RFP Attachment 7_Total Resources Volume_19 Mar 2026.xlsx

XLSX spreadsheet 1 MB Posted

Attached to
Common Armament Tester for Fighter (CAT-F)
Solicitation number
FA8533-25-R-0002
Issued by

About this file

This Excel-based Bill of Materials (BOM) template provides guidance for offerors responding to the Common Armament Tester for Fighters (CAT-F) RFP (FA8533-25-R-0002). The document establishes standardized formatting requirements for labor and Other Direct Cost (ODC) submissions across multiple Contract Line Items (CLINs) covering five government fiscal years.

The labor summary template requires offerors to detail total labor hours by task, work breakdown structure (WBS) elements, and labor categories, broken down by government fiscal year. Labor categories span engineering disciplines (senior engineers, software engineers, technicians, machinists, junior engineers, test engineers) organized across WBS elements including CAT-F Prime Mission Equipment, System Engineering, Design Demonstration, and support activities such as Environmental Testing, Software Development, Integration and Test Reviews, Developmental and Operational Testing, Manufacturing, and Depot Maintenance. The ODC section requires itemization of travel costs (airfare, per diem, rental cars, hotel, mileage, taxes) and non-travel ODCs by CLIN and contract year. Offerors must submit these summaries in Excel format to facilitate government evaluation of resource realism and reasonableness. The template applies to multiple CLINs (0001-0006 for prototype design and digital development phases; 1001-1006 for Engineering and Manufacturing Development; 2001-2005 for production phases; 3001-3004 and 4009-4010 for additional production and support options) covering F-16, F-15, and A-10 O-Level and I-Level handheld/pre-load testers and fault isolation testers, with supporting activities including design demonstration, technical data delivery, government testing support, and travel requirements.

View the file

Other files

File Type Posted
13 May 2026_Industry Questions and Answers.xlsx XLSX spreadsheet
FA8532-25-R-0002-0007.pdf PDF
RFP Attachment 4_Sections L-900_L-901_M-900_M-901_5 May 2026.pdf PDF
7 May 2026_Industry Questions and Answers.xlsx XLSX spreadsheet
RFP Attachment 3_STATEMENT OF OBJECTIVES_5 May 26.pdf PDF
FA8533-25-R-0002-0006.pdf PDF
Industry Questions and Answers_1 May 2026.xlsx XLSX spreadsheet
FA8533-25-R-0002-0005.pdf PDF
FA8533-25-R-0002-0004.pdf PDF
RFP Attachment 4_Sections L-900_L-901_M-900_M-901_14 April 2026.pdf PDF
RFP Attachment 3_STATEMENT OF OBJECTIVES 31 Mar 2026_RFP Amend 0003.pdf PDF
Industry Questions and Answers_22 April 2026.xlsx XLSX spreadsheet
FA8533-25-R-0002-0003.pdf PDF
RFP Attachment 9_CDRLs_25 Feb 2026.pdf PDF
RFP Attachment 4_Sections L-900_ L-901_ M-900_M-901_09 Apr 2026.pdf PDF
RFP Attachment 3_STATEMENT OF OBJECTIVES 31 Mar 2026.pdf PDF
RFP Attachment 8_Cross Reference Matrix_27 Feb 2026.pdf PDF
RFP Attachment 6_Excel Cost Model_20 Mar 2026.xlsx XLSX spreadsheet
RFP Attachment 15_DAF Contracting Compass Parts_27 Mar 2026.pdf PDF
Industry Questions with Answers_06 Mar 2026.xlsx XLSX spreadsheet
Questions to Industry_25 Feb 2026.pdf PDF
RFP Attachment 6 Excel Cost Model_15 Sep 2025.xlsx XLSX spreadsheet
RFP Attachment 11_Technical Manual Contract Requirements (TMCR)_26 Aug 2025.pdf PDF
RFP Attachment 6 Excel Cost Model_15 Sep 2025.xlsx XLSX spreadsheet
RFP Attachment 11_Technical Manual Contract Requirements (TMCR)_26 Aug 2025.docx DOCX document
RFP Attachment 4_Sections L-900_ L-901_ M-900_M-901_17 Feb 2026.pdf PDF
RFP Attachment 2_CAT-F Safety Plan_26 Aug 2025.pdf PDF
RFP Attachment 3_STATEMENT OF OBJECTIVES_10 Sep 2025.pdf PDF
RFP Attachment 6 Excel Cost Model_15 Sep 2025.xlsx XLSX spreadsheet
RFP Attachment 11_Technical Manual Contract Requirements (TMCR)_26 Aug 2025.docx DOCX document
RFP Amendment_FA8533-25-R-0002-0002.pdf PDF
RFP Attachment 9_CDRLs_05 Feb 2025.pdf PDF
RFP Amendment_FA8533-25-R-0002-0001.pdf PDF
Industry Questions with Answers_04 Sep 2025.xlsx XLSX spreadsheet
RFP Attachment 9_CDRLs.pdf PDF
RFP Attachment 14_Additional CDRLs.pdf PDF
RFP Attachment 10_Preaward Survey.pdf PDF
RFP Attachment 6 Excel Cost Model.xlsx XLSX spreadsheet
RFP Attachment 13_AFMC 158_Packaging Requirements.pdf PDF
RFP Attachment 4_Sections L 900_L 901_ M 900_M 901.pdf PDF
RFP_FA8533-25-R-0002.pdf PDF
RFP Attachment 3_STATEMENT OF OBJECTIVES.pdf PDF
RFP Attachment 8_Cross Reference Matrix.pdf PDF
RFP Attachment 7_Total Resources Volume.xlsx XLSX spreadsheet
RFP Attachment 2_CAT-F Safety Plan.pdf PDF
RFP Attachment 5_GFP List.xlsx XLSX spreadsheet
RFP Attachment 11_Techincal Manual Contract Requirements (TMCR).docx DOCX document
RFP Attachment 1_DD254.pdf PDF
RFP Attachment 12_DD1653_ Transportation Data.pdf PDF
RFP Attachment 15_ Intellectual Property Rights.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BOE Material Summary Offeror's are required to provide a Material BOE summary that clearly lists the types and quantities of material resources proposed regardless of source (prime and subcontractors) by the SOW and CWBS time phased by Government Fiscal Year. Since the Technical and Schedule Evaluators will be primarily concerned with soundness of an offeror’s approach, including the realism (for cost-type CLINs) and reasonableness of the types & quantities of materials, proposed unit prices and extended cost should be a sanitized version of the Priced Bill of Material, which offerors must provide in Volume IV Cost/Price. This summary must be provided in Excel to simplify manipulation of the data during evaluation. Otherwise contractor format is acceptable.

