FA850125Q0009 Questions and Answers v2.docx
DOCX document 17 KB Posted
- Attached to
- Robins AFB LCMC/EBUG Lab Wall and Flooring Renovation Federal contract opportunity
- Solicitation number
- FA850125Q0009
About this file
This is a Questions and Answers document for solicitation FA850125Q0009 regarding wall and flooring renovation at the Robins AFB LCMC/EBUG Lab. The document addresses contractor questions about site photos, electrical outlets, cost estimates, and layout specifications.
The Q&A clarifies that contractors must schedule site visits through Captain Calvin Garcia to view the existing walls and electrical outlets. No government cost estimate is provided, but award is expected around mid-February with performance beginning upon award. The renovation involves installing 18 linear feet of DIRTT walls in an L-shape configuration, with most being one straight section connecting to an existing wall. The Air Force added a layout attachment and emphasizes that site visits are intended to clarify detailed specifications with the requirement owner.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA850125Q0009 Questions and Answers v2.docx | DOCX document | |
| FA850125Q0009 Questions and Answers v2.docx | DOCX document | |
| Lab Floorplan.pdf | ||
| FA850125Q0009 Questions and Answers v2.docx | DOCX document | |
| FA850125Q0009 Questions and Answers.docx | DOCX document | |
| A001 Product Engineering Design and Assocaiated Lists_Signed.pdf | ||
| A002 Preparation of Final Inspection_Signed.pdf | ||
| Solicitation - FA850125Q0009.pdf | ||
| A004 Accident_Incident Report_Signed.pdf | ||
| A003 ESOH Plan_Signed.pdf | ||
| EBUG Lab Wall SOW.pdf | ||
| LCMC EBUG single source justification-redacted_Redacted.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA850125Q0009 Questions and Answers
1. Could you please provide photos of the existing walls and floors that need to be removed and replaced?
a) Please reference SOW paragraph 2.0. This paragraph discusses site-visits and the timeframe within which they must be scheduled. Please find the Government POC’s information below:
Captain Calvin Garcia, Email (preferred): calvin.garcia.1@us.af.mil, Phone: 478-222-7518
2. Could you also provide images of any electrical outlets on the existing walls that are part of the renovation scope?
a) Please reference SOW paragraph 2.0. This paragraph discusses site-visits and the timeframe within which they must be scheduled. Please find the Government POC’s information below:
Captain Calvin Garcia, Email (preferred): calvin.garcia.1@us.af.mil, Phone: 478-222-7518
3. Is there a cost estimate , budget or ballpark figure for the project listed? Is there an actual start date for the project?
a) The Government does not provide a cost estimate. There is no definitive start date. The contract start date will depend on the date of award. We hope to award sometime around the middle of February, and the period of performance will begin upon receipt of award.
4. After speaking with multiple contractors and reviewing the SOW, they have all requested the Layout of the walls that is wanted (L shape,Straight,U shape) and position of door and a floor plan and dimensions of the room in which the walls and floors are to be installed. I am unable to find these details in the documents provided on Sam. I apologize if I missed them. If not could you please send me the information so I may quote the contract as accurate as possible.
a) In total it’s 18 linear feet, in an L shape, with most of it being one long straight shot, and then a small portion to connect with an existing wall.
1. We have added an additional attachment for the layout for your reference, but please keep in mind that the goal was to plan site visits with the requirement owner to clarify such information.