Cost Format C_CLIN Summary
| Degraded Visual Environment System - RFP Cost Model |
| "Offeror shall enter data in yellow highlighted fields only" |
| Solicitation Number: |
| Enter Offeror's Business Name: |
| Enter Offeror's CAGE code: |
| Basic Period (Sep 2027 - Sep 2029) | | | | | | | | | |
| CLIN | Contract Type | Description | QTY | Unit | Cost | COM | Fee | Unit Price | Extended Price |
| 0001 | CPFF | HH-60W Degraded Visual Environment System Research, Development, Test, and Evaluation (RDT&E) | 1 | LO | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 0002 | CPFF | HH-60W Degraded Visual Environment System Prototype Installation Kit | 1 | KT | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 0003 | CPFF | HH-60W Degraded Visual Environment System Verification Installation Kit | 1 | KT | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 0004 | CPFF | HH-60W Degraded Visual Environment System Lab/Simulator Kits | 3 | KT | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 0005 | CPFF | HH-60W Degraded Visual Environment System Prototype Installation Labor | 1 | LO | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 0006 | CPFF | HH-60W Degraded Visual Environment System Verification Installation Labor | 1 | LO | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 0007 | FFP | HH-60W Degraded Visual Environment System Familiarization | 1 | LO | | | | $0.00 | $0.00 |
| 0008 | CRNF | Contractor Travel | 1 | LO | $0.00 | $0.00 | | $0.00 | $0.00 |
| 0009 | NSP | Data | 1 | LO | | | | | |
| Total Extended Price - Basic Period | | | | | | | | | $0.00 |
| Ordering Period I (Sep 2029 - Mar 2031) | | | | | | | | | |
| CLIN | Contract Type | Description | QTY | Unit | Cost | COM | Fee | Unit Price | Extended Price |
| 1001 | CPFF | HH-60W Degraded Visual Environment System Research, Development, Test, and Evaluation (RDT&E) | 1 | LO | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 1002 | FFP | HH-60W Degraded Visual Environment System Production Kits (A+B) | 30 | KT | | | | $0.00 | $0.00 |
| 1003 | FFP | HH-60W Degraded Visual Environment System Production Kit Spares (B Only) | 3 | KT | | | | $0.00 | $0.00 |
| 1004 | CPFF | HH-60W Degraded Visual Environment System Production Installation Labor (A+B) | 1 | LO | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 1005 | CPFF | HH-60W Degraded Visual Environment System Prototype Installation Labor | 1 | LO | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 1006 | CPFF | HH-60W Degraded Visual Environment System Verification Installation Labor | 1 | LO | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 1007 | CRNF | Contractor Travel | 1 | LO | $0.00 | $0.00 | | $0.00 | $0.00 |
| 1008 | NSP | Data | 1 | LO | | | | | |
| Total Extended Price - Ordering Period I | | | | | | | | | $0.00 |
| Option 1 (with 5 (five) 1 year Ordering Periods, exercised NLT March 2031 | | | | | | | | | |
| Ordering Period II (Mar 2031 - Sep 2032) | | | | | | | | | |
| CLIN | Contract Type | Description | QTY | Unit | Cost | COM | Fee | Unit Price | Extended Price |
| 2001 | FFP | HH-60W Degraded Visual Environment System Production Kits (A+B) | 29 | KT | | | | $0.00 | $0.00 |
| 2002 | FFP | HH-60W Degraded Visual Environment System Production Kit Spares (B Only) | 3 | KT | | | | $0.00 | $0.00 |
| 2003 | CPFF | HH-60W Degraded Visual Environment System Production Installation Labor (A+B) | 1 | LO | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 2004 | CRNF | Contractor Travel | 1 | LO | $0.00 | $0.00 | | $0.00 | $0.00 |
| 2005 | NSP | Data | 1 | LO | | | | | |
| Total Extended Price - Ordering Period II | | | | | | | | | $0.00 |
| Ordering Period III (Sep 2032 - Mar 2034) | | | | | | | | | |
| CLIN | Contract Type | Description | QTY | Unit | Cost | COM | Fee | Unit Price | Extended Price |
| 3001 | FFP | HH-60W Degraded Visual Environment System Production Kits (A+B) | 26 | KT | | | | $0.00 | $0.00 |
| 3002 | FFP | HH-60W Degraded Visual Environment System Production Kit Spares (B Only) | 2 | KT | | | | $0.00 | $0.00 |
| 3003 | CPFF | HH-60W Degraded Visual Environment System Production Installation Labor (A+B) | 1 | LO | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 3004 | CRNF | Contractor Travel | 1 | LO | $0.00 | $0.00 | | $0.00 | $0.00 |
| 3005 | NSP | Data | 1 | LO | | | | | |
| Total Extended Price - Ordering Period III | | | | | | | | | $0.00 |
| Ordering Period IV (Mar 2034 - Sep 2035) | | | | | | | | | |
| CLIN | Contract Type | Description | QTY | Unit | Cost | COM | Fee | Unit Price | Extended Price |
| 4001 | FFP | HH-60W Degraded Visual Environment System Production Kits (A+B) | 24 | KT | | | | $0.00 | $0.00 |
| 4002 | FFP | HH-60W Degraded Visual Environment System Production Kit Spares (B Only) | 2 | KT | | | | $0.00 | $0.00 |
| 4003 | CPFF | HH-60W Degraded Visual Environment System Production Installation Labor (A+B) | 1 | LO | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 4004 | CRNF | Contractor Travel | 1 | LO | $0.00 | $0.00 | | $0.00 | $0.00 |
| 4005 | NSP | Data | 1 | LO | | | | | |
| Total Extended Price - Ordering Period IV | | | | | | | | | $0.00 |
| Ordering Period V (Sep 2035 - Sep 2036) | | | | | | | | | |
| CLIN | Contract Type | Description | QTY | Unit | Cost | COM | Fee | Unit Price | Extended Price |
| 5001 | CPFF | HH-60W Degraded Visual Environment System Production Installation Labor (A+B) | 1 | LO | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 5002 | CRNF | Contractor Travel | 1 | LO | $0.00 | $0.00 | | $0.00 | $0.00 |
| 5003 | NSP | Data | 1 | LO | | | | | |
| Total Extended Price - Ordering Period V | | | | | | | | | $0.00 |
| Ordering Period VI (Sep 2036 - Sep 2037) | | | | | | | | | |
| CLIN | Contract Type | Description | QTY | Unit | Cost | COM | Fee | Unit Price | Extended Price |
