SHAW AFB SC
FA8773-08-R-0082
General Decision Number: SC080010 02/08/2008 SC10 Superseded General Decision Number: SC20070010
State: South Carolina
Construction Types: Heavy (Heavy and Sewer and Water Line) Counties: Abbeville, Allendale, Bamberg, Barnwell, Beaufort, Calhoun, Cherokee, Chester, Chesterfield, Clarendon, Colleton, Darlington, Dillon, Edgefield, Fairfield, Georgetown, Greenwood, Hampton, Horry, Jasper, Kershaw, Lancaster, Laurens, Lee, Marion, Marlboro, McCormick, Newberry, Oconee, Orangeburg, Saluda, Sumter, Union and Williamsburg Counties in South
Carolina.
IN ALLENDALE AND BARNWELL COUNTIES, DOES NOT INCLUDE THE
SAVANNAH RIVER SITE
HEAVY CONSTRUCTION PROJECTS (includes sewer & water line projects)
Modification Number Publication Date
0 02/08/2008
* SUSC1990-005 02/08/1990
Rates Fringes
BOILERMAKER (TANK WORK)..........$ 12.96 3.315
BRICKLAYER.......................$ 6.40
Carpenter........................$ 7.42
Cement Mason/Concrete Finisher...$ 6.93
Electricians: (Linemen)..........$ 10.08
Ironworker.......................$ 10.98
Laborers:
Chain Saw...................$ 5.85
Pipelayer...................$ 5.85
Unskilled...................$ 5.85
Manhole Builder..................$ 5.85
Pipefitter.......................$ 9.09
Power equipment operators:
Backhoe.....................$ 6.40
Bulldozer...................$ 5.90
Crane.......................$ 7.98
Dragline....................$ 6.06
Front End Loader............$ 5.85
Mechanic....................$ 7.09
Motor Grader................$ 7.15
Scraper-Pan.................$ 5.85
Truck Driver.....................$ 5.85
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (ii)).
In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour
Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the
Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the
Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator
(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
PAGE
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 5 - Davis Bacon Act | — | |
| Attachment 2 - Performance Work Statement | — | |
| Performance Plan.doc | DOC document | |
| Attachment 4 - Service Contract Act | — | |
| Contract Award - F34608-08-D-0012.doc | DOC document | |
| Attachment 3 - Equipment and Installation Performance Specification | — | |
| Revised APPENDIX 5.2.doc | DOC document | |
| Amendment A001.doc | DOC document | |
| Attachment 1 - Pricing TableAmendment 0001.xls | XLS spreadsheet | |
| Attachment 4 - Service Contract Act | — | |
| Preproposal Agenda.doc | DOC document | |
| Preproposal Attendance Sheet.pdf | ||
| Questions and Answers.doc | DOC document | |
| Preproposal Notes.doc | DOC document | |
| Preproposal Conference Slides.pdf | ||
| F34608-03-D-0003 Generic Shaw.pdf | ||
| F34608-03-D-0003 Shaw.pdf | ||
| Attachment 3 - Equipment and Installation Performance Specification | — | |
| Attachment 2 - Performance Work Statement | — | |
| Attachment 4 - Service Contract Act | — | |
| Attachment 1 - Pricing Table.xls | XLS spreadsheet | |
| Attachment 6 - Past Performance Questionnaire | — | |
| SF 1449.doc | DOC document |
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .