About this file

This document contains a question and answer log pertaining to a solicitation for the Simplified Acquisition of Base Engineering Requirements (SABER) contract at Wright-Patterson Air Force Base. The solicitation seeks proposals for construction services such as mechanical, electrical, and facility maintenance work, and is set aside for 8(a) firms located in Ohio. The log addresses questions from potential offerors regarding requirements for the technical proposal, pricing worksheet, personnel qualifications, and a seed project example. Key details include page limits, formatting guidelines, and clarification that pricing information should only be included in Volume III of proposals. Subcontracting of design specialties and naming of alternate contract managers are also addressed.

View the file

Other files for this federal contract opportunity

Other files attached to WPAFB Construction: Simplified Acquisition of Base Engineering Requirements (SABER), newest first.
File Type Posted
30011_Furniture Plan.pdf PDF
WPAFB_BFS_and_ Appendicies_Mar 2016.pdf PDF
Attachment 9 - SABER RFP Pricing Worksheet 2 Mar 2021.xlsx XLSX spreadsheet
Solicitation - FA860121R0015.pdf PDF
SABER QA Log.docx DOCX document
For SEED - Repair HVAC Private Offices 2014.zip ZIP file
For SEED - New Electrical Updates - Basement 2005.zip ZIP file
For SEED - Replace Water Lines 2006.zip ZIP file
For SEED - Building 11 Renovation 2006.zip ZIP file
For SEED - Replace HVAC and AHUA 2004.zip ZIP file
SABER QA Log.docx DOCX document
SABER QA Log.docx DOCX document
SABER QA Log.docx DOCX document
SABER SEED Visit - RFI Log.docx DOCX document
SABER QA Log.docx DOCX document
Attachment 3 - SEED SOO.docx DOCX document
Attachment 5 - Wage Determination - Greene.pdf PDF
Attachment 2 Final 2021 BASIC SOW 8 Feb 2021.docx DOCX document
Attachment 9 - SABER RFP Pricing Worksheet 8 Feb 21.xlsx XLSX spreadsheet
Solicitation - FA860121R0015.pdf PDF
Attachment 1 - Solication Cross Reference Matrix 22Jan21 final.docx DOCX document
Attachment 6 - Wage Determination - Montgomery.pdf PDF
Attachment 4 - SEED Drawing.pdf PDF
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A Log: WPAFB SABER Solicitation No. FA860121R0015

No.
Date Submitted:
Date Answered:
Question Asked:
Government’s Response:
1
2/19/21
2/22/21

Reference RFP L.4.2.4 – Step One, Prior Experience Compliance Gate

Two questions:

(1) Are Project Examples required to be double-spaced? If so, would the Government consider excluding these from the 45-page limit?

(2) Are Project Examples required for our A/E partner, and if so, does the 3 to 5-project requirement include their projects?

1) Project examples may be single spaced

2) A/E Partner does not need to provide 3-5 separate projects. The Government assumes that the A/E partner or sub would be included as part of the prime’s 3-5 project examples.

2
2/19/21
2/22/21
Reference RFP L.4.2.4 – Step Two, Factor 1, Subfactor 1, Item D – Personnel Resumes

We understand that resumes are excluded from the 45-page limit. Are they required to be double-spaced?

Resumes may be in the format in which the resumes are written, and are not required to be double spaced.

3
2/19/21
2/22/21
Reference RFP L.4.2.4 – Step Two, Factor 1, Subfactor 1, Item C – Teaming Agreement

A Teaming Agreement usually runs 7 to 8 pages. Can this item be excluded from the 45-page limit?

The teaming agreement page count may be excluded from the 45-page limit.

4
2/25/21
3/5/21
Do JCP certifications need to be for individual companies or do they need to be for the Joint Venture?

The JCP certification is required for the Joint Venture

5
2/25/21
2/26/21
What is required/meaning of one example of concurrent construction effort?

With SABER there may be multiple project executed at the same time. This requires staff to take on multiple rolls of various projects concurrently. An example would show how your company has carried out multiple projects where the staff may have been responsible for concurrently.

6
2/25/21
3/5/21
The Scope of Work States: “Provide Sound attenuation insulation to achieve an STC rating for privacy (STC 52)”, the door frame assemblies are not defined as needing to obtain an STC rating, does the Government require STC rated door and frame assemblies? If so, to what rating?
Yes. Frames need to be backfilled with appropriate sound deadening material for STC 52
7
2/25/21
2/26/21
Does the government require any other STC enhancements to the room such as Z-ducts for sound control?
No other STC enhancements are required.
8
2/25/21
2/26/21
Can all existing utilities that are not used or reconfigured remain above the ceiling or are they required to be demolished back to the source?
Any existing utilities above the ceiling can remain. They should be “capped off” appropriately.
9
2/25/21

Will bonding be per the entire SABER project or per individual SABER projects?

10
2/25/21

Please clarify if an offer guarantee (i.e., bid bond) is to be included with the proposal, and, if so, in what amount, and if an original hard copy is to be submitted in addition to our electronic submission.

11
2/25/21
2/26/21
Is text provided in tables and graphics required to be double spaced?
No.
12
2/25/21

Solicitation Section 3.4 Electronic Offer states, “The proposal shall be structured as set forth in the table in paragraph 3.1 above, where each item listed in the table shall be a separate folder containing the appropriate file(s). Use separate folders to permit rapid location of all portions, including Subfactors, required plans, exhibits, appendices, and attachments, if any.” Please clarify if the Government requires each Volume to be compiled into one file or if the Government prefers each individual source file to be submitted separately under a folder for each Volume?

Each volume shall be one folder, with documents for that volume enclosed in that folder. Please note, when uploading folders to DoD SAFE, they must be in a zipped format, as folders will not upload if folders are not zipped.

13
2/25/21
2/26/21
Please confirm that any documentation required to demonstrate Certification of US Ownership is excluded from the page limitation.

Correct. Cert of US Ownership is excluded from page limitation.

14
2/25/21
3/5/21
Step 2, Subfactor 1: Management Approach, Item D. states, “Provide evidence (personnel resumes) of qualified key personnel as defined in Section 3 of the SOW.” Please confirm that the key personnel requirements and qualifications as provided in the SOW are the only personnel requirements that must be met and that there are no additional specifications that define personnel qualifications. If there are any additional personnel specifications that apply, can these be provided by the Government as soon as possible so that bidders may have an opportunity to adjust proposed key personnel accordingly?

SOW Spells certifications as required or calls for requirements and certifications for specific job types.

15
2/25/21
2/26/21
Can the Environmental Manager position be subcontracted to a third party?

Yes

16
2/25/21
2/26/21
Prior Experience Compliance Gate, Item D. requests that offerors provide at least one example of concurrent construction efforts. Is it required that the concurrent projects are included in the 3 to 5 selected projects (i.e., that at least two of the submitted projects were performed concurrently)? Or, is it acceptable to demonstrate that an individual project of the 3 to 5 submitted was performed concurrently with other projects performed by the contractor?

It is acceptable to demonstrate an individual project of the 3 to 5 submitted was performed concurrently with other projects performed by the contractor

17
2/25/21
3/5/21
Please confirm that compliance under Item E under Prior Experience Compliance Gate only requires that one of the 3 to 5 submitted projects meets one of the three construction types listed in this Item.

(1) Project may meet all the requirements or 3 to 5 projects should be submitted to demonstrate the requirements. Not all projects submitted need to meet every requirement and projects submitted can meet multiple requirements.

18
2/25/21
2/26/21
For a firm proposing as a Joint Venture, please confirm if Prior Experience meeting the following scenario is compliant under Prior Experience Compliance Gate: If Company A was previously in a joint venture with Company B and Company A performed in JV A/B in the same role as they hold in the proposing joint venture between Company A and Company C, may the experience of JV A/B be submitted for Company A as part of JV A/C on this contract?

Yes, that is acceptable

19
2/25/21
2/26/21
Step 2, Subfactor 2: Project Planning and Execution, Item E.i, requests “a preliminary finish color and material board.” Can color photographs of the color and material boards be provided in lieu of actual color and material boards?

Yes. Photographs will be acceptable for this submission.

20
2/25/21
2/26/21
Step 2, Subfactor 2: Project Planning and Execution, Item F., states that the “proposed coefficients for the base period shall be applied to the seed project.” However, Volume III – Factor 2, Price, paragraph 5.1.2. Price Data, states that “Under no circumstances shall this data and documentation be included elsewhere in the proposal.” Please clarify if the coefficients are to be revealed in the Technical Proposal with the R.S. Means breakout for the seed project.

All pricing information shall be within Volume III. It is expected that the Seed Project documentation also contains pricing information.

21
2/25/21
2/26/21
Section 6.0 Volume IV Contract Documentation, paragraphs 6.1.3 – 6.1.5 list items that “the Government will provide.” Please confirm that these items will be provided after proposal submission and no information other than what is currently provided with the solicitation is to be returned by the offeror with its proposal.

Correct.

22
2/25/21
2/26/21
Under Section 6.2 Other Required Information, please confirm that only items 6.2.1 and 6.2.3. are to be returned with the offeror’s proposal.

Correct. Only information within section 6.2 that needs returned in proposal are 6.2.1 and 6.2.3

23
2/25/21
2/26/21
Statement of Work, Section 4.0 Technical Design Support states, “Required technical design capabilities include, but are not limited to, communications, architectural, structural, civil, mechanical, and electrical.” Please confirm that these design capabilities can be subcontracted to qualitied local A/E firms.

Yes. These design capabilities can be subcontracted as required for projects that require those specialties.

24
2/25/21
2/26/21
Statement of Work, Section 7.0 Quality Control, paragraph 7.1 states, “A finalized version of the quality control plan submitted with the Technical Proposal shall be submitted to the Contracting Officer within thirty (30) days of award.” Please confirm if a Quality Control Plan is to be submitted with offeror’s original proposal. If so, can this plan be excluded from the page limitation?
Yes this plan should be submitted with the original proposal. This may be excluded from the page limitation.
25
2/25/21
2/26/21
Are contractors required to name the Alternate Contract Manager at this time?

Not required at this time. Alternate Contract Manager can be named at award.

26
2/25/21
3/5/21
SOW Section 8, Site Office states the “site office shall be manned continuously during standard working hours and include the following functions: contract manager, task order managers, estimating, negotiating, scheduling, communications, and construction quality control.” However, SOW paragraph 3.1.5 indicates estimating and negotiating may be performed from a remote office. Please clarify the requirements for on-site capabilities.

The trailer should be manned by appropriate administrative personnel to ensure point of contact is always available.

27
2/25/21
3/2/21
The SOW indicates that the majority of Task Orders will be under $1 million, but the project size is capped at $5 million. Would the Government please provide an estimate of the percent of work that is anticipated to exceed $1 million.

Task Orders are provided by Fiscal Year. The scope and costs associated with each varies. An exact percentage cannot be provided.

28
2/25/21
2/26/21

Should offerors adjust Attachment 9, SABER Pricing Worksheet such that the Evaluated Prices are rounded to the nearest dollar, per Section L paragraph 5.1.4?

Yes. Please round to nearest dollar per Section L, Paragraph 5.1.4

29
2/25/21
2/26/21
On Attachment 9, SABER Pricing Worksheet, it appears that Year 5 is not currently being included in the formula in cell Q15 to calculate the Total Evaluated Price. Should offerors adjust this formula to include cell Q10?

Yes. Sorry for this error. Please add Q10 to the formula in Q15

30
2/25/21
2/26/21
Please confirm the SABER Pricing Worksheet is to be included in both Volume III and Volume IV.