SAMPLE-Labor Summary

An Employee of:Total of All Government Fiscal YearsLabor CategoryBOE Reference3.1 EMD, System Design
3.1.1 CAT-F Prime Mission Equipment3.1.2 System Engineering3.1.3 Reserved3.1.4 Technology Readiness Assessment3.1.5 Critical Technology Demonstration3.1.6 Program Protection Plan3.1.7 Data Rights3.1.8 Configuration Management3.1.9 Program Management3.1.10 Risk Management3.1.11 Subcontractor/ Supplier Management3.1.12 Data Management
Notional CWBS3.1.1.1 CAT-F External Controls and Sustaining Engineering Planning3.1.1.2 CAT-F Software Design3.1.2.1 Human Factors Engineering3.1.2.2 Interface Control Working Group3.1.2.3 Technical Performance Measures3.1.2.4 System Engineering Management Plan3.1.6.1 Inspection and Audit3.1.6.2 Cybersecurity3.1.6.3 Anti-Tamper3.1.6.4 Security3.1.6.5 Security Classification Data3.1.7.1 Unlimited Rights3.1.7.2 Government Purpose Rights3.1.7.3 Limited or Restricted Rights3.1.8.1 Data Accession List3.1.9.1 Contractor Integrated Performance Management3.1.9.2 Integrated Baseline Reviews3.1.9.3 Status Reports3.1.9.4 Contract Funds Status Report3.1.9.5 Integrated Master Schedule3.1.12.1 Data Repository3.1.12.2 Government Furnished Data3.1.12.3 Acquired or Furnished Data
3.1.1.2.1 Software Functional Qualification Test3.1.6.5.1 Safeguarding Classified Material3.1.12.2.1 Government Furnished Documentation3.1.12.2.2 Government Furnished Software3.1.12.3.1 Contractor Acquired Property3.1.12.3.2 Government Furnished Property and Services3.1.12.3.3 Government Property and Loss of GP Definition3.1.12.3.4 Reporting Loss of Government Property3.1.12.3.5 GFE/ GFP/ Management/ Govt Furnished Information
WBS/Item NumberWBS Description
1.0Automatic Test System
1.1Common Armament Tester for Fighters Prime Mission Product (CAT-F PMP)
1.1.1CAT-F O-Level System
1.1.1.1CAT-F Subsystem 1…n (specify)1.1.1 Total hours204
1.1.1.1.1SS1, Component 1
ABC Company1.1.1.1.1.1DesignSenior Engineer10
ABC Company1.1.1.1.1.2FabricateTechnician25
ABC CompanyJunior Engineer80
ABC CompanyMachinist15
ABC CompanyElectrical Engineer20
ABC Company1.1.1.1.1.3IntegrateSenior Engineer3
ABC CompanySystems Engineer20
ABC CompanyTechnician17
ABC Company1.1.1.1.1.4TestSenior Engineer4
Test Engineer10
1.1.1.1.2SS1, Component 2...n
1.1.1.1.#SIMILAR BREAKDOWN TO 1.1.1.1 EXAMPLE
1.1.2CAT-F O-Level Software Release 1…n (specify)1.1.2 Total hours8050080
1.1.2.1CSCI 1
ABC Company1.1.2.1.1DesignSoftware Engineer20300
ABC Company1.1.2.1.2FabricateSoftware Engineer20100
ABC Company1.1.2.1.3IntegrateSoftware Engineer20100
ABC Company1.1.2.1.4TestSoftware Engineer2080
1.1.3CAT-F I-Level System
1.1.3.1CAT-F Subsystem 1…n (specify)1.1.1 Total hours204
1.1.3.1.1SS1, Component 1
ABC Company1.1.3.1.1.1DesignSenior Engineer10
ABC Company1.1.3.1.1.2FabricateTechnician25
ABC CompanyJunior Engineer80
ABC CompanyMachinist15
ABC CompanyElectrical Engineer20
ABC Company1.1.3.1.1.3IntegrateSenior Engineer3
ABC CompanySystems Engineer20
ABC CompanyTechnician17
ABC Company1.1.3.1.1.4TestSenior Engineer4
Test Engineer10
1.1.3.1.2SS1, Component 2...n
1.1.3.1.#SIMILAR BREAKDOWN TO 1.1.3.1 EXAMPLE
1.1.4CAT-F I-Level Software Release 1…n (specify)1.1.2 Total hours8050080
1.1.4.1CSCI 1
ABC Company1.1.4.1.1DesignSoftware Engineer20300
ABC Company1.1.4.1.2FabricateSoftware Engineer20100
ABC Company1.1.4.1.3IntegrateSoftware Engineer20100
ABC Company1.1.4.1.4TestSoftware Engineer2080
1.1.5CAT-F Prime Mission Product Integration, Assembly, Test, and Checkout
1.2Platform Integration, Assembly, Test, and Checkout (Trial Kit Install)
1.3Systems Engineering (SE)
1.4Program Management (PM)
1.5System Test and Eval (ST&E)
1.5.1Developmental Test and Evaluation (DT&E)
1.5.2Operational Test and Evaluation (OT&E)
1.5.3Mock-ups/System Integration Labs (SILs)
1.5.4Test and Evaluation Support
1.5.5Test Facilities
1.6Training
1.6.1Equipment
1.6.2Services
1.6.3Facilities
1.7Data
1.7.1Technical Publications
1.7.2Engineering Data
1.7.3Management Data
1.7.4Support Data
1.7.5Data Repository
1.8Peculiar Support Equipment (PSE)
1.8.1Test and Measurement Equipment
1.8.2Support and Handling Equipment
1.9Common Support Equipment (CSE)
1.9.1Test and Measurement Equipment
1.9.2Support and Handling Equipment
1.10Initial Repair Parts
1.11Anti Tamper/Program Protection
1.11.1Plan
1.11.2Implementation/Test

