Questions and Answers 1.xlsx
XLSX spreadsheet 13 KB Posted
- Attached to
- BASE SUPPLY MANAGEMENT SERVICES
- Solicitation number
- FA9401-12-R-0012
About this file
Questions and Answers 1
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0004.doc | DOC document | |
| Questions and Answers 3.xlsx | XLSX spreadsheet | |
| Supply PWS revised 20 Jun 12.docx | DOCX document | |
| APPENDIX M GOVERNMENT FURNISHED FACILITIES Revised.docx | DOCX document | |
| Supply PWS revised 15 Jun 2012.docx | DOCX document | |
| APPENDIX D KIRTLAND SUPPLY WORKLOAD DATA Revised.docx | DOCX document | |
| APPENDIX L GOVERNMENT FURNISHED PROPERTY Revised.docx | DOCX document | |
| Questions and Answers 2.xlsx | XLSX spreadsheet | |
| Amendment 0003.doc | DOC document | |
| Conform Copy RFP 11Jun12.doc | DOC document | |
| Revised ADDENDUM TO FAR 52.212-4 11Jun12.pdf | ||
| Amendment 0002.pdf | ||
| Amendment 0001.pdf | ||
| Revised ADDENDUM TO FAR 52.212-4.pdf | ||
| APPENDICES.pdf | ||
| Wage Determination No.2005-2361.pdf | ||
| Supply 52.212-1.docx | DOCX document | |
| 2009 Supply Kirtland CBA.pdf | ||
| ADDENDUM TO 52.212-4.pdf | ||
| Supply RFP.doc | DOC document | |
| Supply PWS.docx | DOCX document | |
| DD Form 254.pdf |
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMENT FORM
RFP: FA9401-12-R-0012, Base Supply Management Services QUESTIONS & ANSWERS
| SECTION | LOCATION IDENTIFIER | COMMENT | KIRTLAND AFB RESPONSE |
| ITEM #/PARA | |||
| RFP | Is this a new or follow on requirement? If it is a follow on, please let us know the current contract number and incumbent name. | Follow-on requirement. Refer to FBO, solicitation number FA9401-11-R-0011, current contract redacted copy, for the contract number and incumbent name. | |
| RFP | Addendum to FAR 52.212-1 | Proposal submission is email or hard copy ? | Refer to "Addendum to FAR 52.212-1, instructions to offerors" Part I and Part II, page 1 &2. |
| RFP | And how many FTE's are required to perform the duty? | FTEs are to be determined by the contractor. | |
| RFP | RFP Attachment "addendum to FAR 52.212-4, para 8.0 FACILITY CLEARANCE (MAY 1996) (As prescribed in AFFARS 5315.209) and PWS Para 1.3.3.2 | Is the Contractor required to have a Top Secret facility clearance during submission of proposal, at the time of award, or will the Government sponsor the awardee for the clearance upon award? | Refer to PWS para 1.3.3.5 for the facility clearance requirement. "Para 8.0 FACILITY CLEARANCE (MAY 1996 )" is deleted from the RFP Attachment "addendum to FAR 52.212-4. "Revised addendum to FAR 52.212-4, 11Jun12" is posted to FBO. |
| RFP | RFP Closing Date? | Refer to FBO, solicitation FA9401-12-R-0012, Supply RFP attachment, page 1, block 8. | |
| RFP | RFP page 4, Item No. 0003 | The para states “Provide all personnel, equipment, tools, vehicles, supervision and other items and services necessary to perform the Base Supply Management and Operation Services at Kirtland AFB NM IAW PWS, excluding work to be performed in CLINs 0004, 0005, 0006, 0007, and 0008.” However Item No 0009 is also a discrete functional area (Research and Records Maintenance) of Base Supply Management and Operation Services. Should Item No 0009 also be excluded from Item No 0003? | Amendment 0002 is issued to correct this error. Amendment 0002 and Conform copy of RFP are posted to FBO. |
| RFP | RFP page 6, Item No 0007 Customer Requirements | This para references all of PWS para. 2.4 as items and services necessary to perform Item 0007. However Item 0008 references PWS para. 2.4.10 and 2.4.27 as items and services necessary to perform Item 0008. Please clarify the funding item that covers PWS para 2.4.10 and 2.4.27. | Amendment 0002 is issued to correct this error. Amendment 0002 and Conform copy of RFP are posted to FBO. |
| RFP | Addendum to FAR 52.212-1 and Addendum to FAR 52.212-2 | Will an award criteria section be included in solicitation FA9401-12-R-0012? | It is included in RFP. "Addendum to FAR 52.212-1, Instructions to Offerors" is an attachment to the RFP and "Addendum to FAR 52.212-2, Evaluation Criteria" is incorporated in RFP. |
| RFP | ADDENDUM TO FAR 52.212-1, Instructions to Offerors PG 3 para (c) | If we do not have sufficient time to complete the PPI 14 calendar days before the proposal is due, would you accept a 1 page table write up of items i thru vii to be due 14 calendar days before the proposal is due and then a complete finished proposal including all items for each contract due June 29th? | The offeror should submit the information necessary to meet the requirements stated in the RFP and addendum to FAR 52.212-1, para 2(c) |