Industry Day 3 Slides v2.pptx

PPTX presentation 2 MB Posted

Attached to
Base Infrastructure Modernization Industry Day 3
Solicitation number
FA8726-EITAAS-BIM-ID04
Issued by

About this file

This document provides an overview of a Base Infrastructure Modernization Industry Day presentation. The presentation discussed plans to award an Indefinite Delivery/Indefinite Quantity multiple award contract by Q3 FY24 to provide connectivity, network distribution, and network administration services for base infrastructure through task orders. A full and open competition with a small business reserve is planned, targeting 30% subcontracting goals to small businesses. The government anticipates issuing the draft request for proposals in Q1 FY24 and final RFP in Q2 FY24, with an initial task order award by Q4 FY24. Small businesses were encouraged to pursue teaming arrangements and mentor-protege relationships. The presentation addressed organizational conflicts of interest policies and provided acquisition timeline updates.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ROEs for Questions The chat window is for questions only – Include your companies name prior to the question Ex: Company A – Do we ask questions in the chat window?

All questions must be posted into the chat.

Following the presentation there will be a Q&A session. Questions about other programs will not be addressed.

The chat window will be open to receive questions throughout the briefing – It is recommended that Vendors wait until the Q&A session to avoid redundant questions.

Once a question is submitted, it will be reviewed internally to determine whether it is immediately answerable (e.g. is it relevant, is the information requested releasable, etc.), answerable later (requires further analysis), or is non-answerable.

As time and resources allow, the Government will do its best to answer verbally in real time. This may not be achievable. However, the Government will provide a response to any missed questions in the formalized Q&A submitted on Sam.gov.

SAM.gov will include all the answerable questions and will be sanitized of any identifiable information.

Industry Day is being recorded for Internal Use ONLY Government Attendees: Questions must be sent through Teams/Email

AFLCMC/HNIB

28 September 2023 v1 Base Infrastructure Modernization Industry Day 3 Controlled by: AFLCMC/HNIB Controlled by: AFLCMC/HNIB Program Office Category: General Procurement and Acquisition Distribution/Limited Dissemination Control: FEDCON POC: Mr. Brian Carr, AFLCMC/HNIB Industry Day will be recorded for internal use only

Agenda Opening Remarks – Mr. Stephen Bessette Organizational Conflict of Interest – MSgt Lent BIM Acquisition Updates – Mr. Brian Carr Questions and Answer Session – All

Opening Remarks Mr. Stephen Bessette

Organizational Conflict of Interest

(OCI)

Office of the Staff Judge Advocate Hanscom AFB, MA

Organizational Conflict of Interest Definitions FAR 2.101 - Because of other activities or relationships with other persons, a person is unable or potentially unable to render impartial assistance or advice to the Government, or the person’s objectivity in performing the contract work is or might be otherwise impaired, or a person has an unfair competitive advantage

FAR 9.504, Contracting Officer Responsibilities Identify and evaluate potential OCIs as early as possible Avoid, neutralize, or mitigate potential conflicts before contract award Should obtain the advice of legal counsel and technical experts in evaluating potential conflict

FAR 9.505, General Rules Each individual situation should be examined on the basis of its particular facts and the nature of the proposed contract Evaluation requires the exercise of common sense, good judgment, and sound discretion

Types of OCI Biased Ground Rules Systems Engineering and Technical Direction (FAR 9.505-1) Preparation of Statement of Work; Requirements (FAR 9.505-2)

Impaired Objectivity Providing Evaluation Services (FAR 9.505-3)

Unequal Access to Information Access to Proprietary Information (FAR 9.505-4)

Identification of an OCI An OCI may be identified by a contractor, Contracting Officer (CO), or industry

An OCI may be actual or potential conflicts

Types of conflicts involved

Description of contracts and business relationships that form the basis of the conflict

Explanation of means by which conflict may be eliminated or mitigated

Governing FAR Provisions FAR 9.504, Contracting Officer Responsibilities Identify and evaluate potential OCIs as early as possible Avoid, neutralize, or mitigate potential conflicts before contract award Obtain the advice of legal counsel and technical experts in evaluating potential conflicts

FAR 9.505, General Rules Each individual situation should be examined on the basis of its particular facts and the nature of the proposed contract Evaluation requires the exercise of common sense, good judgment, and sound discretion

Identification of an OCI and OCI Conclusion OCI Mitigation Plan Contents General Considerations Definitions Description of OCI situation Management of plan Management of personnel Review of plan

Definition of an Organizational Conflict of Interest Governing FAR provisions OCI Review Process

Base Infrastructure Modernization (BIM) Updates Mr. Brian Carr

Controlled Unclassified Information (CUI) Controlled Unclassified Information (CUI)

