QuestionSet3.docx

DOCX document 14 KB Posted

Attached to
FA8604-MMHS-Storage Aid Systems at WrightPatteron, OH; Gunter Annex, AL; Columbus AFB, MS
Solicitation number
FA8604-20-R-8104
Issued by

About this file

This document includes a request for proposal and related questions and answers. The request seeks storage aid systems for the Air Force Research Laboratory buildings at Wright-Patterson Air Force Base in Ohio, Gunter Annex in Alabama, and Columbus Air Force Base in Mississippi. Key requirements include performance, design, fabrication, installation, orientation and testing of storage aid systems. Proposals are due by 4:00 PM Eastern time on May 14, 2020. The contract is to be completed within 280 days of award. Evaluation will be based on lowest price technically acceptable. The awarded contractor must be registered in SAM and have the capability to perform 50% of the work.

View the file

Other files

File Type Posted
FA8604-20-R-8104-P0005.pdf PDF
FA8604-20-R-8104-P0004.pdf PDF
Question Set 8.docx DOCX document
FA8604-20-R-8104-P0003.pdf PDF
QuestionSet7.pdf PDF
Amendment FA860420R8104_0002.pdf PDF
QuestionSet6.docx DOCX document
QuestionSet5.docx DOCX document
FA8604-20-R-8104-0001 Amendment.pdf PDF
QuestionSet4.docx DOCX document
QuestionSet2.docx DOCX document
QuestionSet1.docx DOCX document
FA8604-20-R-8104 Combined SS RFP.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A Set 3 (10 April 2020) Solitication #: FA8604-20-R-8104

1. There is no bid due date on the RFQ form. Can you please provide it?

ANSWER: Due date was included in the combined synopsis within the original post. All proposals are due by 4:00 PM ET on 14 May 2020.

2. For the Columbus AFB project paragraph 3.1.4 in the cover states the partition walls are to be 18’ high. Is this a typo? The pictures given (attachment 14) show a doorway that is probably 8’ high and the ceiling is right above it with the lights attached to what looks like 2x4s. The bin shelving we are putting inside the cage is only 87” high. 18’ seems like a lot of height when nothing tall is (seemingly) going in the cage. It also calls for chain link. Is wire partition acceptable as provided in previous projects?

ANSWER: The customer has existing 18’ chain link fence around the space and they would like this new fencing to match. Please comply with the specifications as written.