| 5001 | CPFF | HH-60W Degraded Visual Environment System Production Installation Labor (A+B) | 1 | LO | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 5002 | CRNF | Contractor Travel | 1 | LO | $0.00 | $0.00 | | $0.00 | $0.00 |
| 5003 | NSP | Data | 1 | LO | | | | | |
| Total Extended Price - Ordering Period VI | | | | | | | | | $0.00 |
Total Proposed Price $0.00
| 18-Jun-26 |
| SOURCE SELECTION INFORMATION--SEE FAR 2.101 and 3.104 |
FOR OFFICIAL USE ONLY
FFP CLINs
| Notes: |
| 1. The prime offeror shall enter a proposed unit price per CLIN in the yellow-highlighted cells below. |
| 2. Each Firm Fixed Price shall be rounded to the nearest whole dollar. |
| 3. The prime offeror shall ensure the cells below are linked correctly to the CLIN cells on worksheet "Cost Format C_CLIN Summary". |
| Basic Period (Sep 2027 - Sep 2029) | | | Ordering Period I (Sep 2029 - Mar 2031) | | | Ordering Period II (Mar 2031 - Sep 2032) | | | Option Period III (Sep 2032 - Mar 2034) | | | Option Period IV (Mar 2034 - Sep 2035) | | |
| CLIN 0007 | | | CLIN 1002 | | | CLIN 2001 | | | CLIN 3001 | | | CLIN 4001 | | |
| Qty | Unit | Proposed Unit Price | Qty | Unit | Proposed Unit Price | Qty | Unit | Proposed Unit Price | Qty | Unit | Proposed Unit Price | Qty | Unit | Proposed Unit Price |
| 1 | LO | | 30 | KT | | 29 | KT | | 26 | KT | | 24 | KT | |
| CLIN 1003 | | | CLIN 2002 | | | CLIN 3002 | | | CLIN 4002 | | |
| Qty | Unit | Proposed Unit Price | Qty | Unit | Proposed Unit Price | Qty | Unit | Proposed Unit Price | Qty | Unit | Proposed Unit Price |
| 3 | KT | | 3 | KT | | 2 | KT | | 2 | 0 | |
Cost Format A_NRE CLINs
| Notes: |
| 1. The format of this worksheet may be revised as required to be consistent with the Prime Offeror's approved accounting system. |
| 2. The Prime Offeror shall propose labor hours, material costs, and other direct costs in the yellow-highlighted cells below. |
| 3. The Prime Offeror shall ensure the yellow-highlighted rate cells below are linked correctly from the relevant labor rate and add-on factors in the 'Cost Format B_PRIME Rates' worksheet. |
| 4. The proposed factors will be applied to the proposed labor hours, material cost, and other direct costs. |
| 5. Definitions of the labor categories and add-on factors are included in the 'Cost Format B_PRIME Rate Desc' worksheet. |
| 6. Each CPFF Cost, COM and Fee shall be rounded to the nearest whole dollar. |
| CLINs 0001, 1001: CPFF | Proposed Prices (Labor) | | | Proposed Prices (Labor) | | |
| 0001: HH-60W Degraded Visual Environment System Research, Development, Test, and Evaluation (RDT&E) | | | 1001: HH-60W Degraded Visual Environment System Research, Development, Test, and Evaluation (RDT&E) | | |
| Labor Category | Hours | Rates | Cost | Hours | Rates | Cost |
| Labor Category 1: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 2: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 3: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 4: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 5: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 6: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 7: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 8: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 9: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 10: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 11: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 12: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 13: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| TOTAL HOURS/COST | 0 | | $0.00 | 0 | | $0.00 |
| Base | Rates | Cost | Base | Rates | Cost |
| Proposed Add-on Factor (Fringe) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 | | | $0.00 |
| Total Proposed COM | | | $0.00 | | | $0.00 |
| Total Proposed Fee | | | $0.00 | | | $0.00 |
| Total Proposed Price | | | $0.00 | | | $0.00 |
| CLINs 0001, 1001: CPFF | Proposed Prices (Material) | | | Proposed Prices (Material) | | |
| 0001: HH-60W Degraded Visual Environment System Research, Development, Test, and Evaluation (RDT&E) | | | 1001: HH-60W Degraded Visual Environment System Research, Development, Test, and Evaluation (RDT&E) | | |
| Base | Rates | Cost | Base | Rates | Cost |
| Total Proposed Material Cost | | | | | | |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 | | | $0.00 |
| Total Proposed COM | | | $0.00 | | | $0.00 |
| Total Proposed Fee | | | $0.00 | | | $0.00 |
| Total Proposed Price | | | $0.00 | | | $0.00 |
| CLINs 0001, 1001: CPFF | Proposed Prices (Other Direct Cost) | | | Proposed Prices (Other Direct Cost) | | |
| 0001: HH-60W Degraded Visual Environment System Research, Development, Test, and Evaluation (RDT&E) | | | 1001: HH-60W Degraded Visual Environment System Research, Development, Test, and Evaluation (RDT&E) | | |
| Base | Rates | Cost | Base | Rates | Cost |
| Total Proposed Other Direct Cost (ODC) | | | | | | |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 | | | $0.00 |
| Total Proposed COM | | | $0.00 | | | $0.00 |
| Total Proposed Fee | | | $0.00 | | | $0.00 |
| Total Proposed Price | | | $0.00 | | | $0.00 |
| CLINs 0001, 1001: CPFF | Proposed Prices (Labor, Material, and ODC) | | Proposed Prices (Labor, Material, and ODC) | |
| | CLIN 0001: Basic Period (CPFF) | | CLIN 1001: Ordering Period 1 (CPFF) |
| Total Proposed Cost | | $0.00 | | $0.00 |
| Total Proposed COM | | $0.00 | | $0.00 |
| Total Proposed Fee | | $0.00 | | $0.00 |
| Total Proposed Price | | $0.00 | | $0.00 |
Cost Format A_Prototype Kit
| Notes: |
| 1. The format of this worksheet may be revised as required to be consistent with the Prime Offeror's approved accounting system. |
| 2. The Prime Offeror shall propose labor hours, material costs, and other direct costs in the yellow-highlighted cells below. |
| 3. The Prime Offeror shall ensure the yellow-highlighted rate cells below are linked correctly from the relevant labor rate and add-on factors in the 'Cost Format B_PRIME Rates' worksheet. |