ODCs Program ODCs

This document provides a summary of the Other Direct Costs (ODCs) required for the successful execution of the tasks outlined in the Statement of Work (SOW) for the CAT-F acquisition. The types and quantities of ODCs proposed are based on thorough understanding of the requirements and a proven technical approach. The ODC summary includes all ODCs, whether sourced by the prime contractor or subcontractors, and is time-phased by Government Contract Year (GCY). This summary must be provided in Excel to simplify manipulation of the data during evaluation. Otherwise contractor format is acceptable.

ODC Travel
Travel InfoAirfarePer DiemRental CarMileageHotelLodging TaxTotal
CLINContract YearDescriptionDest. DescriptionPeopleDaysTripsQtyRateCostQtyRateCostQtyRateCostQtyRateCostQtyRateCostQtyRateCostCost
Approved Gov Trip to XXXX to support Task. (Number of people, Airfare, Rental Car, Hotel…..)From XXXX to XXXX$0
$0
$0
$0
$0
$0
$0
$0
Travel$0
Total$0
Non-Travel ODCs
CLINContract YearDescriptionCategoryEstimated CostNotes
CLINs with possible ODCs
CLINTitle
0001F-16 O-Level Handheld/Pre-load Tester Prototype Design and Digital Development
1001F16 O-level Handheld/Preload Tester Engineering and Manufacturing Development
0002F-15 O-Level Handheld/Pre-load Tester Prototype Design and Digital Development
0003A-10 O-Level Handheld/Pre-load Tester Prototype Design and Digital Development
0004F-16 I-Level Fault Isolation Tester Design and Digital Development
0005F-15 I-Level Fault Isolation Tester Design and Digital Development
0006A-10 I-Level Fault Isolation Tester Design and Digital Development
0014Design Demonstration (Labor-Not Travel)
0015Travel
1002F-15 O-level Handheld/Preload Tester Engineering and Manufacturing Development
1003A-10 O-level Handheld/Preload Tester Engineering and Manufacturing Development
1004F-16 I-Level Fault Isolation Tester Engineering and Manufacturing Development
1005F-16 I-Level Fault Isolation Tester Engineering and Manufacturing Development
1006A-10 I-Level Fault Isolation Tester Engineering and Manufacturing Development
1011Support Government Testing
1012Travel
1015Technical Data
2001F-15 O-Level Handheld/Pre-load Tester Engineering and Manufacturing Development
2002A-10 O-Level Handheld/Pre-load Tester Engineering and Manufacturing Development
2003F-16 I-Level Fault Isolation Tester Engineering and Manufacturing Development
2004F-15 I-Level Fault Isolation Tester Engineering and Manufacturing Development
2005A-10 I-Level Fault Isolation Tester Engineering and Manufacturing Development
2013Support Government Testing
2014Travel
3001A-10 O-Level Handheld/Preload Tester Engineering and Manufacturing Development
3002F-16 I-Level Fault Isolation Tester Engineering and Manufacturing Development
3003F-15 I-Level Fault Isolation Tester Engineering and Manufacturing Development
3004A-10 I-Level Fault Isolation Tester Engineering and Manufacturing Development
3013Support Government Testing
3014Travel
4009Support Government Testing
4010Travel

