, 277/480 V, 50 kW, incl battery, charger, muffler, & day tank, excl conduit, wiring, & concrete | Ea. |
| Automatic transfer switches, enclosed, 4 pole, 480 V, 150 A Bypass/Iso. SW | Ea. |
| Wire, copper, stranded, 600 volt, 1/0, type THWN-THHN, normal installation conditions in wireway, conduit, cable tray | C.L.F. |
| Rigid galvanized steel conduit, 1-1/2" diameter, to 10' high, includes 11 couplings per 100' | L.F. |
| Hole drilling, concrete wall, 8" thick, 1-1/2" pipe size, to 10' high | Ea. |
| Rigid galvanized steel conduit, field bends, 45 Deg. to 90 Deg., 1-1/2" diameter | Ea. |
| Wire, copper, stranded, 600 volt, #12, type THW, normal installation conditions in wireway, conduit, cable tray | C.L.F. |
| Rigid galvanized steel conduit, 3/4" diameter, to 10' H, incl 2 terminations, 2 elbows, 11 beam clamps, and 11 couplings per 100 LF | L.F. |
| Insulated ground wire, copper, stranded, 1/0 | C.L.F. |
| Grounding rod, copper clad, 10' long, 3/4" diameter | Ea. |
| Grounding coupling, bronze, 3/4" diameter | Ea. |
| Grounding drive studs, 3/4" diameter | Ea. |
| Ground clamp, bronze, 3/4" diameter | Ea. |
| Wire, copper, stranded, 600 volt, #8, type THW, normal installation conditions in wireway, conduit, cable tray | C.L.F. |
| Rigid galvanized steel conduit, 3/4" diameter, to 10' H, incl 2 terminations, 2 elbows, 11 beam clamps, and 11 couplings per 100 LF | L.F. |
| Rigid galvanized steel conduit, field bends, 45 Deg. to 90 Deg., 3/4" diameter | Ea. |
| Circuit breaker, 3 pole, 15 to 60 amp, type FA | Ea. |
| Assembly Cost Lines | |
| Description | Unit |
| Slab on grade, 6" thick, includes forms(4 uses), rebar, concrete placing and finishing | S.F. |
638724541007323614 Backup Generator 1043
| Data Release : Predictive Year 2026 Quarter 1 as of Year 2024 Quarter 4 | Unit Cost Lines | |||||||||||||||||||||||||||||
| Quantity | LineNumber | Line Source | SubContracted Ind. | Description | Crew | Daily Output | Labor Hours | Unit | Material | Labor | Equipment | Total | Ext. Mat. | Ext. Labor | Ext. Equip. | Ext. Total | Mat. O&P | Installation O&P | Labor O&P | Equip. O&P | Total O&P | Ext. Mat. O&P | Ext. Installation O&P | Ext. Labor O&P | Ext. Equip. O&P | Ext. Total O&P | Labor Type | Data Release | CCI Location | Notes |
| 1 | 260583100200 | U | Demo Manual Transfer , flexible conduit and fittings, | 0 | 0 | Ea. | $ 36.00 | $ 215.00 | $ - 0 | $ 251.00 | $ 36.00 | $ 215.00 | $ - 0 | $ 251.00 | $ 39.50 | $ 320.00 | $ - 0 | $ 359.50 | $ 39.50 | $ 320.00 | $ - 0 | $ 359.50 | USER | Year 2026 Quarter 1 | National Average | |||||
