Solicitation #: FA8601-13-R-0052
ZHTV 11-0002, RENOVATE RESTROOMS F/20016
Pre-Award RFI-4
Q1. Will we have access to the freight elevator?
Response: Use of the freight elevator will be permitted.
Q2. Where will the contractor parking be located?
Response: There will not be any assigned contractor parking. Use of the general parking spaces in the lots adjacent to the building is permitted.
Q3. Is there a designated entry point for deliveries?
Response: The south loading dock (1st floor) will be available as a designated entry point and use of the north east corner covered dock with access to the basement will be permitted as well.
Q4. Where will the dumpsters be located, and who is responsible for furnishing the dumpsters.
Response: Dumpsters will be permitted adjacent to both the loading docks designated as entry points. The dumpster location may be in a grass area and the the contractor shall include in their proposal restoration of the lawn per Section 01 01 50 – Project General Requirements.
Dumpster’s and waste removal are the responsibility of the Contractor. Refer to Section 01 01 50 –
Project General Requirements which cites “contractor’s approved containers” and “proper disposal of waste outside of WPAFB”. Refer to Section 01 02 20 – General Environmental Protection Requirements paragraph 3.7 Solid Waste and Recycling for additional information.