503_Quantities.docx

DOCX document 25 KB Posted

Attached to
Bldg. 503 Repair/Minor Const/Equipment Federal contract opportunity
Solicitation number
FA8201-16-B-0009
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

503 Quantities

View the file

Other files for this federal contract opportunity

Other files attached to Bldg. 503 Repair/Minor Const/Equipment, newest first.
File Type Posted
B503KRSM092001-E4.0BLD_503_REPAIRS-E4.0.pdf PDF
Bldg-503PB_WO53153.xlsx XLSX spreadsheet
IFB_B503_Amend_04.docx DOCX document
503 Individual Pictures 53.pdf PDF
503 Individual Pictures 104.pdf PDF
Manufdata1.pdf PDF
503 Individual Pictures 103.pdf PDF
503 Individual Pictures 107.pdf PDF
7400_System_450_VOC_Primers_RO11_GDH1090.pdf PDF
503 Individual Pictures 85.pdf PDF
503 Individual Pictures 78.pdf PDF
Manufdata2.pdf PDF
ASPHALT_DETAIL.pdf PDF
503 Individual Pictures 105.pdf PDF
503 Individual Pictures 75.pdf PDF
503 Individual Pictures 88.pdf PDF
503 Individual Pictures 74.pdf PDF
UT104.txt TXT text file
503 Individual Pictures 77.pdf PDF
503 Individual Pictures 71.pdf PDF
503 Individual Pictures 67.pdf PDF
503 Individual Pictures 60.pdf PDF
503_Individual_51-109_Pictures_81.zip ZIP file
503 Individual Pictures 81.pdf PDF
503 Individual Pictures 59.pdf PDF
503 Individual Pictures 108.pdf PDF
503 Individual Pictures 61.pdf PDF
503_Individual_Pictures_Addendum.pdf PDF
503 Individual Pictures 56.pdf PDF
503 Individual Pictures 97.pdf PDF
5600_System_CS23_GHD582_0516 —
503 Individual Pictures 98.pdf PDF
503 Individual Pictures 68.pdf PDF
503 Individual Pictures 95.pdf PDF
503 Individual Pictures 58.pdf PDF
503 Individual Pictures 82.pdf PDF
503 Individual Pictures 94.pdf PDF
200_Anti_Skid_Additive_CS37_GDH82_715.pdf PDF
503 Individual Pictures 96.pdf PDF
LS-102.pdf PDF
503 Individual Pictures 92.pdf PDF
A_INTRODUCTION.docx DOCX document
MaterialsEstimate.docx DOCX document
Manufdata1s.pdf PDF
503 Individual Pictures 106.pdf PDF
Architectural_Compatibility_Standard.pdf PDF
General_Decision_No._UT160104_29_July_UT104.pdf PDF
TAB_K__1_Aug_11.pdf PDF
Schedule_of_Drawings.doc DOC document
BLDG._503_EXTERIOR_UPGRADE_SET_sow.pdf PDF
Show all 50

Bldg. 503 Repair/Minor Const/Equipment has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

503 Exterior Upgrade Estimated Quantities

#1 Pointing

· (Bldg. 503) SW“Hole filling”= 2 ft2See picture 1 and 2
· (Bldg. 503A) SW “Pointing”= 1 ft2See picture 19

· Total Area = 3 ft2

#2 RailingMeasurements were taken of top rail only for scaling purposes.
· (Bldg. 503) NW“Dock”= 64 ft.See picture 90
· (Bldg. 503) SW= 240 ft.See picture 3
· (Bldg. 503) SE= 35 ft.See picture 73
· (Bldg. 503) E= 45 ft.See picture 80
· (Bldg. 503A) SE “Drive ramp”= 333 ft.See picture (45-47)
· (Bldg. 503A) NE “Hand ramp”= 310 ft.See picture 62, 65
· (Bldg. 503B) E= 50 ft.

· Total Linear ft. = 1100 ft.

#3 Exterior StairsArea2 inch Tread Safety yellow paint
· (Bldg. 503) NW “Dock”= 28 ft2= 5 ft2See picture 90
· (Bldg. 503) SW= 163 ft2= 22 ft2See picture 4
· (Bldg. 503) E= 30 ft2= 5 ft2See picture 73
· (Bldg. 503A) NE= 30 ft2= 3 ft2See picture 65

Areas found by measuring overall length by width.

· Total Area = 250 ft2Total Tread Area = 35 ft2
#4 Pot Holes(~ 30 areas)
· (Bldg. 503) W“Road”= 158 ft2See picture (101-106)
· (Bldg. 503) E= 245 ft2See picture (71,72,74,75,78,82,83,84,86)
· (Bldg. 503) N “Along Column”= 1 ft2See picture 98A
· (Bldg. 503A) W“Parking”= 10 ft2See picture (32-34)
· (Bldg. 503A) E= 18 ft2See picture 59
· (Bldg. 507) W= 230 ft2See picture (39, 40A, 40B, 41, 44A, 45A)
· (Bldg. 507) NW= 1775 ft2See Picture 54B
· (Ancillary)= 480 ft2 Un-photographed

· Total Area = 2917 ft2

#5 Sink Holes(2 areas)
· (Bldg. 503A) NE“Outside of smoke Area”= 200 ft2See picture 70
· (Bldg. 503B) E “Power pole guy wire”= 30 ft2See picture 85

· Total Area = 230 ft2 #6 Cracks Assumptions are as follows: 80% of cracks are through wall, wall is 12 inches thick, 95% of cracks are blind side, crack width does not exceed ¼ in., interior web dispersal unknown.