| 4. The proposed factors will be applied to the proposed labor hours, material cost, and other direct costs. |
| 5. Definitions of the labor categories and add-on factors are included in the 'Cost Format B_PRIME Rate Desc' worksheet. |
| 6. Each CPFF Cost, COM and Fee shall be rounded to the nearest whole dollar. |
| CLIN 0002: CPFF | Proposed Prices (Labor) | | |
| 0002: HH-60W Degraded Visual Environment System Prototype Installation Kit | | |
| Labor Category | Hours | Rates | Cost |
| Labor Category 1: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 2: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 3: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 4: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 5: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 6: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 7: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 8: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 9: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 10: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 11: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 12: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 13: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| TOTAL HOURS/COST | 0 | | $0.00 |
| Base | Rates | Cost |
| Proposed Add-on Factor (Fringe) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 |
| Total Proposed COM | | | $0.00 |
| Total Proposed Fee | | | $0.00 |
| Total Proposed Price | | | $0.00 |
| CLIN 0002: CPFF | Proposed Prices (Material) | | |
| 0002: HH-60W Degraded Visual Environment System Prototype Installation Kit | | |
| Base | Rates | Cost |
| Total Proposed Material Cost | | | |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 |
| Total Proposed COM | | | $0.00 |
| Total Proposed Fee | | | $0.00 |
| Total Proposed Price | | | $0.00 |
| CLIN 0002: CPFF | Proposed Prices (Other Direct Cost) | | |
| 0002: HH-60W Degraded Visual Environment System Prototype Installation Kit | | |
| Base | Rates | Cost |
| Total Proposed Other Direct Cost (ODC) | | | |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 |
| Total Proposed COM | | | $0.00 |
| Total Proposed Fee | | | $0.00 |
| Total Proposed Price | | | $0.00 |
| CLIN 0002: CPFF | Proposed Prices (Labor, Material, and ODC) | |
| | CLIN 0002: Basic Period (CPFF) |
| Total Proposed Cost | | $0.00 |
| Total Proposed COM | | $0.00 |
| Total Proposed Fee | | $0.00 |
| Total Proposed Price | | $0.00 |
Cost Format A_Verification Kit
| Notes: |
| 1. The format of this worksheet may be revised as required to be consistent with the Prime Offeror's approved accounting system. |
| 2. The Prime Offeror shall propose labor hours, material costs, and other direct costs in the yellow-highlighted cells below. |
| 3. The Prime Offeror shall ensure the yellow-highlighted rate cells below are linked correctly from the relevant labor rate and add-on factors in the 'Cost Format B_PRIME Rates' worksheet. |
| 4. The proposed factors will be applied to the proposed labor hours, material cost, and other direct costs. |
| 5. Definitions of the labor categories and add-on factors are included in the 'Cost Format B_PRIME Rate Desc' worksheet. |
| 6. Each CPFF Cost, COM and Fee shall be rounded to the nearest whole dollar. |
| CLIN 0003: CPFF | Proposed Prices (Labor) | | |
| 0003: HH-60W Degraded Visual Environment System Verification Installation Kit | | |
| Labor Category | Hours | Rates | Cost |
| Labor Category 1: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 2: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 3: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 4: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 5: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 6: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 7: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 8: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 9: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 10: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 11: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 12: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 13: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| TOTAL HOURS/COST | 0 | | $0.00 |
| Base | Rates | Cost |
| Proposed Add-on Factor (Fringe) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 |
| Total Proposed COM | | | $0.00 |
| Total Proposed Fee | | | $0.00 |
| Total Proposed Price | | | $0.00 |
| CLIN 0003: CPFF | Proposed Prices (Material) | | |
| 0003: HH-60W Degraded Visual Environment System Verification Installation Kit | | |
| Base | Rates | Cost |
| Total Proposed Material Cost | | | |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 |
| Total Proposed COM | | | $0.00 |
| Total Proposed Fee | | | $0.00 |
| Total Proposed Price | | | $0.00 |
| CLIN 0003: CPFF | Proposed Prices (Other Direct Cost) | | |
| 0003: HH-60W Degraded Visual Environment System Verification Installation Kit | | |
| Base | Rates | Cost |
| Total Proposed Other Direct Cost (ODC) | | | |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 |
| Total Proposed COM | | | $0.00 |
| Total Proposed Fee | | | $0.00 |
| Total Proposed Price | | | $0.00 |
| CLIN 0003: CPFF | Proposed Prices (Labor, Material, and ODC) | |
| | CLIN 0003: Basic Period (CPFF) |
| Total Proposed Cost | | $0.00 |
| Total Proposed COM | | $0.00 |
| Total Proposed Fee | | $0.00 |
| Total Proposed Price | | $0.00 |
Cost Format A_LabSim Kits
| Notes: |
| 1. The format of this worksheet may be revised as required to be consistent with the Prime Offeror's approved accounting system. |
| 2. The Prime Offeror shall propose labor hours, material costs, and other direct costs in the yellow-highlighted cells below. |
| 3. The Prime Offeror shall ensure the yellow-highlighted rate cells below are linked correctly from the relevant labor rate and add-on factors in the 'Cost Format B_PRIME Rates' worksheet. |
