Question_Answer.docx
DOCX document 14 KB Posted
- Attached to
- A-10 PACAF DEPOT MAINTENANCE Federal contract opportunity
- Solicitation number
- FA8202-19-R-1007
About this file
Q&A
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attac_5_Past_Performance_Information_Sheet.docx | DOCX document | |
| Question_Answer.docx | DOCX document | |
| Question_Answer.docx | DOCX document | |
| Attch_2_PastPerformanceQuestionnaire.docx | DOCX document | |
| CY_PACAF_CLIN_Structure_10_YR_Extended.xlsx | XLSX spreadsheet | |
| Contract_Data_Requirement_List_(CDRL).pdf | ||
| Attch_2_PastPerformanceQuestionnaire.docx | DOCX document | |
| FA820219R1007.pdf | ||
| Performance_Work_Statement_(PWS).pdf | ||
| CY_PACAF_CLIN_Structure_10_YR_Extended.xlsx | XLSX spreadsheet | |
| Attac_5_Past_Performance_Information_Sheet.docx | DOCX document | |
| Delivery_Schedule-Flow_Days.docx | DOCX document | |
| Section_L.pdf | ||
| Attch_1_Past_Perf_Info_Sheet.docx | DOCX document | |
| Attach_4_Client_Authorization.docx | DOCX document | |
| Section_M.pdf | ||
| Attach_3_SubKtr_and_Joint_Venture_Partner_Consent.docx | DOCX document |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The purpose of this amendment is to answer the questions provided below:
1. Where will the contract be performed?
Answer: As described in the basic requirement the awardee will be required to perform these services within 400 nautical miles of Osan Air Force Base, Republic of Korea.
2. Will the Government hold discussions?
Answer: The Government intends to make award without discussions. If, at the discretion of the Government, discussions are deemed necessary, they will be conducted in accordance with FAR 15.306 -- Exchanges With Offerors After Receipt of Proposals.
3. Is there a cut-off/end date for submission of questions or clarifications?
Answer: The Government requests all questions and requests for clarification be submitted no later than 29 April 2019. The government will provide answers no later than 6 May 2019. Responses are due no later than 20 May 2019, 12:00 PM Mountain Standard Time. Note, the Government will provide responses as soon as they are available.
4. What is the correct PoP for the TEP (Pricing Matrix)?
Answer: The ordering period is from 1 Jan – 30 Dec, reference the updated attached TEP. This will attachment will supersede all other previous copies.