| 1 | 260505201530 | U | Disconnect A/C from panel Remove conductors. | 0 | 0 | Ea. | $ - 0 | $ 138.00 | $ - 0 | $ 138.00 | $ - 0 | $ 138.00 | $ - 0 | $ 138.00 | $ 20.00 | $ 255.00 | $ 50.00 | $ 325.00 | $ 20.00 | $ 255.00 | $ 50.00 | $ 325.00 | USER | Year 2026 Quarter 1 | National Average | |||||
| 1.5 | 024116174250 | Building footings and foundations demolition, add for disposal, up to 5 miles, excludes disposal costs and dump fees | B30 | 220 | 0.109 | C.Y. | $ - 0 | $ 6.90 | $ 16.05 | $ 22.95 | $ - 0 | $ 10.35 | $ 24.08 | $ 34.43 | $ - 0 | $ 10.25 | $ 17.65 | $ 27.90 | $ - 0 | $ 15.38 | $ 26.48 | $ 41.85 | STD | Year 2026 Quarter 1 | National Average | |||||
| 80 | 024116130500 | Building demolition, small buildings or single buildings, steel, includes 20 mile haul, excludes salvage, foundation demolition or dump fees | B3 | 14800 | 0.003 | C.F. | $ - 0 | $ 0.19 | $ 0.25 | $ 0.44 | $ - 0 | $ 15.20 | $ 20.00 | $ 35.20 | $ - 0 | $ 0.28 | $ 0.28 | $ 0.56 | $ - 0 | $ 22.40 | $ 22.40 | $ 44.80 | STD | Year 2026 Quarter 1 | National Average | |||||
| 54 | 024113304220 | Minor site demolition, sidewalk, concrete, mesh reinforced, 6" thick, remove, excludes hauling | B6 | 112 | 0.214 | S.Y. | $ - 0 | $ 12.20 | $ 2.69 | $ 14.89 | $ - 0 | $ 658.80 | $ 145.26 | $ 804.06 | $ - 0 | $ 18.05 | $ 2.96 | $ 21.01 | $ - 0 | $ 974.70 | $ 159.84 | $ 1,134.54 | STD | Year 2026 Quarter 1 | National Average | |||||
| 26 | 033053404720 | Structural concrete, thickened edge for slab on grade (3500 psi), depth is added to and poured monolithically with slab, 12" wide x 12" deep, reinforced, includes forms(4 uses), Grade 60 rebar, concrete (Portland cement Type I), placing and finishing | C14C | 1310 | 0.086 | L.F. | $ 20.50 | $ 5.30 | $ 0.03 | $ 25.83 | $ 533.00 | $ 137.80 | $ 0.78 | $ 671.58 | $ 22.50 | $ 7.85 | $ 0.03 | $ 30.38 | $ 585.00 | $ 204.10 | $ 0.78 | $ 789.88 | STD | Year 2026 Quarter 1 | National Average | |||||
| 5 | 347113172700 | U | Security vehicle barriers, pipe bollards, steel, concrete filled/painted, 8" diam. | B6 | 0 | 0 | Ea. | $ 875.00 | $ 129.00 | $ 29.50 | $ 1,033.50 | $ 4,375.00 | $ 645.00 | $ 147.50 | $ 5,167.50 | $ 1,000.00 | $ 192.00 | $ 32.50 | $ 1,224.50 | $ 5,000.00 | $ 960.00 | $ 162.50 | $ 6,122.50 | USER | Year 2026 Quarter 1 | National Average | ||||
| 1 | 033053401300 | U | Structural concrete, in place, column, round, up to 1% reinforcing by area, 20" diameter, includes forms(4 uses), Grade 60 rebar, concrete (Portland cement Type I), placing and finishing | C14A | 0 | 0 | C.Y. | $ 500.00 | $ 298.00 | $ 22.00 | $ 820.00 | $ 500.00 | $ 298.00 | $ 22.00 | $ 820.00 | $ 550.00 | $ 445.00 | $ 24.50 | $ 1,019.50 | $ 550.00 | $ 445.00 | $ 24.50 | $ 1,019.50 | USER | Year 2026 Quarter 1 | National Average | ||||
