Additional RFI Questions: Please respond by 22 April 2008
1. Are there any business practices unique to your industry? If so, please describe.
2. Is your company willing to provide a product drawing with unlimited rights which meets the requirements of our PD? (Copy of DD1423 attached.)
3. What is the estimated time period for installation of one of these stands at a field location? Estimated number of people needed to assemble?
4. What is the estimated production time for the first pre-production unit? What would be the lead-time for the production units? What is your maximum manufacturing capacity per month?
5. Will you have critical subcontractors to assist with this effort? If so, in what capacity will they be involved?