No. Pricing Worksheet only needs to be in Volume III. Offeror need not fill out pricing information in Section B of Volume IV as the pricing worksheet included in Volume III fulfills this requirement

31
2/25/21
2/26/21
There appears to be conflicting information regarding the use of RSMeans labor line items in Statement of Work paragraph 11.1.2 and paragraphs 11.1.6.1 and 11.1.6.2. Please clarify the allowable use of the RSMeans labor line items.
11.1.2 Defines what the RS Means Pricing Book contains. This states that RS Means includes RS Means labor costs as line items of work. For 11.1.6.1 and 11.1.6.2 coefficients these DIV 01 labor line items shall not be used. The labor line items shall be included in the contractor’s adjustment factor.
32
2/25/21
2/26/21

Can the Government provide a list of all attendees at the Seed Project site visits so that potential offerors may have an opportunity to identify interested subcontractors for bidding purposes?

Yes. The Government will release a list of Seed Project Site Visit attendees soon.

33
2/25/21
2/26/21
Please confirm, as was mentioned at the seed project site visit, that exterior elevations are not required.

Exterior elevations submissions are not required since there is no exterior work for this project.

34
2/25/21
2/26/21
For the seed project, please confirm that existing Government owned TVs and other equipment will be removed by the Government prior to the start of work.

Yes. All furniture, art treatments, A/V equipment, and computer equipment will be removed by the government prior to the commencement of construction

35
2/25/21
2/26/21
For the seed project, please clarify the requirement for Texture and Pattern samples. Given that this is an electronic submission, are photographs acceptable to meet this requirement?

Photographs are acceptable as long as they can demonstrate the texture and pattern samples for any required submittals

36
2/25/21

Referencing Statement of Work paragraph 6.5.2.2., is Contracting planning to provide the carpet selection from all four carpet manufacturers or is there a waiver in place for this requirement? If not, please clarify how contractors are to provide carpet selection.

For seed project carpet selection, see question #37.

37
2/25/21

At the seed project site visit, it was indicated to replace the carpet to match existing. Please provide the existing carpet selection and manufacturer(s) as defined by SOW paragraph 6.5.2.2.

For the SEED project, all contractors shall please use a price of $2,000 and apply their coefficient to that price.

38
2/25/21
2/26/21
The Statement of Objectives (SOO) for the seed project identifies zero (0) days for Long Lead items. In reviewing the seed project requirements, it appears that long lead items are required. Please clarify if extra time will be granted for any long lead items that may be required.
Extra time in the schedule will be granted for Long Lead Items, as identified.
39
2/25/21
2/26/21
Is it the intent of the seed project to provide a complete STC-52 rated envelope for the new office spaces or just to provide an appropriate level of insulation for conversation-level privacy from the hallway?

The intent of the STC 52 rating is only desired for the partitions between adjoin and public spaces. Existing walls between current conference room and adjoin offices, wall between existing conference room and hallway and new partition wall between proposed offices. NOT the exterior wall or floor/ceiling.

40
2/25/21
2/26/21
For the seed project deliverables, is it required that offerors apply the formatting requirements specified for the remainder of the proposal as defined by paragraph 3.1.2 (e.g., 3/4-inch side margins, 12-point Times New Roman font, and double spacing) or would the Government prefer that deliverables conform to the format of a typical design task order submittal, given that reasonable font size, spacing, and margins are applied?

Formatting requirements shall follow the guidelines under paragraph 3.1.2 for all Offerors to have the same consistent format.

41
2/25/21
2/26/21
Will the Government please allow two business days after the release of RFI responses for offerors to submit any additional RFI that may occur as a result of the Government’s responses?

Government has established cutoff date for RFIs as 5 March. This will allow the Government until 9 March to respond to RFIs and allow for incorporation into proposals.

