About this file

This document contains a Q&A log and details of a federal contract opportunity for construction services at Wright-Patterson Air Force Base. The Simplified Acquisition of Base Engineering Requirements for WPAFB solicitation is set aside for 8(a) small businesses located in Ohio involved in general building construction. The Q&A log addresses page limits, formatting requirements, and exclusions for project examples, resumes, and teaming agreements in proposals due in response to the solicitation. Relevant response dates are provided.

View the file

Other files for this federal contract opportunity

Other files attached to WPAFB Construction: Simplified Acquisition of Base Engineering Requirements (SABER), newest first.
File Type Posted
30011_Furniture Plan.pdf PDF
WPAFB_BFS_and_ Appendicies_Mar 2016.pdf PDF
Solicitation - FA860121R0015.pdf PDF
Attachment 9 - SABER RFP Pricing Worksheet 2 Mar 2021.xlsx XLSX spreadsheet
SABER QA Log.docx DOCX document
SABER QA Log.docx DOCX document
For SEED - Replace HVAC and AHUA 2004.zip ZIP file
For SEED - Repair HVAC Private Offices 2014.zip ZIP file
For SEED - New Electrical Updates - Basement 2005.zip ZIP file
For SEED - Replace Water Lines 2006.zip ZIP file
For SEED - Building 11 Renovation 2006.zip ZIP file
SABER QA Log.docx DOCX document
SABER QA Log.docx DOCX document
SABER QA Log.docx DOCX document
SABER SEED Visit - RFI Log.docx DOCX document
Attachment 4 - SEED Drawing.pdf PDF
Solicitation - FA860121R0015.pdf PDF
Attachment 1 - Solication Cross Reference Matrix 22Jan21 final.docx DOCX document
Attachment 6 - Wage Determination - Montgomery.pdf PDF
Attachment 3 - SEED SOO.docx DOCX document
Attachment 5 - Wage Determination - Greene.pdf PDF
Attachment 2 Final 2021 BASIC SOW 8 Feb 2021.docx DOCX document
Attachment 9 - SABER RFP Pricing Worksheet 8 Feb 21.xlsx XLSX spreadsheet
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A Log: WPAFB SABER Solicitation No. FA860121R0015

No.
Date Submitted:
Date Answered:
Question Asked:
Government’s Response:
1
2/19/21
2/22/21

Reference RFP L.4.2.4 – Step One, Prior Experience Compliance Gate

Two questions:

(1) Are Project Examples required to be double-spaced? If so, would the Government consider excluding these from the 45-page limit?

(2) Are Project Examples required for our A/E partner, and if so, does the 3 to 5-project requirement include their projects?

1) Project examples may be single spaced

2) A/E Partner does not need to provide 3-5 separate projects. The Government assumes that the A/E partner or sub would be included as part of the prime’s 3-5 project examples.

2
2/19/21
2/22/21
Reference RFP L.4.2.4 – Step Two, Factor 1, Subfactor 1, Item D – Personnel Resumes

We understand that resumes are excluded from the 45-page limit. Are they required to be double-spaced?

Resumes may be in the format in which the resumes are written, and are not required to be double spaced.

3
2/19/21
2/22/21
Reference RFP L.4.2.4 – Step Two, Factor 1, Subfactor 1, Item C – Teaming Agreement

A Teaming Agreement usually runs 7 to 8 pages. Can this item be excluded from the 45-page limit?

The teaming agreement page count may be excluded from the 45-page limit.