3PEP RFP Questions and Responses - Rev 7.pdf

PDF 177 KB Posted

Attached to
Third Party Equipment Purchasing (3PEP) 8(a) Federal contract opportunity
Solicitation number
FA8517-21-R-0001
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

About this file

This document provides answers to questions from potential offerors on two solicitations. It grants a two week extension to both solicitations, FA8517-21-R-0001 and FA8517-21-R-0002, issued by the Department of the Air Force Materiel Command Air Force Sustainment Center. Proposals for both solicitations, which procure strategic support equipment items with initial unit prices of $50,000 or less, are now due on March 16, 2021 rather than the original date of March 2, 2021. Solicitation FA8517-21-R-0001 is an 8(a) set-aside that anticipates awarding three ID/IQ contracts for up to 10 years each to 8(a) companies for sourcing, acquiring, and delivering support equipment national stock numbers.

View the file

Other files for this federal contract opportunity

Other files attached to Third Party Equipment Purchasing (3PEP) 8(a), newest first.
File Type Posted
FA8517-21-R-0001-0003.pdf PDF
3PEP SOW FD2060-21-00138_Feb_2021.pdf PDF
3PEP LM_FA8517-21-R-0001_8(a).pdf PDF
Attention All Offerors.docx DOCX document
FA8517-21-R-0001-0002.pdf PDF
3PEP RFP Questions and Responses - Rev 9.pdf PDF
NOTICE - Req. for TSR FORM FA8517-21-R-0001.pdf PDF
3PEP RFP Questions and Responses - Rev 8 (rev1).pdf PDF
FA8517-21-R-0001-0001.pdf PDF
3PEP RFP Questions and Responses - Rev 6 v2.pdf PDF
3PEP RFP Questions and Responses - Rev 4.pdf PDF
3PEP RFP Questions and Responses - Rev 5.pdf PDF
3PEP RFP Questions and Responses - Rev 3.pdf PDF
3PEP RFP Questions and Responses - Rev 2.pdf PDF
NOTICE - PPI Tool FA8517-21-R-0001.pdf PDF
NOTICE - BID SETS FA8517-21-R-0001 2.pdf PDF
FA8517-21-R-0001 Attachment 3 - Past Performance Questionnaire_Final.pdf PDF
FA8517-21-R-0001 Attachment 5 - Subcontractor and Teaming Member Consent Form_Final.pdf PDF
FA8517-21-R-0001 Section M_Final.pdf PDF
FA8517-21-R-0001 Section L Provision_Final.pdf PDF
3PEP SOW FD2060-21-00138_Jan_2021_Final.pdf PDF
A001_Technical_Report-Study_Services(JAN 2021)_Final.pdf PDF
Copy of FA8517-21-R-0001 Attachment 7 - Price Proposal Matrix - 06Jan21_Final.xlsx XLSX spreadsheet
FA8517-21-R-0001 Attachment 6 - Client Authorization Letter_Final.pdf PDF
FA8517-21-R-0001 Attachment 1 - Intstructions to Offerors_Final.pdf PDF
FA8517-21-R-0001 Attachment 2 - Relevancy Table_Final.pdf PDF
A002_Scientific_and_Technical_Reports(JAN2021)_Final.pdf PDF
FA8517-21-R-0001 Attachment 4 - Transmittal Letter_Final.pdf PDF
FA8517-21-R-0001_Final.pdf PDF
NOTICE - BID SETS FA8517-21-R-0001.pdf PDF
NOTICE - BID SETS FA8517-21-R-0001.pdf PDF
3PEP RFP Questions and Responses - Addendum_1.pdf PDF
3PEP SOW FA8517-21-R-0001_Oct 29 2020.docx DOCX document
FA8517-21-R-0001.pdf PDF
FA8517-21-R-0001 Attachment 5 - Subcontractor and Teaming Member Consent Form.doc DOC document
FA8517-21-R-0001 Attachment 1 - Intstructions to Offerors.docx DOCX document
FA8517-21-R-0001 Attachment 3 - Past Performance Questionnaire.doc DOC document
FA8517-21-R-0001 Attachment 4 - Transmittal Letter.doc DOC document
FA8517-21-R-0001 Attachment 7 - Price Proposal Matrix.xlsx XLSX spreadsheet
3PEP LM_FA8517-21-R-0001.docx DOCX document
FA8517-21-R-0001 Attachment 2 - Relevancy Table.docx DOCX document
FA8517-21-R-0001 Attachment 6 - Client Authorization Letter.doc DOC document
Show all 42

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

3 PEP QUESTIONS & ANSWERS

SUBMITTED AFTER RELEASE

OF THE FINAL RFPS

ADDITIONAL QUESTIONS

The following additional questions and answers are provided for informational purposes only and intended to assist in clarifying issues raised by potential offerors regarding the official solicitation. Please note, the official solicitation has set forth and established the actual terms and conditions of this acquisition. Any discrepancy between the official solicitation and these questions and answers must be resolved based upon the parameters of the official solicitation. It was the intent of the Government to resolve the majority, if not all, of the issues raised by these questions and answers within the context of the official solicitation; however, additional questions have been raised after its release.

1. Questions related to Extensions:

Question 1: Regarding FA851721R0002 Third Party Equipment Purchasing, can you please clarify if a deadline extension till March 17th, 2021 is acceptable?

Question 2: On behalf of Company X and their partner – X2 we are requesting a 60 day extension to the deadline on solicitation (FA851721R0001).

Team X and X2 are small business concerns, and we’re having a hardship responding to the solicitation by 3/2/2021. This is not a sufficient amount of time due to the complications caused by COVID-19. These complications are having a direct impact in preparing a submittal with reduced staff, especially in the logistics and supply areas, which are key in preparing pricing information. There are also 2d and 3rd order affects with vendors unable to respond in a timely manner to our requests for pricing because their sources are also behind and struggling.

We believe an additional 60 days to the published proposal due date, will allow all of the offerors, not just our team, sufficient time to respond. These are clearly unprecedented times and we appreciate your patience and understanding.

Question: 3: We are in communication with the suppliers listed for this solicitation. Due to the recent weather events throughout the western and southern United States, much of the supplier base is requesting extensions. Suppliers are informing us they are not able to prepare pricing or return to the office due to damage and/or inability to return to office. For these reasons we are requesting a two week extension to the pricing submission. This will allow suppliers time to return to their buildings and their regions infrastructure to return.

Response: The Team has decided to grant a two week extension for proposal submissions. Proposals are now due on March 16, 2021 instead of March 2, 2021.

NOTE: For clarification purposes, both solicitations, FA8517-21-R-0001, 8(a) and FA8517-21-R-0002, SB, are being extended to 16 Mar 21. RFP amendments are being drafted to incorporate all the changes that have been made to the RFPs.