42
3/1/21

Please clarify if an offer guarantee in the form of a bid bond on SF-24 is to be included with the proposal, and, if so, in what amount? If there is a percentage (such as 20% of the bid or $3Million, whichever is less), please clarify if the percentage is based off the seed project bid only.

43
3/1/21

If a bid bond is required, must offerors submit the original hard copy to the owner in addition to including a scanned copy in the electronic submission?

44
3/1/21

There is no mention of a bid guarantee/bid bond in the organization of the volumes described in Section L. If a bid bond is required, please clarify where in the submission it should be located.

45
3/1/21
3/2/21
Section L, Item 6.1 requires that offerors return a signed copy of the Model Contract and sections A through K. Please clarify what parts of the solicitation specifically make up the “Model Contract.”
The solicitation is the model contract up to part L and on.
46
3/1/21
3/2/21
Is the offeror fulfilling the requirement to return a signed copy of the Model Contract by submitting the signed Standard Form 1442?
Yes
47
3/1/21
3/2/21
Please clarify if offerors should submit all pages of Sections A through K (including sections C, D, E, J), or only include Sections A, B, F, G, H, I, K as is listed in Items 6.1.1 through 6.1.7 of Section L.
Offerors shall follow the instructions in Section 6.1. The signed copy of the model contract covers sections C, D, E, J.
48
3/1/21
3/2/21
If Section C is to be included with our proposal, please confirm that Attachment 2 Statement of Work or any drawings or specifications do not need to be included.
No need to include the SOW for the basic IDIQ in the proposal.
49
3/1/21
3/2/21
Please confirm that none of the attachments listed in Section J need to be included in the proposal when submitting Sections A through K in Volume 4.
Attachment 9, Pricing Worksheet, shall be submitted with the proposal in accordance with 5.2.
50
3/2/21
3/5/21
The existing room thermostat in Room 107 appears to be pneumatic. Are the new VAV’s required to be pneumatic or DDC?
Verify pneumatic control and continue using existing system
51
3/2/21
3/5/21
Are the new VAV boxes required to have reheat capability? If so, is it hot water reheat or electric reheat?
Yes, hot water
52
3/2/21
3/5/21
Are there currently reheat supply and return water lines in proximity to Room 107?
Yes
53
3/2/21
3/5/21
Is return air ducted or ceiling plenum? What is required for this seed project?
Ducted
54
3/2/21
3/5/21
The Seed Project SOO requires fire alarm devices for the two new offices. The existing fire alarm control panel is a Autocall panel that was installed in 1982. New notification devices cannot be installed on this existing panel. Will it be necessary to include the installation of a new fire alarm control panel and update the devices throughout the entire facility?

Delete requirement

55
3/2/21
3/5/21
Regarding the seed project, is the existing plaster wall to receive a level 4 finish?
Yes
56
3/2/21
3/5/21
Regarding the seed project, do all STC walls need to be finished and primed to the deck above?
No. Only what is visible
57
3/2/21
3/5/21
Regarding the seed project, can all work be performed during normal working hours (7am-5pm)?
Yes
58
3/2/21
3/5/21
From our experience at the site visit on Feb 24, 2021, and our questions concerning existing equipment and infrastructure, we respectfully request as-built drawings that depict at least the immediate area, as well as drawings that would depict the mechanical room holding the mechanical equipment serving the subject area, as well as the server room to which necessary cabling needs to be routed to. Any details regarding the one-line diagram depicting the Fire Alarm Control Panel are also requested.
As-Builts will be provided. See item #54 regarding Fire Alarm Requirement
59
3/2/21
3/5/21
There is a provision in the solicitation requiring proof of documentation of domestic ownership. The operative language is as follows:

Provide documentation showing that the prime contractor level is US owned/operated contractors/companies; foreign contractors are prohibited to participate at this particular level. Provide certification by the Joint Certification Program (JCP) administered by the Defense Logistics Information Service (DLIS).