| 4. The proposed factors will be applied to the proposed labor hours, material cost, and other direct costs. |
| 5. Definitions of the labor categories and add-on factors are included in the 'Cost Format B_PRIME Rate Desc' worksheet. |
| 6. Each CPFF Cost, COM and Fee shall be rounded to the nearest whole dollar. |
| CLIN 0004: CPFF | Proposed Prices (Labor) | | |
| 0004: HH-60W Degraded Visual Environment System Lab/Simulator Kits | | |
| Labor Category | Hours | Rates | Cost |
| Labor Category 1: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 2: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 3: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 4: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 5: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 6: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 7: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 8: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 9: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 10: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 11: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 12: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| Labor Category 13: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 |
| TOTAL HOURS/COST | 0 | | $0.00 |
| Base | Rates | Cost |
| Proposed Add-on Factor (Fringe) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 |
| Total Proposed COM | | | $0.00 |
| Total Proposed Fee | | | $0.00 |
| Total Proposed Price | | | $0.00 |
| CLIN 0004: CPFF | Proposed Prices (Material) | | |
| 0004: HH-60W Degraded Visual Environment System Lab/Simulator Kits | | |
| Base | Rates | Cost |
| Total Proposed Material Cost | | | |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 |
| Total Proposed COM | | | $0.00 |
| Total Proposed Fee | | | $0.00 |
| Total Proposed Price | | | $0.00 |
| CLIN 0004: CPFF | Proposed Prices (Other Direct Cost) | | |
| 0004: HH-60W Degraded Visual Environment System Lab/Simulator Kits | | |
| Base | Rates | Cost |
| Total Proposed Other Direct Cost (ODC) | | | |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 |
| Total Proposed COM | | | $0.00 |
| Total Proposed Fee | | | $0.00 |
| Total Proposed Price | | | $0.00 |
| CLIN 0004: CPFF | Proposed Prices (Labor, Material, and ODC) | |
| | CLIN 0004: Basic Period (CPFF) |
| Total Proposed Cost | | $0.00 |
| Total Proposed COM | | $0.00 |
| Total Proposed Fee | | $0.00 |
| Total Proposed Price | | $0.00 |
Cost Format A_Proto-Insta-Labor
| Notes: |
| 1. The format of this worksheet may be revised as required to be consistent with the Prime Offeror's approved accounting system. |
| 2. The Prime Offeror shall propose labor hours, material costs, and other direct costs in the yellow-highlighted cells below. |
| 3. The Prime Offeror shall ensure the yellow-highlighted rate cells below are linked correctly from the relevant labor rate and add-on factors in the 'Cost Format B_PRIME Rates' worksheet. |
| 4. The proposed factors will be applied to the proposed labor hours, material cost, and other direct costs. |
| 5. Definitions of the labor categories and add-on factors are included in the 'Cost Format B_PRIME Rate Desc' worksheet. |
| 6. Each CPFF Cost, COM and Fee shall be rounded to the nearest whole dollar. |
| CLINs 0005, 1005: CPFF | Proposed Prices (Labor) | | | Proposed Prices (Labor) | | |
| 0005: HH-60W Degraded Visual Environment System Prototype Installation Labor | | | 1005: HH-60W Degraded Visual Environment System Prototype Installation Labor | | |
| Labor Category | Hours | Rates | Cost | Hours | Rates | Cost |
| Labor Category 1: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 2: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 3: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 4: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 5: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 6: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 7: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 8: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 9: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 10: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 11: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 12: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 13: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| TOTAL HOURS/COST | 0 | | $0.00 | 0 | | $0.00 |
| Base | Rates | Cost | Base | Rates | Cost |
| Proposed Add-on Factor (Fringe) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 | | | $0.00 |
| Total Proposed COM | | | $0.00 | | | $0.00 |
| Total Proposed Fee | | | $0.00 | | | $0.00 |
| Total Proposed Price | | | $0.00 | | | $0.00 |
| CLINs 0005, 1005: CPFF | Proposed Prices (Material) | | | Proposed Prices (Material) | | |
| 0005: HH-60W Degraded Visual Environment System Prototype Installation Labor | | | 1005: HH-60W Degraded Visual Environment System Prototype Installation Labor | | |
| Base | Rates | Cost | Base | Rates | Cost |
| Total Proposed Material Cost | | | | | | |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 | | | $0.00 |
| Total Proposed COM | | | $0.00 | | | $0.00 |
| Total Proposed Fee | | | $0.00 | | | $0.00 |
| Total Proposed Price | | | $0.00 | | | $0.00 |
| CLINs 0005, 1005: CPFF | Proposed Prices (Other Direct Cost) | | | Proposed Prices (Other Direct Cost) | | |
| 0005: HH-60W Degraded Visual Environment System Prototype Installation Labor | | | 1005: HH-60W Degraded Visual Environment System Prototype Installation Labor | | |
| Base | Rates | Cost | Base | Rates | Cost |
| Total Proposed Other Direct Cost (ODC) | | | | | | |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 | | | $0.00 |
| Total Proposed COM | | | $0.00 | | | $0.00 |
| Total Proposed Fee | | | $0.00 | | | $0.00 |
| Total Proposed Price | | | $0.00 | | | $0.00 |
| CLINs 0005, 1005: CPFF | Proposed Prices (Labor, Material, and ODC) | | Proposed Prices (Labor, Material, and ODC) | |