CLIN 0001 BOE Labor Summary

An Employee of:Total of All Government Fiscal YearsLabor CategoryBOE Reference3.1 EMD, System Design
3.1.1 CAT-F Prime Mission Equipment3.1.2 System Engineering3.1.3 Reserved3.1.4 Technology Readiness Assessment3.1.5 Critical Technology Demonstration3.1.6 Program Protection Plan3.1.7 Data Rights3.1.8 Configuration Management3.1.9 Program Management3.1.10 Risk Management3.1.11 Subcontractor/ Supplier Management3.1.12 Data Management
Notional CWBS3.1.1.1 CAT-F External Controls and Sustaining Engineering Planning3.1.1.2 CAT-F Software Design3.1.2.1 Human Factors Engineering3.1.2.2 Interface Control Working Group3.1.2.3 Technical Performance Measures3.1.2.4 System Engineering Management Plan3.1.6.1 Inspection and Audit3.1.6.2 Cybersecurity3.1.6.3 Anti-Tamper3.1.6.4 Security3.1.6.5 Security Classification Data3.1.7.1 Unlimited Rights3.1.7.2 Government Purpose Rights3.1.7.3 Limited or Restricted Rights3.1.8.1 Data Accession List3.1.9.1 Contractor Integrated Performance Management3.1.9.2 Integrated Baseline Reviews3.1.9.3 Status Reports3.1.9.4 Contract Funds Status Report3.1.9.5 Integrated Master Schedule3.1.12.1 Data Repository3.1.12.2 Government Furnished Data3.1.12.3 Acquired or Furnished Data
3.1.1.2.1 Software Functional Qualification Test3.1.6.5.1 Safeguarding Classified Material3.1.12.2.1 Government Furnished Documentation3.1.12.2.2 Government Furnished Software3.1.12.3.1 Contractor Acquired Property3.1.12.3.2 Government Furnished Property and Services3.1.12.3.3 Government Property and Loss of GP Definition3.1.12.3.4 Reporting Loss of Government Property3.1.12.3.5 GFE/ GFP/ Management/ Govt Furnished Information
WBS/Item NumberWBS Description
1.0Automatic Test System
1.1Common Armament Tester for Fighters Prime Mission Product (CAT-F PMP)
1.1.1CAT-F O-Level System
1.1.1.1CAT-F Subsystem 1…n (specify)
1.1.1.1.1SS1, Component 1
1.1.1.1.1.1Design
1.1.1.1.1.2Fabricate
1.1.1.1.1.3Integrate
1.1.1.1.1.4Test
1.1.1.1.2SS1, Component 2...n
1.1.1.1.#SIMILAR BREAKDOWN TO 1.1.1.1 EXAMPLE
1.1.2CAT-F O-Level Software Release 1…n (specify)
1.1.2.1CSCI 1
1.1.2.1.1Design
1.1.2.1.2Fabricate
1.1.2.1.3Integrate
1.1.2.1.4Test
1.1.3CAT-F I-Level System
1.1.3.1CAT-F Subsystem 1…n (specify)
1.1.3.1.1SS1, Component 1
1.1.3.1.1.1Design
1.1.3.1.1.2Fabricate
1.1.3.1.1.3Integrate
1.1.3.1.1.4Test
1.1.3.1.2SS1, Component 2...n
1.1.3.1.#SIMILAR BREAKDOWN TO 1.1.3.1 EXAMPLE
1.1.4CAT-F I-Level Software Release 1…n (specify)
1.1.4.1CSCI 1
1.1.4.1.1Design
1.1.4.1.2Fabricate
1.1.4.1.3Integrate
1.1.4.1.4Test
1.1.5CAT-F Prime Mission Product Integration, Assembly, Test, and Checkout
1.2Platform Integration, Assembly, Test, and Checkout (Trial Kit Install)
1.3Systems Engineering (SE)
1.4Program Management (PM)
1.5System Test and Eval (ST&E)
1.5.1Developmental Test and Evaluation (DT&E)
1.5.2Operational Test and Evaluation (OT&E)
1.5.3Mock-ups/System Integration Labs (SILs)
1.5.4Test and Evaluation Support
1.5.5Test Facilities
1.6Training
1.6.1Equipment
1.6.2Services
1.6.3Facilities
1.7Data
1.7.1Technical Publications
1.7.2Engineering Data
1.7.3Management Data
1.7.4Support Data
1.7.5Data Repository
1.8Peculiar Support Equipment (PSE)
1.8.1Test and Measurement Equipment
1.8.2Support and Handling Equipment
1.9Common Support Equipment (CSE)
1.9.1Test and Measurement Equipment
1.9.2Support and Handling Equipment
1.10Initial Repair Parts
1.11Anti Tamper/Program Protection
1.11.1Plan
1.11.2Implementation/Test
An Employee of:Government Fiscal Year 1Labor CategoryBOE Reference3.1 EMD, System Design
3.1.1 CAT-F Prime Mission Equipment3.1.2 System Engineering3.1.3 Reserved3.1.4 Technology Readiness Assessment3.1.5 Critical Technology Demonstration3.1.6 Program Protection Plan3.1.7 Data Rights3.1.8 Configuration Management3.1.9 Program Management3.1.10 Risk Management3.1.11 Subcontractor/ Supplier Management3.1.12 Data Management