A. Question: If a bidder would choose to propose as a joint venture between a domestic 8a company and a foreign owned firm, with the 8a as the majority stakeholder of the firm, would such a joint venture violate the provisions of this requirement, namely having a foreign owned venture partner owning a minority stake in the Joint Venture?

B. Follow-on Question: Given that the response to the solicitation requires the offeror to be an 8a firm with a bona fide place of business in Ohio, or a Joint venture owned in the majority by the 8a, how is it even possible for a foreign company to enter into this competition given the nature of the 8a certification?

A. Yes. Foreign Contractors are prohibited to participate at this particular level as either a sole source or joint venture B. See response A

60
3/4/21
3/5/21
Solicitation, Section L, 3.1.2 (page 59), can the 1”margin contain header/footer information (i.e. solicitation #, volume #, page #)? If so, is it permitted that this text be formatted in the tables, charts, graphs, figures requirements of text no smaller than 10 point, as this is not the main narrative text?

Yes. This will be permitted

61
3/4/21
3/5/21
Solicitation, Section L, 3.1.2 (page 59), do we need to include the following information in the page footer of our proposal? “FOR OFFICIAL USE ONLY, SOURCE SELECTION INFORMATION, See FAR 3.104 AND 2.101”

If so, could this be in the margin of each page?

Yes. This will be permitted

3/9/21

In reference to QA Log No. 12 response, could you provide more information on how you would like the electronic files submitted and organized on the DoD SAFE website, for your ease of use?

Solicitation, Section L, 3.4 – states “Electronic files shall be titled SABER_Rebuy_Contractor_Name_WPAFB_2021”. With multiple folders (one for each Volume) and files (subfactors/sections), do we include this as the name of each folder and file? Should we put the Volume # or Subfactor # after the 2021 in the title?

Yes. The name should be included on each folder and file to ensure all files submitted are credited to the contractor submitting. Volume # and Subfactor # should be included after the title.

3/9/21
Per QA Log No. 12: “Each volume shall be one folder, with documents for that volume enclosed in that folder.” Is it sufficient to include a combined PDF of each Volume (to include table of contents, glossary, all sections, etc.) and also include separate files of each section/subfactor?
For the purposes of review, the documents (PDFs) should remain separate rather than combined.
3/9/21
Per the solicitation and QA log responses, there are multiple items that are excluded from the page count (i.e. JCP documentation, teaming agreement, resumes, seed project proposal). Do you still want those pages sequentially numbered if they are excluded from the page limits?

If these are not be page numbered, do you want these items in appendices or in the corresponding sections without page numbers?

Exclude these from the page count. Corresponding sections without page numbers shall be appropriate

65
3/5/21
3/9/21
In the 2021 RS Means Facilities Construction Cost Data manual, there is a new section, 01 21 53.65, incorporating items for infection disease precautions. Please clarify if contractors will be allowed to use these line items on the new contract as long as COVID-19 protocols are mandated on projects?
Yes, due to COVID restrictions in some situations, this line item may be warranted.
66
03/05/21
3/9/21
SECTION – J: Reflects a table of attachments under column “Number” items #4&5 are missing. Under column “Attachment Name” attachments #7&8 are missing. Are there additional documents that should have been provided?
There is no attachment 7 or 8 for this effort (only 1-6, and 9). The contract writing system puts a number in the “number” column for section J. Under attachment name there should be attachments named 1-6 & 9. There are no additional attachments should have been provided. Please ignore the “number” column.
67
03/05/21
3/9/21
Attachment 3 – SEED SOO.docx: Item 3.5 indicates all work shall be compliant with the SOW and “Specifications” Are there specifications or Base Standards available?
The specifications will be following the UFGS and UFC and The Base Facility Standards (BFS). The latest BFS is available.
68
03/05/21
3/9/21
Attachment 3 – SEED SOO.docx: 10.1 HAZARDOUS MATERIAL: directs us to remove lead-based paint and mold as required. Due to the age of the facility, there is a high probability of encountering those conditions and also ACM.

