DRAFT SDR Processes 2 Jul 25.pdf
PDF 212 KB Posted
- Solicitation number
- FA8630-24-R-B007
About this file
This document is a detailed process guide for Supply Discrepancy Reports (SDR) for the Parts and Repair Ordering System (PROS) contract. The document outlines five distinct processes for handling supply discrepancies: Original SDR, Request for Reconsideration, Contested SDR, Request for Additional Information, and Exhibit Return Request. Each process is structured with specific steps, maximum calendar days for completion, and precise actions required by different parties including the contractor, ILCO (Integrated Logistics Coordination Office), customer, PROS PMO, AFSAC/WFK, and others. The processes provide a comprehensive workflow for reporting, reviewing, challenging, and resolving supply discrepancies, with clear timeframes and status tracking mechanisms. Key elements include input requirements, response protocols, potential extensions, exhibit return procedures, and resolution pathways for different scenarios of supply discrepancy claims.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PROS Historical Actuals.xlsx | XLSX spreadsheet | |
| PROS 7 Section J Attachment 5 - Pricing Matrix.xlsx | XLSX spreadsheet | |
| DRAFT CDRLS 2Jul25.pdf | ||
| Solicitation - FA863025RB007 2Jul25.pdf | ||
| PROS 7 Section L DRAFT RFP 2Jul25.docx | DOCX document | |
| PROS 7 Section M DRAFT RFP 2Jul25.docx | DOCX document | |
| DRAFT PWS PROS 7 13Jun25.pdf | ||
| PROS 7 OPI Clause.pdf | ||
| 2025_Sample_Pros_Extract.zip | ZIP file | |
| Attachment 2 Draft PWS 1Oct2024.pdf | ||
| Attachment 1 Questions and USG Responses 3July2024.pdf | ||
| SSS 4 June 2024.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA8630-26-D-XXXX
Section J, Attachment 8, PROS SDR Processes
7 July 2025
PROS Supply Discrepancy Report (SOR) Processes
In accordance with PWS Paragraph 4.3 and Appendix A, the processes outlined in this document shall be used for all PROS Supply Discrepancy Reports (SDR). ILCO timeframes are provided for illustrative purposes only. All timeframes are calendar days.
Table of Contents Process 1 -Original SDR Process 2 - Request for Reconsideration Process 3 - Contested SDR Process 4- Request for Additional Infonnation Process 5 - Exhibit Return Request
Process 1- 0ri&inal SDR
Step Activity Max Calendar
Davs
Action
1 ILCO
(AFSAC
SDR Office
5 • ReviewSDR
• Release record to PROS contractor, updating SDR-A to status 20 -
Awaiting Action Agency Response, or close w/104 or denial w/o sending out
2 Contractor
(PROS
Prime Contractor)
60 • Review SOR and coordinate with vendor as applicable
- If SDR is for information only (H1), such as extended dollar value is
$200.00 or less, contractor shall reply with action activity response code 144 "Recorded for information and trend analysis"
- If contractor requires additional information from customer to process SDR, refer to Process4
- If contractor requires exhibit return for evaluation, refer to Process 5
- If necessary, request extension of Estimated Completion Date
(ECO); there shall be no more than two extensions of ECO and total of extension(s) shall not exceed 180 days and extension requests must have valid justification ; Valid justification consists of documentary evidence from vendor of action(s) in process to resolve SOR
- Input interim response in WebSDR extending ECO; response shall provide progress and SDR will be changed to 21 status
• Provide detailed validity recommendation with supporting documentation and Proof of Delivery (POD) to WebSDR input
- pending POD receipt
• Upload all supporting documentation and POD (as applicable) in WebSDR
3 ILCO 5 • Review contractor's reply and
- Release SOR to FMS customer or
- Reject SOR response if missing attachments identified in response or
- Coordinate, via email, with contractor if clarification of response is required
- Or reject response (23) for clarification
- If interim response, change status to reflect (21)
4 Contractor 5 • If rejected due to missing attachments, input documentation in WebSDR
• If email is received from ILCO for clarification, provide response
• For rejected response (23) in step 4, coordinate and input revised response in WebSDR
5 ILCO
5 • Review contractor's reply and
- Release SOR to FMScustomer or reject if reply is lacking/insufficient
Process 2 - Request for Reconsideration If original SOR claim is determined not valid, customer may request reconsideration. A request for reconsideration containing additional discrepancies NOT reported in original SOR may be determined not valid unless the initial failure prevented customer from discovering additional discrepancy, e.g. item failed on step 1 of test in original SOR and upon return to customer it failed on step 3.