Notional CWBS3.1.1.1 CAT-F External Controls and Sustaining Engineering Planning3.1.1.2 CAT-F Software Design3.1.2.1 Human Factors Engineering3.1.2.2 Interface Control Working Group3.1.2.3 Technical Performance Measures3.1.2.4 System Engineering Management Plan3.1.6.1 Inspection and Audit3.1.6.2 Cybersecurity3.1.6.3 Anti-Tamper3.1.6.4 Security3.1.6.5 Security Classification Data3.1.7.1 Unlimited Rights3.1.7.2 Government Purpose Rights3.1.7.3 Limited or Restricted Rights3.1.8.1 Data Accession List3.1.9.1 Contractor Integrated Performance Management3.1.9.2 Integrated Baseline Reviews3.1.9.3 Status Reports3.1.9.4 Contract Funds Status Report3.1.9.5 Integrated Master Schedule3.1.12.1 Data Repository3.1.12.2 Government Furnished Data3.1.12.3 Acquired or Furnished Data
3.1.1.2.1 Software Functional Qualification Test3.1.6.5.1 Safeguarding Classified Material3.1.12.2.1 Government Furnished Documentation3.1.12.2.2 Government Furnished Software3.1.12.3.1 Contractor Acquired Property3.1.12.3.2 Government Furnished Property and Services3.1.12.3.3 Government Property and Loss of GP Definition3.1.12.3.4 Reporting Loss of Government Property3.1.12.3.5 GFE/ GFP/ Management/ Govt Furnished Information
WBS/Item NumberWBS Description
1.0Automatic Test System
1.1Common Armament Tester for Fighters Prime Mission Product (CAT-F PMP)
1.1.1CAT-F O-Level System
1.1.1.1CAT-F Subsystem 1…n (specify)
1.1.1.1.1SS1, Component 1
1.1.1.1.1.1Design
1.1.1.1.1.2Fabricate
1.1.1.1.1.3Integrate
1.1.1.1.1.4Test
1.1.1.1.2SS1, Component 2...n
1.1.1.1.#SIMILAR BREAKDOWN TO 1.1.1.1 EXAMPLE
1.1.2CAT-F O-Level Software Release 1…n (specify)
1.1.2.1CSCI 1
1.1.2.1.1Design
1.1.2.1.2Fabricate
1.1.2.1.3Integrate
1.1.2.1.4Test
1.1.3CAT-F I-Level System
1.1.3.1CAT-F Subsystem 1…n (specify)
1.1.3.1.1SS1, Component 1
1.1.3.1.1.1Design
1.1.3.1.1.2Fabricate
1.1.3.1.1.3Integrate
1.1.3.1.1.4Test
1.1.3.1.2SS1, Component 2...n
1.1.3.1.#SIMILAR BREAKDOWN TO 1.1.3.1 EXAMPLE
1.1.4CAT-F I-Level Software Release 1…n (specify)
1.1.4.1CSCI 1
1.1.4.1.1Design
1.1.4.1.2Fabricate
1.1.4.1.3Integrate
1.1.4.1.4Test
1.1.5CAT-F Prime Mission Product Integration, Assembly, Test, and Checkout
1.2Platform Integration, Assembly, Test, and Checkout (Trial Kit Install)
1.3Systems Engineering (SE)
1.4Program Management (PM)
1.5System Test and Eval (ST&E)
1.5.1Developmental Test and Evaluation (DT&E)
1.5.2Operational Test and Evaluation (OT&E)
1.5.3Mock-ups/System Integration Labs (SILs)
1.5.4Test and Evaluation Support
1.5.5Test Facilities
1.6Training
1.6.1Equipment
1.6.2Services
1.6.3Facilities
1.7Data
1.7.1Technical Publications
1.7.2Engineering Data
1.7.3Management Data
1.7.4Support Data
1.7.5Data Repository
1.8Peculiar Support Equipment (PSE)
1.8.1Test and Measurement Equipment
1.8.2Support and Handling Equipment
1.9Common Support Equipment (CSE)
1.9.1Test and Measurement Equipment
1.9.2Support and Handling Equipment
1.10Initial Repair Parts
1.11Anti Tamper/Program Protection
1.11.1Plan
1.11.2Implementation/Test
An Employee of:Government Fiscal Year 2Labor CategoryBOE Reference3.1 EMD, System Design
3.1.1 CAT-F Prime Mission Equipment3.1.2 System Engineering3.1.3 Reserved3.1.4 Technology Readiness Assessment3.1.5 Critical Technology Demonstration3.1.6 Program Protection Plan3.1.7 Data Rights3.1.8 Configuration Management3.1.9 Program Management3.1.10 Risk Management3.1.11 Subcontractor/ Supplier Management3.1.12 Data Management
Notional CWBS3.1.1.1 CAT-F External Controls and Sustaining Engineering Planning3.1.1.2 CAT-F Software Design3.1.2.1 Human Factors Engineering3.1.2.2 Interface Control Working Group3.1.2.3 Technical Performance Measures3.1.2.4 System Engineering Management Plan3.1.6.1 Inspection and Audit3.1.6.2 Cybersecurity3.1.6.3 Anti-Tamper3.1.6.4 Security3.1.6.5 Security Classification Data3.1.7.1 Unlimited Rights3.1.7.2 Government Purpose Rights3.1.7.3 Limited or Restricted Rights3.1.8.1 Data Accession List3.1.9.1 Contractor Integrated Performance Management3.1.9.2 Integrated Baseline Reviews3.1.9.3 Status Reports3.1.9.4 Contract Funds Status Report3.1.9.5 Integrated Master Schedule3.1.12.1 Data Repository3.1.12.2 Government Furnished Data3.1.12.3 Acquired or Furnished Data