| | CLIN 0005: Basic Period (CPFF) | | CLIN 1005: Ordering Period 1 (CPFF) |
| Total Proposed Cost | | $0.00 | | $0.00 |
| Total Proposed COM | | $0.00 | | $0.00 |
| Total Proposed Fee | | $0.00 | | $0.00 |
| Total Proposed Price | | $0.00 | | $0.00 |
Cost Format A_Veri-Insta-Labor
| Notes: |
| 1. The format of this worksheet may be revised as required to be consistent with the Prime Offeror's approved accounting system. |
| 2. The Prime Offeror shall propose labor hours, material costs, and other direct costs in the yellow-highlighted cells below. |
| 3. The Prime Offeror shall ensure the yellow-highlighted rate cells below are linked correctly from the relevant labor rate and add-on factors in the 'Cost Format B_PRIME Rates' worksheet. |
| 4. The proposed factors will be applied to the proposed labor hours, material cost, and other direct costs. |
| 5. Definitions of the labor categories and add-on factors are included in the 'Cost Format B_PRIME Rate Desc' worksheet. |
| 6. Each CPFF Cost, COM and Fee shall be rounded to the nearest whole dollar. |
| CLINs 0006 & 1006: CPFF | Proposed Prices (Labor) | | | Proposed Prices (Labor) | | |
| 0006: HH-60W Degraded Visual Environment System Verification Installation Labor | | | 1006: HH-60W Degraded Visual Environment System Verification Installation Labor | | |
| Labor Category | Hours | Rates | Cost | Hours | Rates | Cost |
| Labor Category 1: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 2: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 3: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 4: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 5: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 6: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 7: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 8: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 9: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 10: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 11: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 12: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 13: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| TOTAL HOURS/COST | 0 | | $0.00 | 0 | | $0.00 |
| Base | Rates | Cost | Base | Rates | Cost |
| Proposed Add-on Factor (Fringe) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 | | | $0.00 |
| Total Proposed COM | | | $0.00 | | | $0.00 |
| Total Proposed Fee | | | $0.00 | | | $0.00 |
| Total Proposed Price | | | $0.00 | | | $0.00 |
| CLINs 0006 & 1006: CPFF | Proposed Prices (Material) | | | Proposed Prices (Material) | | |
| 0006: HH-60W Degraded Visual Environment System Verification Installation Labor | | | 1006: HH-60W Degraded Visual Environment System Verification Installation Labor | | |
| Base | Rates | Cost | Base | Rates | Cost |
| Total Proposed Material Cost | | | | | | |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 | | | $0.00 |
| Total Proposed COM | | | $0.00 | | | $0.00 |
| Total Proposed Fee | | | $0.00 | | | $0.00 |
| Total Proposed Price | | | $0.00 | | | $0.00 |
| CLINs 0006 & 1006: CPFF | Proposed Prices (Other Direct Cost) | | | Proposed Prices (Other Direct Cost) | | |
| 0006: HH-60W Degraded Visual Environment System Verification Installation Labor | | | 1006: HH-60W Degraded Visual Environment System Verification Installation Labor | | |
| Base | Rates | Cost | Base | Rates | Cost |
| Total Proposed Other Direct Cost (ODC) | | | | | | |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 | | | $0.00 |
| Total Proposed COM | | | $0.00 | | | $0.00 |
| Total Proposed Fee | | | $0.00 | | | $0.00 |
| Total Proposed Price | | | $0.00 | | | $0.00 |
| CLINs 0006 & 1006: CPFF | Proposed Prices (Labor, Material, and ODC) | | Proposed Prices (Labor, Material, and ODC) | |
| | CLIN 0006: Basic Period (CPFF) | | CLIN 1006: Ordering Period 1 (CPFF) |
| Total Proposed Cost | | $0.00 | | $0.00 |
| Total Proposed COM | | $0.00 | | $0.00 |
| Total Proposed Fee | | $0.00 | | $0.00 |
| Total Proposed Price | | $0.00 | | $0.00 |
Cost Format A_Travel CLINs
| Notes: |
| 1. The format of this worksheet may be revised as required to be consistent with the Prime Offeror's approved accounting system. |
| 2. The Prime Offeror shall propose labor hours, material costs, and other direct costs in the yellow-highlighted cells below. |
| 3. The Prime Offeror shall ensure the yellow-highlighted rate cells below are linked correctly from the relevant labor rate and add-on factors in the 'Cost Format B_PRIME Rates' worksheet. |
| 4. The proposed factors will be applied to the proposed labor hours, material cost, and other direct costs. |
| 5. Definitions of the labor categories and add-on factors are included in the 'Cost Format B_PRIME Rate Desc' worksheet. |
| 6. Each CPFF Cost, COM and Fee shall be rounded to the nearest whole dollar. |
| CLINs 0008, 1007, 2004, 3004, 4004, 5002, 6002 | Proposed Prices (Other Direct Cost) | | | Proposed Prices (Other Direct Cost) | | | Proposed Prices (Other Direct Cost) | | | Proposed Prices (Other Direct Cost) | | | Proposed Prices (Other Direct Cost) | | | Proposed Prices (Other Direct Cost) | | | Proposed Prices (Other Direct Cost) | | |
| 0008: Travel - Basic Period | | | 1007: Travel - Ordering Period 1 | | | 2004: Travel - Ordering Period 2 | | | 3004: Travel - Ordering Period 3 | | | 4004: Travel - Ordering Period 4 | | | 5002: Travel - Ordering Period 5 | | | 6002: Travel - Ordering Period 6 | | |
| Base | Rates | Cost | Base | Rates | Cost | Base | Rates | Cost | Base | Rates | Cost | Base | Rates | Cost | Base | Rates | Cost | Base | Rates | Cost |