| 0.1 | 260513167000 | U | Medium-cable single cable, copper, XLP shielding, | R16 | 0 | 0 | M.L.F. | $ 7,075.00 | $ 4,150.00 | $ 315.00 | $ 11,540.00 | $ 707.50 | $ 415.00 | $ 31.50 | $ 1,154.00 | $ 7,800.00 | $ 6,175.00 | $ 350.00 | $ 14,325.00 | $ 780.00 | $ 617.50 | $ 35.00 | $ 1,432.50 | USER | Year 2026 Quarter 1 | National Average | ||||
| 1 | 263213132100 | Generator set, diesel, 3 phase 4 wire, 277/480 V, 50 kW, incl battery, charger, muffler, & day tank, excl conduit, wiring, & concrete | R3 | 0.42 | 47.619 | Ea. | $ 20,000.00 | $ 3,650.00 | $ 540.00 | $ 24,190.00 | $ 20,000.00 | $ 3,650.00 | $ 540.00 | $ 24,190.00 | $ 22,000.00 | $ 5,425.00 | $ 595.00 | $ 28,020.00 | $ 22,000.00 | $ 5,425.00 | $ 595.00 | $ 28,020.00 | STD | Year 2026 Quarter 1 | National Average | |||||
| 1 | 263623101500 | Automatic transfer switches, enclosed, 4 pole, 480 V, 150 A Bypass/Iso. SW | ELEC | 2.4 | 6.667 | Ea. | $ 28,900.00 | $ 515.00 | $ - 0 | $ 29,415.00 | $ 28,900.00 | $ 515.00 | $ - 0 | $ 29,415.00 | $ 31,800.00 | $ 765.00 | $ - 0 | $ 32,565.00 | $ 31,800.00 | $ 765.00 | $ - 0 | $ 32,565.00 | STD | Year 2026 Quarter 1 | National Average | |||||
| 5 | 260519901600 | Wire, copper, stranded, 600 volt, 1/0, type THWN-THHN, normal installation conditions in wireway, conduit, cable tray | ELEC | 6.6 | 2.424 | C.L.F. | $ 340.00 | $ 187.00 | $ - 0 | $ 527.00 | $ 1,700.00 | $ 935.00 | $ - 0 | $ 2,635.00 | $ 375.00 | $ 278.00 | $ - 0 | $ 653.00 | $ 1,875.00 | $ 1,390.00 | $ - 0 | $ 3,265.00 | STD | Year 2026 Quarter 1 | National Average | |||||
| 150 | 260533140580 | Rigid galvanized steel conduit, 1-1/2" diameter, to 10' high, includes 11 couplings per 100' | ELEC | 80 | 0.1 | L.F. | $ 11.05 | $ 7.75 | $ - 0 | $ 18.80 | $ 1,657.50 | $ 1,162.50 | $ - 0 | $ 2,820.00 | $ 12.15 | $ 11.45 | $ - 0 | $ 23.60 | $ 1,822.50 | $ 1,717.50 | $ - 0 | $ 3,540.00 | STD | Year 2026 Quarter 1 | National Average | |||||
| 14 | 260533950150 | Hole drilling, concrete wall, 8" thick, 1-1/2" pipe size, to 10' high | R31 | 9.5 | 0.842 | Ea. | $ 0.44 | $ 65.00 | $ 7.55 | $ 72.99 | $ 6.16 | $ 910.00 | $ 105.70 | $ 1,021.86 | $ 0.48 | $ 96.50 | $ 8.30 | $ 105.28 | $ 6.72 | $ 1,351.00 | $ 116.20 | $ 1,473.92 | STD | Year 2026 Quarter 1 | National Average | |||||
| 8 | 260533131995 | Rigid galvanized steel conduit, field bends, 45 Deg. to 90 Deg., 1-1/2" diameter | ELEC | 18 | 0.444 | Ea. | $ - 0 | $ 34.50 | $ - 0 | $ 34.50 | $ - 0 | $ 276.00 | $ - 0 | $ 276.00 | $ - 0 | $ 51.00 | $ - 0 | $ 51.00 | $ - 0 | $ 408.00 | $ - 0 | $ 408.00 | STD | Year 2026 Quarter 1 | National Average | |||||
