Solicitation #: FA8601-13-R-0052

ZHTV 11-0002, RENOVATE RESTROOMS F/20016

Pre-Award RFI-5

Q1. The finish schedule I-100 shows solid surface SS-1 in all the restrooms and are showing that some rooms get the tops, can you please clarify.

Response: The Finish Legend on I-100, inadvertently indicates solid surface “lavatory counters”.

There are no solid surface intregal bowl lavatory countertops in the project scope. Refer to the architectural and finish plans for locations with flat slab countertops that are solid surface. On the Finish Schedule, the reference to SS-1 is only applicable to countertops where called out on the architectural and finish plans.