3.1.1.2.1 Software Functional Qualification Test3.1.6.5.1 Safeguarding Classified Material3.1.12.2.1 Government Furnished Documentation3.1.12.2.2 Government Furnished Software3.1.12.3.1 Contractor Acquired Property3.1.12.3.2 Government Furnished Property and Services3.1.12.3.3 Government Property and Loss of GP Definition3.1.12.3.4 Reporting Loss of Government Property3.1.12.3.5 GFE/ GFP/ Management/ Govt Furnished Information
WBS/Item NumberWBS Description
1.0Automatic Test System
1.1Common Armament Tester for Fighters Prime Mission Product (CAT-F PMP)
1.1.1CAT-F O-Level System
1.1.1.1CAT-F Subsystem 1…n (specify)
1.1.1.1.1SS1, Component 1
1.1.1.1.1.1Design
1.1.1.1.1.2Fabricate
1.1.1.1.1.3Integrate
1.1.1.1.1.4Test
1.1.1.1.2SS1, Component 2...n
1.1.1.1.#SIMILAR BREAKDOWN TO 1.1.1.1 EXAMPLE
1.1.2CAT-F O-Level Software Release 1…n (specify)
1.1.2.1CSCI 1
1.1.2.1.1Design
1.1.2.1.2Fabricate
1.1.2.1.3Integrate
1.1.2.1.4Test
1.1.3CAT-F I-Level System
1.1.3.1CAT-F Subsystem 1…n (specify)
1.1.3.1.1SS1, Component 1
1.1.3.1.1.1Design
1.1.3.1.1.2Fabricate
1.1.3.1.1.3Integrate
1.1.3.1.1.4Test
1.1.3.1.2SS1, Component 2...n
1.1.3.1.#SIMILAR BREAKDOWN TO 1.1.3.1 EXAMPLE
1.1.4CAT-F I-Level Software Release 1…n (specify)
1.1.4.1CSCI 1
1.1.4.1.1Design
1.1.4.1.2Fabricate
1.1.4.1.3Integrate
1.1.4.1.4Test
1.1.5CAT-F Prime Mission Product Integration, Assembly, Test, and Checkout
1.2Platform Integration, Assembly, Test, and Checkout (Trial Kit Install)
1.3Systems Engineering (SE)
1.4Program Management (PM)
1.5System Test and Eval (ST&E)
1.5.1Developmental Test and Evaluation (DT&E)
1.5.2Operational Test and Evaluation (OT&E)
1.5.3Mock-ups/System Integration Labs (SILs)
1.5.4Test and Evaluation Support
1.5.5Test Facilities
1.6Training
1.6.1Equipment
1.6.2Services
1.6.3Facilities
1.7Data
1.7.1Technical Publications
1.7.2Engineering Data
1.7.3Management Data
1.7.4Support Data
1.7.5Data Repository
1.8Peculiar Support Equipment (PSE)
1.8.1Test and Measurement Equipment
1.8.2Support and Handling Equipment
1.9Common Support Equipment (CSE)
1.9.1Test and Measurement Equipment
1.9.2Support and Handling Equipment
1.10Initial Repair Parts
1.11Anti Tamper/Program Protection
1.11.1Plan
1.11.2Implementation/Test
An Employee of:Government Fiscal Year 3Labor CategoryBOE Reference3.1 EMD, System Design
3.1.1 CAT-F Prime Mission Equipment3.1.2 System Engineering3.1.3 Reserved3.1.4 Technology Readiness Assessment3.1.5 Critical Technology Demonstration3.1.6 Program Protection Plan3.1.7 Data Rights3.1.8 Configuration Management3.1.9 Program Management3.1.10 Risk Management3.1.11 Subcontractor/ Supplier Management3.1.12 Data Management
Notional CWBS3.1.1.1 CAT-F External Controls and Sustaining Engineering Planning3.1.1.2 CAT-F Software Design3.1.2.1 Human Factors Engineering3.1.2.2 Interface Control Working Group3.1.2.3 Technical Performance Measures3.1.2.4 System Engineering Management Plan3.1.6.1 Inspection and Audit3.1.6.2 Cybersecurity3.1.6.3 Anti-Tamper3.1.6.4 Security3.1.6.5 Security Classification Data3.1.7.1 Unlimited Rights3.1.7.2 Government Purpose Rights3.1.7.3 Limited or Restricted Rights3.1.8.1 Data Accession List3.1.9.1 Contractor Integrated Performance Management3.1.9.2 Integrated Baseline Reviews3.1.9.3 Status Reports3.1.9.4 Contract Funds Status Report3.1.9.5 Integrated Master Schedule3.1.12.1 Data Repository3.1.12.2 Government Furnished Data3.1.12.3 Acquired or Furnished Data
3.1.1.2.1 Software Functional Qualification Test3.1.6.5.1 Safeguarding Classified Material3.1.12.2.1 Government Furnished Documentation3.1.12.2.2 Government Furnished Software3.1.12.3.1 Contractor Acquired Property3.1.12.3.2 Government Furnished Property and Services3.1.12.3.3 Government Property and Loss of GP Definition3.1.12.3.4 Reporting Loss of Government Property3.1.12.3.5 GFE/ GFP/ Management/ Govt Furnished Information