| 3 | 260519900100 | Wire, copper, stranded, 600 volt, #12, type THW, normal installation conditions in wireway, conduit, cable tray | ELEC | 11 | 0.727 | C.L.F. | $ 25.00 | $ 56.00 | $ - 0 | $ 81.00 | $ 75.00 | $ 168.00 | $ - 0 | $ 243.00 | $ 27.50 | $ 83.50 | $ - 0 | $ 111.00 | $ 82.50 | $ 250.50 | $ - 0 | $ 333.00 | STD | Year 2026 Quarter 1 | National Average | |||||
| 200 | 260533131770 | Rigid galvanized steel conduit, 3/4" diameter, to 10' H, incl 2 terminations, 2 elbows, 11 beam clamps, and 11 couplings per 100 LF | ELEC | 80 | 0.1 | L.F. | $ 5.10 | $ 7.75 | $ - 0 | $ 12.85 | $ 1,020.00 | $ 1,550.00 | $ - 0 | $ 2,570.00 | $ 5.65 | $ 11.45 | $ - 0 | $ 17.10 | $ 1,130.00 | $ 2,290.00 | $ - 0 | $ 3,420.00 | STD | Year 2026 Quarter 1 | National Average | |||||
| 1 | 260526803790 | Insulated ground wire, copper, stranded, 1/0 | ELEC | 6.6 | 2.424 | C.L.F. | $ 340.00 | $ 187.00 | $ - 0 | $ 527.00 | $ 340.00 | $ 187.00 | $ - 0 | $ 527.00 | $ 375.00 | $ 278.00 | $ - 0 | $ 653.00 | $ 375.00 | $ 278.00 | $ - 0 | $ 653.00 | STD | Year 2026 Quarter 1 | National Average | |||||
| 4 | 260526800100 | Grounding rod, copper clad, 10' long, 3/4" diameter | ELEC | 4.4 | 1.818 | Ea. | $ 65.50 | $ 140.00 | $ - 0 | $ 205.50 | $ 262.00 | $ 560.00 | $ - 0 | $ 822.00 | $ 72.50 | $ 208.00 | $ - 0 | $ 280.50 | $ 290.00 | $ 832.00 | $ - 0 | $ 1,122.00 | STD | Year 2026 Quarter 1 | National Average | |||||
| 4 | 260526800170 | Grounding coupling, bronze, 3/4" diameter | 0 | 0 | Ea. | $ 24.00 | $ - 0 | $ - 0 | $ 24.00 | $ 96.00 | $ - 0 | $ - 0 | $ 96.00 | $ 26.00 | $ - 0 | $ - 0 | $ 26.00 | $ 104.00 | $ - 0 | $ - 0 | $ 104.00 | STD | Year 2026 Quarter 1 | National Average | ||||||
| 4 | 260526800220 | Grounding drive studs, 3/4" diameter | 0 | 0 | Ea. | $ 38.00 | $ - 0 | $ - 0 | $ 38.00 | $ 152.00 | $ - 0 | $ - 0 | $ 152.00 | $ 41.50 | $ - 0 | $ - 0 | $ 41.50 | $ 166.00 | $ - 0 | $ - 0 | $ 166.00 | STD | Year 2026 Quarter 1 | National Average | ||||||
| 4 | 260526800250 | Ground clamp, bronze, 3/4" diameter | ELEC | 32 | 0.25 | Ea. | $ 4.78 | $ 19.30 | $ - 0 | $ 24.08 | $ 19.12 | $ 77.20 | $ - 0 | $ 96.32 | $ 5.25 | $ 28.50 | $ - 0 | $ 33.75 | $ 21.00 | $ 114.00 | $ - 0 | $ 135.00 | STD | Year 2026 Quarter 1 | National Average | |||||
| 2 | 260519900140 | Wire, copper, stranded, 600 volt, #8, type THW, normal installation conditions in wireway, conduit, cable tray | ELEC | 8 | 1 | C.L.F. | $ 57.00 | $ 77.50 | $ - 0 | $ 134.50 | $ 114.00 | $ 155.00 | $ - 0 | $ 269.00 | $ 63.00 | $ 115.00 | $ - 0 | $ 178.00 | $ 126.00 | $ 230.00 | $ - 0 | $ 356.00 | STD | Year 2026 Quarter 1 | National Average | |||||