| Total Proposed Other Direct Cost (ODC) | | | | | | | | | | | | | | | | | | | | | |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| Total Proposed COM | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| Total Proposed Price | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| Proposed Prices (Labor, Material, and ODC) | | Proposed Prices (Labor, Material, and ODC) | | Proposed Prices (Labor, Material, and ODC) | | Proposed Prices (Labor, Material, and ODC) | | Proposed Prices (Labor, Material, and ODC) | | Proposed Prices (Labor, Material, and ODC) | | Proposed Prices (Labor, Material, and ODC) | |
| | CLIN 0008: Basic Period | | CLIN 1007: Ordering Period 1 | | CLIN 2004: Ordering Period 2 | | CLIN 3004: Ordering Period 3 | | CLIN 4004: Ordering Period 4 | | CLIN 5002: Ordering Period 5 | | CLIN 6002: Ordering Period 6 |
| Total Proposed Cost | | $0.00 | | $0.00 | | $0.00 | | $0.00 | | $0.00 | | $0.00 | | $0.00 |
| Total Proposed COM | | $0.00 | | $0.00 | | $0.00 | | $0.00 | | $0.00 | | $0.00 | | $0.00 |
| Total Proposed Price | | $0.00 | | $0.00 | | $0.00 | | $0.00 | | $0.00 | | $0.00 | | $0.00 |
Cost Format A_Prod-Insta-Labor
| Notes: |
| 1. The format of this worksheet may be revised as required to be consistent with the Prime Offeror's approved accounting system. |
| 2. The Prime Offeror shall propose labor hours, material costs, and other direct costs in the yellow-highlighted cells below. |
| 3. The Prime Offeror shall ensure the yellow-highlighted rate cells below are linked correctly from the relevant labor rate and add-on factors in the 'Cost Format B_PRIME Rates' worksheet. |
| 4. The proposed factors will be applied to the proposed labor hours, material cost, and other direct costs. |
| 5. Definitions of the labor categories and add-on factors are included in the 'Cost Format B_PRIME Rate Desc' worksheet. |
| 6. Each CPFF Cost, COM and Fee shall be rounded to the nearest whole dollar. |
| CLIN 1004, 2003, 3003, 4003, 5001, 6001 : CPFF | Proposed Prices (Labor) | | | Proposed Prices (Labor) | | | Proposed Prices (Labor) | | | Proposed Prices (Labor) | | | Proposed Prices (Labor) | | | Proposed Prices (Labor) | | |
| 1004: HH-60W Degraded Visual Environment System Production Installation Labor | | | 2003: HH-60W Degraded Visual Environment System Production Installation Labor | | | 3003: HH-60W Degraded Visual Environment System Production Installation Labor | | | 4003: HH-60W Degraded Visual Environment System Production Installation Labor | | | 5001: HH-60W Degraded Visual Environment System Production Installation Labor | | | 6001: HH-60W Degraded Visual Environment System Production Installation Labor | | |
| Labor Category | Hours | Rates | Cost | Hours | Rates | Cost | Hours | Rates | Cost | Hours | Rates | Cost | Hours | Rates | Cost | Hours | Rates | Cost |
| Labor Category 1: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 2: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 3: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 4: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 5: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 6: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 7: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 8: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 9: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 10: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 11: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 12: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 13: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| TOTAL HOURS/COST | 0 | | $0.00 | 0 | | $0.00 | 0 | | $0.00 | 0 | | $0.00 | 0 | | $0.00 | 0 | | $0.00 |
| Base | Rates | Cost | Base | Rates | Cost | Base | Rates | Cost | Base | Rates | Cost | Base | Rates | Cost | Base | Rates | Cost |
| Proposed Add-on Factor (Fringe) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| Total Proposed COM | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| Total Proposed Fee | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| Total Proposed Price | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| CLIN 1004, 2003, 3003, 4003, 5001, 6001 : CPFF | Proposed Prices (Material) | | | Proposed Prices (Material) | | | Proposed Prices (Material) | | | Proposed Prices (Material) | | | Proposed Prices (Material) | | | Proposed Prices (Material) | | |
| 1004: HH-60W Degraded Visual Environment System Production Installation Labor | | | 2003: HH-60W Degraded Visual Environment System Production Installation Labor | | | 3003: HH-60W Degraded Visual Environment System Production Installation Labor | | | 4003: HH-60W Degraded Visual Environment System Production Installation Labor | | | 5001: HH-60W Degraded Visual Environment System Production Installation Labor | | | 6001: HH-60W Degraded Visual Environment System Production Installation Labor | | |
| Base | Rates | Cost | Base | Rates | Cost | Base | Rates | Cost | Base | Rates | Cost | Base | Rates | Cost | Base | Rates | Cost |
| Total Proposed Material Cost | | | | | | | | | | | | | | | | | | |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| Total Proposed COM | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| Total Proposed Fee | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| Total Proposed Price | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| CLIN 1004, 2003, 3003, 4003, 5001, 6001 : CPFF | Proposed Prices (Other Direct Cost) | | | Proposed Prices (Other Direct Cost) | | | Proposed Prices (Other Direct Cost) | | | Proposed Prices (Other Direct Cost) | | | Proposed Prices (Other Direct Cost) | | | Proposed Prices (Other Direct Cost) | | |
| 1004: HH-60W Degraded Visual Environment System Production Installation Labor | | | 2003: HH-60W Degraded Visual Environment System Production Installation Labor | | | 3003: HH-60W Degraded Visual Environment System Production Installation Labor | | | 4003: HH-60W Degraded Visual Environment System Production Installation Labor | | | 5001: HH-60W Degraded Visual Environment System Production Installation Labor | | | 6001: HH-60W Degraded Visual Environment System Production Installation Labor | | |