Customer must request reconsideration within 45 days of original SOR response release date as indicated in SOR-A, unless exhibit was returned during original SOR. If exhibit was returned, customer is allowed 90 days to request reconsideration.
Davs
Action
1 Customer 45 or 90 • Request Reconsideration ofSDR, including added info required 2 ILCO 5 • Update SOR to status 20 "Awaiting Action Agency Response" and route to contractor or deny if no added info furnished 3 Contractor 60 • Review SOR and coordinate with vendor as applicable
- Recommend SOR not valid if customer claims additional discrepancies not reported in original SOR
- If contractor requires additional information from customer to process SOR, refer to Process4
- If contractor requires exhibit return for evaluation, refer to Process 5
- If necessary, request extension of Estimated Completion Date
(ECO); there shall be no more than two extensions of ECO and total of extension(s) shall not exceed 180 days and all extension request must have valid justification ; valid justification consists of documentary evidence from vendor of action(s) in process to resolve
SOR
- Input interim response in WebSDR extending ECO; response shall provide progress status
• Upload all supporting documentation and POD (as applicable) in WebSDR
• Input reply in WebSDR
4 ILCO 5 • Review contractor's reply and
- Release SOR to FMS customer or
- Place SOR in Interim status (21) if awaiting POD and update suspense or
- Reject reply (23) if missing or incorrect attachments identified in response or
- Coordinate, via email, if response clarification required
- If interim response, status will be updated to reflect (21)
5 Contractor 5 • If rejected due to missing attachments, input documentation in SOR-A
• If email is received from ILCO for clarification, provide response
• For rejected response (23) in step 5, coordinate and input revised response in SOR-A
6 ILCO
5 • Review contractor's reply and
- Release SOR to FMScustomer or reject if reply is lacking/insufficient
Process_3- Contested SDR If Reconsideration SOR is determined invalid, customer may contest decision with additional supporting documentation. Additional discrepancies NOT reported in original or reconsideration SORs will be determined invalid unless initial failure prevented customer from discovering additional discrepancy, e.g.
item failed on step 1 of test in original SOR and upon return to customer it failed on step 3.
Customer must request contest within 45 days of reconsideration SOR response release date as indicated in SOR-A, unless exhibit was returned during reconsideration SOR. If exhibit was returned, customer is allowed 90 days to request contest.
Davs
Action
1 Customer 45 or 90 • Submit Contested SOR with additional supporting information 2 ILCO 20 • Upon receipt, ILCO will review the contested SOR submission and supporting documentation (status code 14 - "Rejected SOR Submission
- Requires ILCO Review")
• Change SOR to status 26- "ILCO Intervention"
• Validate and prepare the contested package to include cover letter for
PMO and AFLCMC/WFK, to include statement of events and copies of any supporting documentation
• If additional, substantive information provided by customer or an event has occurred requiring another PMO review, forward contested SOR package to PMO
• Change SOR status code to 15 - "Awaiting PROS PMO Assessment (Contested)"
3 PROS
PMO (As Required)
50 • Review and generate PMO assessment of SOR claim
• As part of PMO assessment, contractor may be required to review any additional information provided in contested package to determine if additional information impacts previous decision
• Attach PMO assessment to contested SOR package and return to ILCO
• If, during PMO assessment, vendor reverses previous denial and proposes resolution to SOR, PMO will coordinate contractor's response via email with ILCO; If additional information or exhibit return is required, the process reverts back to Process 2; Request info or exhibit return per Process 4 or 5 as applicable
Page 5 of7
Days
Action
4 ILCO As required
• Coordinate with AFSAC management (Legal, SAF/IA & DSCA as applicable); If no contractor/USG liability:
- Determine location of assets and direct return to customer if required
- Obtain evidence of material return and attach to final reply
- Input reply closing SOR in SOR-A (status code CD -
"Credit Denied") and send final reply to customer
• If USG liable:
- Determine location of assets and direct return to customer if required
- Obtain evidence of material return and attach to final reply
- Input reply closing SOR (status code CA- "Credit Approved") and send final reply to customer
- Process reimbursement via admin funds
• If Contractorliable:
- Forward package to AFSAC/WFK for resolution
- Change Status code to 54 - "Awaiting AFLCMC/WFK Action on
Legal or MILDEP/DSCAApproval."