| 200 | 260533131770 | Rigid galvanized steel conduit, 3/4" diameter, to 10' H, incl 2 terminations, 2 elbows, 11 beam clamps, and 11 couplings per 100 LF | ELEC | 80 | 0.1 | L.F. | $ 5.10 | $ 7.75 | $ - 0 | $ 12.85 | $ 1,020.00 | $ 1,550.00 | $ - 0 | $ 2,570.00 | $ 5.65 | $ 11.45 | $ - 0 | $ 17.10 | $ 1,130.00 | $ 2,290.00 | $ - 0 | $ 3,420.00 | STD | Year 2026 Quarter 1 | National Average | |||||
| 8 | 260533131992 | Rigid galvanized steel conduit, field bends, 45 Deg. to 90 Deg., 3/4" diameter | ELEC | 40 | 0.2 | Ea. | $ - 0 | $ 15.45 | $ - 0 | $ 15.45 | $ - 0 | $ 123.60 | $ - 0 | $ 123.60 | $ - 0 | $ 23.00 | $ - 0 | $ 23.00 | $ - 0 | $ 184.00 | $ - 0 | $ 184.00 | STD | Year 2026 Quarter 1 | National Average | |||||
| 3 | 261316104800 | Circuit breaker, 3 pole, 15 to 60 amp, type FA | ELEC | 5.3 | 1.509 | Ea. | $ 840.00 | $ 117.00 | $ - 0 | $ 957.00 | $ 2,520.00 | $ 351.00 | $ - 0 | $ 2,871.00 | $ 925.00 | $ 173.00 | $ - 0 | $ 1,098.00 | $ 2,775.00 | $ 519.00 | $ - 0 | $ 3,294.00 | STD | Year 2026 Quarter 1 | National Average | |||||
| Unit Cost Total | $ 70,137.13 | $ 64,033.28 | $ 14,703.45 | $ 1,036.82 | $ 79,773.55 | $ 65,166.68 | $ - 0 | $ 14,982.28 | $ 1,081.22 | $ 81,230.18 | $ 70,678.22 | $ - 0 | $ 21,858.08 | $ 1,192.70 | $ 93,728.99 | |||||||||||||||
| Data Release : Predictive Year 2026 Quarter 1 as of Year 2024 Quarter 4 | Assembly Cost Lines | |||||||||||||||||||||||||||||
| Quantity | LineNumber | Line Source | SubContracted Ind. | Description | Crew | Daily Output | Labor Hours | Unit | Material | Labor | Equipment | Total | Ext. Mat. | Ext. Labor | Ext. Equip. | Ext. Total | Mat. O&P | Installation O&P | Labor O&P | Equip. O&P | Total O&P | Ext. Mat. O&P | Ext. Installation O&P | Ext. Labor O&P | Ext. Equip. O&P | Ext. Total O&P | Labor Type | Data Release | CCI Location | Notes |
| 40 | A10301204520 | U | Slab on grade, 6" thick, light industrial, reinforced | S.F. | $ 10.64 | $ 425.60 | $ 7.56 | $ 5.42 | $ 12.98 | $ 302.40 | $ 216.80 | $ 519.20 | STD | Year 2026 Quarter 1 | National Average | |||||||||||||||
| Assembly Cost Total | $ 10.64 | $ - 0 | $ - 0 | $ - 0 | $ 425.60 | $ 7.56 | $ 5.42 | $ - 0 | $ - 0 | $ 12.98 | $ 302.40 | $ 216.80 | $ - 0 | $ - 0 | $ 519.20 | |||||||||||||||
| Grand Total | $ 70,147.77 | $ 64,033.28 | $ 14,703.45 | $ 1,036.82 | $ 80,199.15 | $ 65,174.24 | $ 5.42 | $ 14,982.28 | $ 1,081.22 | $ 81,243.16 | $ 70,980.62 | $ 216.80 | $ 21,858.08 | $ 1,192.70 | $ 94,248.19 |