DescriptionProgram Diagram
Connect Solutions

Connectivity via Black Core Architecture at Layer 1 as-a-service Optimal combination of wired and wireless infrastructure to connect users to on- and off-premise enterprise services

BAN Operations (NIPR/SIPR) Network Distribution through a modernized architecture and network stack

Network Administration (NIPR/SIPR)

Support for SD-WAN

Proposed ScheduleContract Overview
Proposed Draft RFP: Q1 FY24

Proposed Final RFP: Q2 FY24 IDIQ Award: Q3 FY24 First TO Award: Q4 FY24 Multiple Award IDIQ, PoP: Q1/Q2 FY24 – Q1/Q2 FY34 IDIQ Total Length: 10 years (5 year base; 5 year option) TO Pool for Base Modernization/Operations (Large/Small business)

Effort Overview

ProgramFY 2023FY 2024
Q2Q3Q4Q1Q2Q3Q4
BIM
IDIQ Award
TO Award

Develop Bidder’s Library Develop Draft RFP Response & Evaluation TO Contract Definitization Update Contract Documentation

IDIQ Award

TO RFP Release

TO Award(s) Develop Bidder’s Library/Technical Documentation Business Clearance Draft RFP IDIQ RFP Release

Response & Evaluation Projected Acquisition Timeline

Business Clearance

Updated Strategy Overview

PreviousCurrent
Vendor Pools1 Services Pool
Separate 1 Equipment Pool SB Set-asideFull and Open pool and a SB Reserve pool

(All services and vendors purchase hardware) Integrator Role DAF Integrator Vendor Only

Overall scope of work has not changed. The Government has streamlined the number of pools to benefit schedule and performance. Through RRE Lessons Learned, the Government wants to avoid being the integrator.

IDIQ Tactical Overview Previous Concept

IDIQ Tactical Overview New Concept

*- Task Order numbers are for illustrative purposes only and are not a set-aside guarantee.

IDIQ: Full and Open Competition with Small Business Reserve The Reserve will include slots for SB's, 8(a)s, HUBZone, Woman-Owned, and Service-Disabled Veteran-Owned SB's Small Businesses (including SDBS) are strongly encouraged to form Small Business Teaming Arrangements (partnerships with other SB concerns) and Mentor-Protégé relationships (Mentor can be an SB or other-than-small) Evaluation for the Small Business Reserve will be the same as those not in the Small Business Reserve SB's in the Reserve will compete against the other IDIQ holders for awards, except for orders that are set aside On-ramping will occur approximately one year into the IDIQ, and additionally as needed, to bring additional Small Businesses (to include SBTAs, Joint Ventures, and Mentor-Protégés) into the IDIQ

Small Business Subcontracting Goals and Small Business Participation Commitments will be evaluated Contractor goals will be 30% of each order value subcontracted to Small Business concerns

Strategy to engage SBs for direct Task Order awards Government will have a 34% goal for Task Orders awarded to SBs Small Business Reserve will be the primary way to meet that goal Complexity and mission requirements will guide whether orders are set aside for Small Businesses or Small Business Concerns

Small Business Strategy

BIM – Documentation Updates

IDIQ

IDIQ Bidders Library Updates are coming

Feedback on the documents will be considered RFI for Task Order SLAs Releasing Service Level Agreements for comments and feedback.

This is strictly for the upcoming and future Task Orders. It has no bearing on the IDIQ or its evaluation.

TASK ORDERS

Alert for Small Businesses Seek information regarding Small Business Teaming Arrangements and Mentor-Protégé relationships now!

Vendor List of Attendees and Sign-ups will be provided in SAM an indicated in ID3 signup

Information for Small Business Teaming Arrangements and the Mentor-Protégé Programs DoD Mentor-Protégé Program - https://business.defense.gov/Programs/Mentor-Protege-Program/ Small Mentor, Small Protégé SBA Mentor-Protégé Program - https://www.sba.gov/federal-contracting/contracting-assistance-programs/sba-mentor-protege-program Small or Large Mentor, Small Protégé Small Business Joint Ventures - https://www.sba.gov/federal-contracting/contracting-assistance-programs/joint-ventures All parties must be a Small Business Small Businesses with Small Business Subcontractors - https://www.acquisition.gov/far/52.219-14

Q&A Session and Closing

Please submit any additional questions that were not answered at this Industry Day no later than 6 October via email to:

terri.rutkiewicz@us.af.mil Jason.Lent@us.af.mil

Verbal answers provided at this Industry Day will be official/formalized in writing posted on Sam.gov

The Government will post all questions received in any form in a formal Q&A Sam.gov posting image1.jpeg image2.emf image3.png image4.png image5.png image6.png

File details come from the government source that posted it. Updated .