· Has any Hazardous material testing been done for the facility?

· Can you please provide a copy of any reports?

Shall we include special testing in our proposal?

No testing has been done. Testing may be included in the proposal if there is indication of any hazardous material.

69
03/05/21
3/9/21
Attachment 3 – SEED SOO.docx: 8. *Schedule of Materials Submittals, and 9.*Drawings Required: Is it the intent that the proposal include all items marked with and “X”?
yes
70
03/05/21
3/9/21
Attachment 3 – SEED SOO.docx: Is this an example of the standard Task Order proposal request, that we are to assume will be issued with each TO?
yes
71
03/05/21
3/9/21
Attachment 3 – SEED SOO.docx: Item10.2.3 makes a reference to “within removed walls”

1. Is it the intent that we remove the common wall at the west side of the space to reconstruct as a STC 52 rated assembly?

If the common wall between adjacent space to the west is to remain, what is the construction assembly? We need to determine what is required to meet the STC rating.

If any walls are to be removed, then any existing wiring, receptacles, or other utilities shall be removed. For this project, no walls are removed.

72
03/05/21
3/9/21
Attachment 3 – SEED SOO.docx: Item 10.5.1 references “Return Duct Lines”, during the site visit upon inspection of the space above the acoustical ceiling, there was a single supply line and nothing identified as a return line ducting. Is this facility a ducted return or a return air plenum?
The facility does not have a return air plenum.
73
03/05/21

In lieu of the extensive last minute RFIs and government responses, would the government provide an additional week extension to the submission proposal date?

74
03/05/21
3/9/21
Site Visit: Contractors identified that there appeared to be a built-up GWB assembly on the corridor side of wall. If this is multiple layers of GWB in an attempt to increase the STC rating, please provide the wall assembly to determine the requirements to bring this wall to the STC 52 rating.
The make-up of the wall assembly for the corridor wall may be altered only from the interior of the new offices. The corridor side should not be altered. Wall assembly types are only provided and required for Sensitive Compartmented Information Facilities to meet a required DoD Standard. For STC requirements, use standard construction methods or assemblies to meet the requirement.
75
03/05/21
3/9/21
Attachment 3 – SEED SOO.docx: Item 10.3.1 directs us to 10.3.1 Infill areas around new windows with brick masonry to match existing elevation.” It is my understanding that this is deleted from the SSO scope of work. Is this correct?
This is correct. No masonry work is part of the scope for this project.
76
03/05/21
3/9/21
Attachment 3 – SEED SOO.docx: Item10.4.5 directs us to “Provide and install comm. as designated on furniture plan.” Please provide the furniture layout so we can determine the pathway for the new comm and data.
Plans will be provided
77
03/05/21
3/9/21
Attachment 3 – SEED SOO.docx: Item10.3.4 directs us to “Provide Sound attenuation insulation to achieve an STC rating for privacy (STC 52)”

1. Is this for all walls? (East, West, South, North)

2. What is the existing East Wall construction? It looks like it could be masonry or concrete.

3. Are we to assume the doors required per 10.3.6 are to be full STC 52 Rated assemblies? (door/frame/hardware) Is the STC 52 a prescribed construction, or will there be testing requirement for the assemblies and spaces?

1. This rating requirement for Sound Privacy is for the corridor wall, adjoining walls shared with other office spaces and the new partition separating the conference room. Not the exterior wall, floor or ceiling.

2. This should be identified in the As-Builts.

3. Yes the door and frame assembly should meet the STC 52

4. STC 52 is a prescribed construction. Testing is not required.

78
03/05/21
3/9/21
Are there and based facility design guides, or facility standards that need to be considered? And will the government provide these documents?
There is a Base Facility Standard (BFS) specific to WPAFB. This document will be provided.
79
3/5/21
3/9/21
Reference RFP L 5.2, Section 3.

There is a request for “other information” that includes “termination costs”. Please explain what is meant by “termination costs”.

Contract Termination Costs