Questions from Industry Post-RFP.xlsx

XLSX spreadsheet 22 KB Posted

Attached to
F-15 Training Device Acquisition and Support (TDAS) Federal contract opportunity
Solicitation number
FA8621-12-R-6259
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Wright Patterson Air Force Base

View the file

Other files for this federal contract opportunity

Other files attached to F-15 Training Device Acquisition and Support (TDAS), newest first.
File Type Posted
What's New 9 April 2012.pdf PDF
What's New.docx DOCX document
Att 18 - F15 TDAS Section L.pdf PDF
Solicitation - FA8621-12-R-6259 —
Questions from Industry Post-RFP.pdf PDF
Exhibit A - F-15 TDAS CDRLs.pdf PDF
Solicitation - FA8621-12-R-6259 —
Att 01 - PWS - F-15 TDAS.pdf PDF
Questions from Industry.xlsx XLSX spreadsheet
Contract Document - FA8621-12-R-6259.pdf PDF
Att 18E - Client Authorization Letter.pdf PDF
Request for Proposal Cover Letter - F-15 TDAS.pdf PDF
Questions from Industry.xlsx XLSX spreadsheet
Exhibit A - CDRLs.pdf PDF
Att 18B - Cross Reference Matrix.pdf PDF
Att 02 - Price Matrix.pdf PDF
What's New.docx DOCX document
Att 04 - ATD-MTD Device Locations.pdf PDF
Att 19 - TDAS Section M.pdf PDF
What's New.docx DOCX document
Att 02 - Price Matrix.pdf PDF
Draft Contractual Document - FA8621-12-R-6259.pdf PDF
What's New.docx DOCX document
Questions from Industry Site Visit.xlsx XLSX spreadsheet
Att 18A - Price Proposal Submission Sheet —
Att 19 - TDAS Section M 17Feb2012.pdf PDF
Exhibit A - F-15 TDAS CDRLs.pdf PDF
Att 18 - F15 TDAS Section L 17Feb12.pdf PDF
Att 18A - Price Proposal Submission Sheet and Att 02 —
TSSC Site Visit Info.docx DOCX document
What's New.docx DOCX document
Pre-Solicitation Conference Information.docx DOCX document
TFE-6 Conversion.pdf PDF
F-15 TDAS Data Rights.xlsx XLSX spreadsheet
Att 18A - Price Proposal Submission Sheet.pdf PDF
Att 18B - Cross Reference Matrix.pdf PDF
Att 18C - Past Performance Questionnaire.pdf PDF
Att 03 - Proposal Adequacy Checklist.pdf PDF
Att 18A - Price Proposal Submission Sheet.pdf PDF
Exhibit A - CDRLs - F-15 TDAS.pdf PDF
Att 03 - Proposal Adequacy Checklist.pdf PDF
Att 18G - IMP IMS Instructions.pdf PDF
Att 18 - F15 TDAS Section_L_17Jan12.pdf PDF
Questions from Industry RFI-PWS.xlsx XLSX spreadsheet
What's New.docx DOCX document
Restricted Data Rights.pdf PDF
What's New.docx DOCX document
What's New.pdf PDF
What's New.docx DOCX document
Attendee Sign-In.docx DOCX document
Show all 50

F-15 Training Device Acquisition and Support (TDAS) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FBO

QuestionsAnswersSectionLocation
1Regarding the TFE-2 Conversion GFAE file provided by the Government on Bidder's Library disk #2: will the Government supply the GFAE listed in Column H? If not, does (Y) in the required GFAE column (H) mean the parts must be real aircraft parts?The government will not be supplying GFAE listed in Column H. The parts with a (Y) in column H are required to be real aircraft parts.
2The IMP/IMS Instructions included with the Final RFP states that contract award is October 2013. Is this the official date, or is this date an error?This is an error. The anticipated contract award date is October 2012.
3The IMP/IMS Instructions included with the Final RFP calls out a requirement for EVMS. There is no requirement for EVMS in the PWS, Section L, or the Draft Contract Document. Also there is no requirement for EVMS reports in the CDRL requirement document (i.e. CPR, CSSR, CSFR, etc.).This is error. There is no requirement for EVMS as the current IMP/IMS Instructions state. EVMS will be removed from para. 3.
4In the PWS under paragraph 3.1.4.2 Monthly Activity Report it states the following; "The contractor shall submit monthly activity reports not later than (NLT) seven business days after the first of the month that shall address the following…." There is a requirement in CDRL list for CDRL A013, Contractor's Progress and Status Report, due 30 days after the completion of Transition and then monthly by the 10th of the month. Are these the same report? Also, please note there is no reference to the CDRL A013 in the PWS.CDRL A013 and A018 will be changed as follows: "Subsequent submissions shall be submitted Not Later Than (NLT) seven business days after the first of each month." Also, CDRL A013 is referenced with CDRLs A012 & A018 after PWS Para 3.1.4.2.8, the CDRL numbers will be moved to the bottom of the monthly report section.
5PWS paragraph 6.2.6 states that the Suite 8 OFP will include all items from a bulleted requirements list. Following the list it states that the Suite 8 OFP developed under another contract will include all items in the list. It's understood that this OFP will be acquired. Is it the Government's intention that the features listed under the third bullet and sub-bullets will be incorporated by the contractor during the Suite 8 OFP implementation in the training devices and this bullet is not something included in the acquired Suite 8 OFP? Will the received OFP already have the items identified as sub-bullets to bullet #3?The Suite 8 OFP will incorporate the capabilities of each bullet and sub-bullets in PWS Paragraph 6.2.6 into the aircraft programming modules. Those capabilities will need to be integrated into the TDAS devices. For instance, the Suite 8 OFP will allow the aircraft (and by extension the devices) to carry and launch an AIM-9X Block 1 or 2 missile, but the OFP and that capability will need to be integrated into the device to simulate it properly (i.e. add fly out model, etc).
6Section L, page 14, (B), please confirm the past performance questionnaire responses are due from the clients the same day as the Past Performance Volume, 29 March 2012.There is a discrepancy between the due date found in Section L and the due date found on Page 15 of the Past Performance Questionnaire (PPQ). However, we do not plan to revise the PPQ because, in many cases, offerors have already sent the PPQ to respondents. As such, we request that offerors instruct respondents to submit PPQs directly to the Contracting Officer by 26 Mar 2012 but no later than 29 March 2012. We request that Past Performance Volumes be submitted by 29 Mar 2012.
7Please describe the nature of the license for the "Threat Server, Multi-Mode Radar System (MMRS)." What is the type of license - site, node locked, user, enterprise, other? What is the maximum number of clients that can use the license? Are additional licenses required to be purchased for use on IAT number 7 & 8?This is a system server license, which is purchased for each device. This license will need to be purchased for IAT numbers 7 & 8.
8Is it the Government's intention for the contractor to submit all five sections of each Past Performance Questionnaire or just the completed sections 1-3 for each?Each offeror will complete Sections 1-3 of the questionnaire and send to POCs on the referenced contract. We expect each offeror to submit a copy of the questionnaire (with Sections 1-3 complete) directly to us as part of the Past Performance Volume. The respondent POCs will then complete Sections 4-5 and remit to the Government.
9Is it the Government's intention for the contractor to modify only 4 TFE-2, Automatic Flight Control System Trainers, as called out in the PWS (Para 6.2.2), not all 6 of the existing TFE-2 trainers?The Government plans to modify four of the TFE-2 trainers.

1.3.8

F-15 TDAS Questions and Answers 17 January 2012

All answers are subject to change until the Final RFP is issued.

File details come from the government source that posted it. Updated .