5 AFSAC/
WFK
30 • If AFLCMC/WFK accepts SAF/IA and DSCA final determination of contractor liability, take appropriate action by issuing demand letter to PROS contractor with copies to ILCO, Legal, and PMO
• If AFLCMC/WFK disagrees with SAF/IA and DSCA final determination and justifies contractor non-validity recommendation:
- Coordinate response with necessary parties
- Generate official correspondence for SAF/IA and DSCA review that justify contractor's recommendation
- Forward official correspondence to ILCO
6 Contractor 30 • Respond to demand letter
- Provide credit by inputting reply with action activity response code
101 - "Credit Approved" and process credit invoice, if applicable, or
- Provide alternate method of resolution
7 AFSAC/
WFK&
PMO
5 • Notify ILCO of final contract resolution
Page 6of 7
Process 4 - Request for Additional Information
Days
Action
Contractor
• Input reply in WebSDR (Reply code 104 - "Additional Clarification
Required from Customer. See Remarks") 2 ILCO 5 • Forward SOR reply requesting additional information to customer and update SOR status to 99 - "Awaiting Customer Response" 3 Customer 45 • Provide additional information requested 4 ILCO 5 • If received within 45 days, SOR-A will automatically forward updated SOR to contractor, updating SOR to status 20 - "Awaiting Action Agency Response"
• Process reverts to Process 1 or 2 as applicable
• If response from customer not received by day 46, SOR-A will automatically close SOR and provide email notification to customer, PMO and contractor
Process-5. - ExhibitRetum Request Note 1: Customer is required to return exhibit to USG custody within 180 days of notification as indicated in SOR-A. If vendor requires exhibit receipt at its facility (versus USG in-country turn-in point) within specified warranty timeframe and that timeframe is less than the required 180 days, contractor shall notify customer of reduced exhibit return time, with explanation why return time is reduced.
Note 2: When requesting exhibit, contractor shall include POC name and phone number at the exhibit destination in the exhibit request per U.S. Customs requirement.
Days
Action
1 Contractor 10 • Provide Not To Exceed (NTE) cost if evaluation fee will be charged for TTI should SOR be denied
• Notify customer of reduced exhibit return time if applicable w/explanation
• Input exhibit return request in WebSDR (Reply Code 108 - "Forward
Material to Address Shown for Inspection/Exhibit Analysis) 2 ILCO 5 • Generate DD 1348 for customer to return discrepant material
• Update SOR status to 99 - "Pending Exhibit Return"
• Monitor SOR until material physically returned to final destination provided by contractor
180 - Customer • Properly package SOR exhibit for shipment
• Return SOR exhibit as directed to final destination provided by contractor (USG allows an additional 30 days for customer to provide notification of shipment for total of 210 days, except as indicated in Note 1 above. Customer will receive follow-up reminder at 60 and 120 days and notice of closure at 210 days)
• Notify ILCO of material return; Failure to notify may result in closure of
SOR
4 ILCO 5 If customer provides notification of exhibit turn-in to USG custody, ILCO will attach to record, await receipt confirmation by contractor
• Upon confirmation of exhibit receipt at final destination, ILCO will update SOR status to 20
- "Awaiting Action Agency Response" w/contractor's Estimated Completion Date (ECO) of TTI
Page 7of 7
Days
Action
5 Contractor 60 • If exhibit not received as required, contractor inputs denial in WebSDR;
SOR may revert back to Process 1 or 2
• SDR reverts back to Process 1 or 2 as applicable
Process 2 - Request for Reconsideration
File details come from the government source that posted it. Updated .