| Base | Rates | Cost | Base | Rates | Cost | Base | Rates | Cost | Base | Rates | Cost | Base | Rates | Cost | Base | Rates | Cost |
| Total Proposed Other Direct Cost (ODC) | | | | | | | | | | | | | | | | | | |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| Total Proposed COM | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| Total Proposed Fee | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| Total Proposed Price | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| CLIN 1004, 2003, 3003, 4003, 5001, 6001 : CPFF | Proposed Prices (Labor, Material, and ODC) | | Proposed Prices (Labor, Material, and ODC) | | Proposed Prices (Labor, Material, and ODC) | | Proposed Prices (Labor, Material, and ODC) | | Proposed Prices (Labor, Material, and ODC) | | Proposed Prices (Labor, Material, and ODC) | |
| | CLIN 1004: Ordering Period 1 (CPFF) | | CLIN 2003: Ordering Period 2 (CPFF) | | CLIN 3003: Ordering Period 3 (CPFF) | | CLIN 4003: Ordering Period 4 (CPFF) | | CLIN 5001: Ordering Period 5 (CPFF) | | CLIN 6001: Ordering Period 6 (CPFF) |
| Total Proposed Cost | | $0.00 | | $0.00 | | $0.00 | | $0.00 | | $0.00 | | $0.00 |
| Total Proposed COM | | $0.00 | | $0.00 | | $0.00 | | $0.00 | | $0.00 | | $0.00 |
| Total Proposed Fee | | $0.00 | | $0.00 | | $0.00 | | $0.00 | | $0.00 | | $0.00 |
| Total Proposed Price | | $0.00 | | $0.00 | | $0.00 | | $0.00 | | $0.00 | | $0.00 |
Cost Format B_PRIME Rates
| Notes: |
| 1. The format of this worksheet may be revised as required to be consistent with the contractor's approved accounting system to include, but not limited to, inserting additional labor categories and revising the indirect rate structure. |
| 2. The Prime Offeror shall propose labor rates and add-on factors in the yellow-highlighted cells below. All proposed labor rates shall be rounded to two (2) decimal places. All proposed indirect rates and add-on factors are limited to four (4) decimal places. |
| 3. The Prime Offeror shall ensure the rate and add-on factor cells below are linked correctly to the relevant CPFF, CPIF, and CRNF rate cells on the prime's Cost Format A worksheets. |
| 4. The Prime Offeror shall provide definitions of the labor categories and add-on factors in the 'Cost Format B_PRIME Rate Desc' worksheet. |
| Proposed Direct Labor Rates | | | | | | |
| Basic | OP I | OP II | OP III | OP IV | OP V | OP VI |
| Labor Category | Hourly Rate | Hourly Rate | Hourly Rate | Hourly Rate | Hourly Rate | Hourly Rate | Hourly Rate |
| Labor Category 1: [INSERT LABOR CATEGORY NAME HERE] | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| Labor Category 2: [INSERT LABOR CATEGORY NAME HERE] | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| Labor Category 3: [INSERT LABOR CATEGORY NAME HERE] | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| Labor Category 4: [INSERT LABOR CATEGORY NAME HERE] | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| Labor Category 5: [INSERT LABOR CATEGORY NAME HERE] | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| Labor Category 6: [INSERT LABOR CATEGORY NAME HERE] | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| Labor Category 7: [INSERT LABOR CATEGORY NAME HERE] | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| Labor Category 8: [INSERT LABOR CATEGORY NAME HERE] | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| Labor Category 9: [INSERT LABOR CATEGORY NAME HERE] | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| Labor Category 10: [INSERT LABOR CATEGORY NAME HERE] | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| Labor Category 11: [INSERT LABOR CATEGORY NAME HERE] | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| Labor Category 12: [INSERT LABOR CATEGORY NAME HERE] | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| Labor Category 13: [INSERT LABOR CATEGORY NAME HERE] | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| Proposed Labor Add-on Factors | | | | | | |
| Basic | OP I | OP II | OP III | OP IV | OP V | OP VI |
| Proposed Add-on Factor (Fringe) | | | | | | | |
| Proposed Add-on Factor (Overhead) | | | | | | | |
| Proposed Add-on Factor (G&A) | | | | | | | |
| Proposed Add-on Factor (COM) | | | | | | | |
| Proposed Add-on Factor (R&D Fee) | | | | | | | |
| Proposed Add-on Factor (Fee) | | | | | | | |
| Proposed Material Add-on Factors | | | | | | |
| Basic | OP I | OP II | OP III | OP IV | OP V | OP VI |
| Proposed Add-on Factor (Overhead) | | | | | | | |
| Proposed Add-on Factor (G&A) | | | | | | | |
| Proposed Add-on Factor (COM) | | | | | | | |
| Proposed Add-on Factor (R&D Fee) | | | | | | | |
| Proposed Add-on Factor (Non-R&D Fee) | | | | | | | |
| Proposed Travel Add-on Factors | | | | | | |
| Basic | OP I | OP II | OP III | OP IV | OP V | OP VI |
| Proposed Add-on Factor (Overhead) | | | | | | | |
| Proposed Add-on Factor (G&A) | | | | | | | |
| Proposed Add-on Factor (COM) | | | | | | | |
Cost Format B_PRIME Rate Desc
| Notes: |
| 1. The format of this worksheet may be revised as necessary to accommodate additional labor categories as proposed by the Prime Offeror. |
| 2. The Prime Offeror shall enter the labor category names in Column B as it pertains to the Prime Offeror's proposed labor for cost-type CLINs. |
| 3. The Prime Offeror shall provide definitions of the labor categories and add-on factors in Column C. An example is provided in cell D10 and E11. |
| 4. The Prime Offeror shall ensure the labor categories identified below are reflected on the Cost Format A tabs to provide a correlation for proposed labor. |
Labor Category and Add-on Factor Descriptions Example Labor Category Example Description
| Labor Category | Description | | |