WBS/Item NumberWBS Description
1.0Automatic Test System
1.1Common Armament Tester for Fighters Prime Mission Product (CAT-F PMP)
1.1.1CAT-F O-Level System
1.1.1.1CAT-F Subsystem 1…n (specify)
1.1.1.1.1SS1, Component 1
1.1.1.1.1.1Design
1.1.1.1.1.2Fabricate
1.1.1.1.1.3Integrate
1.1.1.1.1.4Test
1.1.1.1.2SS1, Component 2...n
1.1.1.1.#SIMILAR BREAKDOWN TO 1.1.1.1 EXAMPLE
1.1.2CAT-F O-Level Software Release 1…n (specify)
1.1.2.1CSCI 1
1.1.2.1.1Design
1.1.2.1.2Fabricate
1.1.2.1.3Integrate
1.1.2.1.4Test
1.1.3CAT-F I-Level System
1.1.3.1CAT-F Subsystem 1…n (specify)
1.1.3.1.1SS1, Component 1
1.1.3.1.1.1Design
1.1.3.1.1.2Fabricate
1.1.3.1.1.3Integrate
1.1.3.1.1.4Test
1.1.3.1.2SS1, Component 2...n
1.1.3.1.#SIMILAR BREAKDOWN TO 1.1.3.1 EXAMPLE
1.1.4CAT-F I-Level Software Release 1…n (specify)
1.1.4.1CSCI 1
1.1.4.1.1Design
1.1.4.1.2Fabricate
1.1.4.1.3Integrate
1.1.4.1.4Test
1.1.5CAT-F Prime Mission Product Integration, Assembly, Test, and Checkout
1.2Platform Integration, Assembly, Test, and Checkout (Trial Kit Install)
1.3Systems Engineering (SE)
1.4Program Management (PM)
1.5System Test and Eval (ST&E)
1.5.1Developmental Test and Evaluation (DT&E)
1.5.2Operational Test and Evaluation (OT&E)
1.5.3Mock-ups/System Integration Labs (SILs)
1.5.4Test and Evaluation Support
1.5.5Test Facilities
1.6Training
1.6.1Equipment
1.6.2Services
1.6.3Facilities
1.7Data
1.7.1Technical Publications
1.7.2Engineering Data
1.7.3Management Data
1.7.4Support Data
1.7.5Data Repository
1.8Peculiar Support Equipment (PSE)
1.8.1Test and Measurement Equipment
1.8.2Support and Handling Equipment
1.9Common Support Equipment (CSE)
1.9.1Test and Measurement Equipment
1.9.2Support and Handling Equipment
1.10Initial Repair Parts
1.11Anti Tamper/Program Protection
1.11.1Plan
1.11.2Implementation/Test
An Employee of:Government Fiscal Year 4Labor CategoryBOE Reference3.1 EMD, System Design
3.1.1 CAT-F Prime Mission Equipment3.1.2 System Engineering3.1.3 Reserved3.1.4 Technology Readiness Assessment3.1.5 Critical Technology Demonstration3.1.6 Program Protection Plan3.1.7 Data Rights3.1.8 Configuration Management3.1.9 Program Management3.1.10 Risk Management3.1.11 Subcontractor/ Supplier Management3.1.12 Data Management
Notional CWBS3.1.1.1 CAT-F External Controls and Sustaining Engineering Planning3.1.1.2 CAT-F Software Design3.1.2.1 Human Factors Engineering3.1.2.2 Interface Control Working Group3.1.2.3 Technical Performance Measures3.1.2.4 System Engineering Management Plan3.1.6.1 Inspection and Audit3.1.6.2 Cybersecurity3.1.6.3 Anti-Tamper3.1.6.4 Security3.1.6.5 Security Classification Data3.1.7.1 Unlimited Rights3.1.7.2 Government Purpose Rights3.1.7.3 Limited or Restricted Rights3.1.8.1 Data Accession List3.1.9.1 Contractor Integrated Performance Management3.1.9.2 Integrated Baseline Reviews3.1.9.3 Status Reports3.1.9.4 Contract Funds Status Report3.1.9.5 Integrated Master Schedule3.1.12.1 Data Repository3.1.12.2 Government Furnished Data3.1.12.3 Acquired or Furnished Data
3.1.1.2.1 Software Functional Qualification Test3.1.6.5.1 Safeguarding Classified Material3.1.12.2.1 Government Furnished Documentation3.1.12.2.2 Government Furnished Software3.1.12.3.1 Contractor Acquired Property3.1.12.3.2 Government Furnished Property and Services3.1.12.3.3 Government Property and Loss of GP Definition3.1.12.3.4 Reporting Loss of Government Property3.1.12.3.5 GFE/ GFP/ Management/ Govt Furnished Information
WBS/Item NumberWBS Description
1.0Automatic Test System
1.1Common Armament Tester for Fighters Prime Mission Product (CAT-F PMP)
1.1.1CAT-F O-Level System
1.1.1.1CAT-F Subsystem 1…n (specify)
1.1.1.1.1SS1, Component 1
1.1.1.1.1.1Design
1.1.1.1.1.2Fabricate
1.1.1.1.1.3Integrate
1.1.1.1.1.4Test
1.1.1.1.2SS1, Component 2...n
1.1.1.1.#SIMILAR BREAKDOWN TO 1.1.1.1 EXAMPLE
1.1.2CAT-F O-Level Software Release 1…n (specify)
1.1.2.1CSCI 1
1.1.2.1.1Design
1.1.2.1.2Fabricate
1.1.2.1.3Integrate
1.1.2.1.4Test
1.1.3CAT-F I-Level System
1.1.3.1CAT-F Subsystem 1…n (specify)
1.1.3.1.1SS1, Component 1
1.1.3.1.1.1Design
1.1.3.1.1.2Fabricate
1.1.3.1.1.3Integrate
1.1.3.1.1.4Test
1.1.3.1.2SS1, Component 2...n
1.1.3.1.#SIMILAR BREAKDOWN TO 1.1.3.1 EXAMPLE
1.1.4CAT-F I-Level Software Release 1…n (specify)
1.1.4.1CSCI 1
1.1.4.1.1Design
1.1.4.1.2Fabricate
1.1.4.1.3Integrate
1.1.4.1.4Test
1.1.5CAT-F Prime Mission Product Integration, Assembly, Test, and Checkout
1.2Platform Integration, Assembly, Test, and Checkout (Trial Kit Install)
1.3Systems Engineering (SE)
1.4Program Management (PM)
1.5System Test and Eval (ST&E)
1.5.1Developmental Test and Evaluation (DT&E)
1.5.2Operational Test and Evaluation (OT&E)
1.5.3Mock-ups/System Integration Labs (SILs)
1.5.4Test and Evaluation Support
1.5.5Test Facilities
1.6Training
1.6.1Equipment
1.6.2Services
1.6.3Facilities
1.7Data
1.7.1Technical Publications
1.7.2Engineering Data
1.7.3Management Data
1.7.4Support Data
1.7.5Data Repository
1.8Peculiar Support Equipment (PSE)
1.8.1Test and Measurement Equipment
1.8.2Support and Handling Equipment
1.9Common Support Equipment (CSE)
1.9.1Test and Measurement Equipment
1.9.2Support and Handling Equipment
1.10Initial Repair Parts
1.11Anti Tamper/Program Protection
1.11.1Plan
1.11.2Implementation/Test
An Employee of:Government Fiscal Year 5Labor CategoryBOE Reference3.1 EMD, System Design
3.1.1 CAT-F Prime Mission Equipment3.1.2 System Engineering3.1.3 Reserved3.1.4 Technology Readiness Assessment3.1.5 Critical Technology Demonstration3.1.6 Program Protection Plan3.1.7 Data Rights3.1.8 Configuration Management3.1.9 Program Management3.1.10 Risk Management3.1.11 Subcontractor/ Supplier Management3.1.12 Data Management
Notional CWBS3.1.1.1 CAT-F External Controls and Sustaining Engineering Planning3.1.1.2 CAT-F Software Design3.1.2.1 Human Factors Engineering3.1.2.2 Interface Control Working Group3.1.2.3 Technical Performance Measures3.1.2.4 System Engineering Management Plan3.1.6.1 Inspection and Audit3.1.6.2 Cybersecurity3.1.6.3 Anti-Tamper3.1.6.4 Security3.1.6.5 Security Classification Data3.1.7.1 Unlimited Rights3.1.7.2 Government Purpose Rights3.1.7.3 Limited or Restricted Rights3.1.8.1 Data Accession List3.1.9.1 Contractor Integrated Performance Management3.1.9.2 Integrated Baseline Reviews3.1.9.3 Status Reports3.1.9.4 Contract Funds Status Report3.1.9.5 Integrated Master Schedule3.1.12.1 Data Repository3.1.12.2 Government Furnished Data3.1.12.3 Acquired or Furnished Data
3.1.1.2.1 Software Functional Qualification Test3.1.6.5.1 Safeguarding Classified Material3.1.12.2.1 Government Furnished Documentation3.1.12.2.2 Government Furnished Software3.1.12.3.1 Contractor Acquired Property3.1.12.3.2 Government Furnished Property and Services3.1.12.3.3 Government Property and Loss of GP Definition3.1.12.3.4 Reporting Loss of Government Property3.1.12.3.5 GFE/ GFP/ Management/ Govt Furnished Information
WBS/Item NumberWBS Description
1.0Automatic Test System
1.1Common Armament Tester for Fighters Prime Mission Product (CAT-F PMP)
1.1.1CAT-F O-Level System
1.1.1.1CAT-F Subsystem 1…n (specify)
1.1.1.1.1SS1, Component 1
1.1.1.1.1.1Design
1.1.1.1.1.2Fabricate
1.1.1.1.1.3Integrate
1.1.1.1.1.4Test
1.1.1.1.2SS1, Component 2...n
1.1.1.1.#SIMILAR BREAKDOWN TO 1.1.1.1 EXAMPLE
1.1.2CAT-F O-Level Software Release 1…n (specify)
1.1.2.1CSCI 1
1.1.2.1.1Design
1.1.2.1.2Fabricate
1.1.2.1.3Integrate
1.1.2.1.4Test
1.1.3CAT-F I-Level System
1.1.3.1CAT-F Subsystem 1…n (specify)
1.1.3.1.1SS1, Component 1
1.1.3.1.1.1Design
1.1.3.1.1.2Fabricate
1.1.3.1.1.3Integrate
1.1.3.1.1.4Test
1.1.3.1.2SS1, Component 2...n
1.1.3.1.#SIMILAR BREAKDOWN TO 1.1.3.1 EXAMPLE
1.1.4CAT-F I-Level Software Release 1…n (specify)
1.1.4.1CSCI 1
1.1.4.1.1Design
1.1.4.1.2Fabricate
1.1.4.1.3Integrate
1.1.4.1.4Test
1.1.5CAT-F Prime Mission Product Integration, Assembly, Test, and Checkout
1.2Platform Integration, Assembly, Test, and Checkout (Trial Kit Install)