| Labor Category 1: [INSERT LABOR CATEGORY NAME HERE] | | Quality Assurance Specialist | Ensures compliance with U.S. export regulations. This position will manage the approval and documentation of exports of all components, data, and technical information. They will work closely with the Contracts Administrator and Program Manager to ensure that all international shipments, technical data exchanges, and communications comply with ITAR and EAR requirements. Additionally, they will monitor and enforce export licenses and ensure that proper reporting is conducted. |
| Labor Category 2: [INSERT LABOR CATEGORY NAME HERE] | | | |
| Labor Category 3: [INSERT LABOR CATEGORY NAME HERE] | | | |
| Labor Category 4: [INSERT LABOR CATEGORY NAME HERE] | | | |
| Labor Category 5: [INSERT LABOR CATEGORY NAME HERE] | | | |
| Labor Category 6: [INSERT LABOR CATEGORY NAME HERE] | | | |
| Labor Category 7: [INSERT LABOR CATEGORY NAME HERE] | | | |
| Labor Category 8: [INSERT LABOR CATEGORY NAME HERE] | | | |
| Labor Category 9: [INSERT LABOR CATEGORY NAME HERE] | | | |
| Labor Category 10: [INSERT LABOR CATEGORY NAME HERE] | | | |
| Labor Category 11: [INSERT LABOR CATEGORY NAME HERE] | | | |
| Labor Category 12: [INSERT LABOR CATEGORY NAME HERE] | | | |
| Labor Category 13: [INSERT LABOR CATEGORY NAME HERE] | | | |
| Add-On Factor | Description | Identify the Base the Factor is Applied to: | Example Description: |
| Fringe | | Example: The base for Fringe is total direct labor cost. | Includes employee health insurance, retirement plans, and paid time off |
| Overhead | | | |
| G&A | | | |
| COM | | | |
| Fee | | | |
Cost Format D_NRE SUB
| Notes: |
| 1. The format of this worksheet may be revised as required to be consistent with the major subcontractor's approved accounting system. |
| 2. The Prime Offer shall have the major subcontractor propose labor hours, material costs, and other direct costs in the yellow-highlighted cells below. |
| 3. The Prime Offeror shall ensure the yellow-highlighted rate cells below are linked correctly from the relevant labor rate and add-on factors in the 'Cost Format B_SUB Rates' worksheet. |
| 4. The proposed factors will be applied to the total proposed labor hours and material cost. |
| 5. Definitions of the labor categories and add-on factors are included in the 'Cost Format B_SUB Rate Desc' worksheet. |
| 6. Each CPFF Cost, COM and Fee shall be rounded to the nearest whole dollar. |
| CLINs 0001, 1001: CPFF | Proposed Prices (Labor) | | | Proposed Prices (Labor) | | |
| 0001: HH-60W Degraded Visual Environment System Research, Development, Test, and Evaluation (RDT&E) | | | 1001: HH-60W Degraded Visual Environment System Research, Development, Test, and Evaluation (RDT&E) | | |
| Labor Category | Hours | Rates | Cost | Hours | Rates | Cost |
| Labor Category 1: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 2: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 3: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 4: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 5: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 6: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 7: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 8: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 9: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 10: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 11: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 12: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| Labor Category 13: [INSERT LABOR CATEGORY NAME HERE] | | $0.00 | $0.00 | | $0.00 | $0.00 |
| TOTAL HOURS/COST | 0 | | $0.00 | 0 | | $0.00 |
| Base | Rates | Cost | Base | Rates | Cost |
| Proposed Add-on Factor (Fringe) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 | | | $0.00 |
| Total Proposed COM | | | $0.00 | | | $0.00 |
| Total Proposed Fee | | | $0.00 | | | $0.00 |
| Total Proposed Price | | | $0.00 | | | $0.00 |
| CLINs 0001, 1001: CPFF | Proposed Prices (Material) | | | Proposed Prices (Material) | | |
| 0001: HH-60W Degraded Visual Environment System Research, Development, Test, and Evaluation (RDT&E) | | | 1001: HH-60W Degraded Visual Environment System Research, Development, Test, and Evaluation (RDT&E) | | |
| Base | Rates | Cost | Base | Rates | Cost |
| Total Proposed Material Cost | | | | | | |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 | | | $0.00 |
| Total Proposed COM | | | $0.00 | | | $0.00 |
| Total Proposed Fee | | | $0.00 | | | $0.00 |
| Total Proposed Price | | | $0.00 | | | $0.00 |
| CLINs 0001, 1001: CPFF | Proposed Prices (Other Direct Cost) | | | Proposed Prices (Other Direct Cost) | | |
| 0001: HH-60W Degraded Visual Environment System Research, Development, Test, and Evaluation (RDT&E) | | | 1001: HH-60W Degraded Visual Environment System Research, Development, Test, and Evaluation (RDT&E) | | |
| Base | Rates | Cost | Base | Rates | Cost |
| Total Proposed Other Direct Cost (ODC) | | | | | | |
| Proposed Add-on Factor (Overhead) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (G&A) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (COM) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Proposed Add-on Factor (Fee) | $0.00 | - 0 | $0.00 | $0.00 | - 0 | $0.00 |
| Total Proposed Cost | | | $0.00 | | | $0.00 |
| Total Proposed COM | | | $0.00 | | | $0.00 |
| Total Proposed Fee | | | $0.00 | | | $0.00 |
| Total Proposed Price | | | $0.00 | | | $0.00 |
| CLINs 0001, 1001: CPFF | Proposed Prices (Labor, Material, and ODC) | | Proposed Prices (Labor, Material, and ODC) | |
| | CLIN 0001: Basic Period (CPFF) | | CLIN 1001: Ordering Period 1 (CPFF) |
| Total Proposed Cost | | $0.00 | | $0.00 |
| Total Proposed COM | | $0.00 | | $0.00 |
| Total Proposed Fee | | $0.00 | | $0.00 |
| Total Proposed Price | | $0.00 | | $0.00 |
Cost Format D_Proto-Kit SUB
| Notes: |
| 1. The format of this worksheet may be revised as required to be consistent with the major subcontractor's approved accounting system. |
| 2. The Prime Offer shall have the major subcontractor propose labor hours, material costs, and other direct costs in the yellow-highlighted cells below. |