· (Bldg. 503) NW“End of dock”= 30 ft.
· (Bldg. 503) SW“Entryway”= 100 ft.See picture 3
· (Bldg. 503) E“Up to grate”= 13 ft.
· (Bldg. 503A) SE“Driving ramp”= 198 ft.See picture 46, 47
· (Bldg. 503A) E“Equip. Yard”= 46 ft.See picture 55
· (Bldg. 503A) NE “Ramp”= 303 ft.See picture 62, 64
· (Bldg. 503B) E“Ramp”= 30 ft.

· (Ancillary ) “Un-photographed” = 150 ft.

· Total Linear ft. = 870 ft.

#7 Concrete Corners(To be replaced)
· (Bldg. 503) NW “Includes brick” (x 3)= 2 ft3See picture 90A, 90B
· (Bldg. 503) W(x 4)= 5 ft3See picture 5, 6, 17A
· (Bldg. 503A) SE“Driving Ramp”(x 1)= 2 ft3See picture 45
· (Bldg. 503A) NE“Ramp”(x 11)= 35 ft3See picture 60,61

· Total Cubed ft. = 44 ft3 #8 Acrylic Sealer

· (Bldg. 503) NW “Dock”= 254 ft2
· (Bldg. 503) SW= 2637 ft2See picture 3
· (Bldg. 503) E= 394 ft2
· (Bldg. 503A) SE“Drive Ramp”= 2754 ft2See picture 45
· (Bldg. 503A) NE“Ramp”= 2640 ft2See picture 62, 65
· (Bldg. 503B) E“Ramp”= 445 ft2

· Total Area = 9125 ft3

#9 Curb Repair (3 areas)

· (Bldg. 503) NE“Dock”= 2 ft.See picture 100
· (Bldg. 503A) S“Parking”= 2 ft.See picture 21
· (Bldg. 507) W“Parking”= 3 ft.See picture 36, 37

· Total Linear ft. = 7 ft.

#10 Landscape CurbingNew
· (Bldg. 503) W= 45 ft.See picture 14

· Total Linear ft. = 45 ft.

#11 Loading Dock Angle Painting

· (Bldg. 503) NW= 72 ft2See picture 91
· (Bldg. 503) NE= 56 ft2See picture 91

· Total Area = 103 ft2 #12 Wall Cleaning

· (Bldg. 503) N“300 ft. long and 17 ft. high w/ outdoor areas removed”= 5600 ft2
· (Bldg. 503H) W “200 ft. long and 8 ft. high w/ outdoor areas removed”= 1600 ft2

· Total Area = 7200 ft2 See picture 96 &79 #13 Bollards

· (Bldg. 503) N“Dock”(4 ft. x 6 in.)= 10= 70 ft2See picture 98
· (Bldg. 503A)“Concrete AT/FP”= 28= 615 ft2See pictures 12, 16, 20

· Total Bollards = 38 Total Area = 685 ft2 #14 Bird Screening

· (Bldg. 503) NE “Dock” = 175 ft2 See picture 99,99A,99B,99C

· Total Area = 175 ft2 #15 Column Painting (12 total columns)

· (Bldg. 503) N“Dock (x 7) 16 ft. columns”= 700 ft2See picture 92
· (Bldg. 503) SW“(x 5) columns”= 363 ft2See picture 3

· Total Area = 1100 ft2

#16 Sidewalk Grinding

· (Bldg. 503A) S“Under Pine tree”= 5 ft.See picture 38
· (Bldg. 503) SE= 3 ft.See picture 72

· Total Linear ft. = 8 ft.

#17 Chain-Link Repair

· (Bldg. 503) NWStraighten 2 Posts
· (Bldg. 503A) SStraighten 10 Posts Chain-link= 54 ft2See pictures 22, 23, 29

· Total Posts = 12 Posts Total Area of chain-link = 54 ft2 #18 Equipment Yard Fencing

· (Bldg. 503A) E “(6 ft. x 6 in. Slats)

· (x 50) Outside (x 20) Inside”= 70See picture 55
· (Bldg. 503A) E “(2 in. x 1 in) attaching rung”= 30 ft.

· Total Slats = 70 Total Linear ft. (attach rung) = 30 ft.

#19 Equipment Yard Insulation

· (Bldg. 503A) ESee picture 56
· 3 in. = 55 ft.(x 8) 90o Elbows and (x 4) 45o Elbows
· 1 in. = 95 ft.(x 10) 90o Elbows

Interior Paint and Stair Areas

#20 Yellow/Black Paint(4 in. Strip)See picture 109
· (Bldg. 503A) Lower“9 areas”= 60 ft2
· (Bldg. 503A) Main“3 areas”= 185 ft2
· (Bldg. 503)“8 areas”= 155 ft2
· (Bldg. 503B) E“Ramp”= 5 ft2See picture 87

· Total Area = 405 ft2

#21 Green/White Paint(3 ft. x 3 ft.)See picture 108
· (Bldg. 503A) Lower“5 areas”= 45 ft2

· Total Area = 45 ft2

#22 Interior Stairs (w/no risers)Area2 inch Tread Safety Yellow
· (Bldg. 503) NW= 72 ft2= 12 ft2See picture 107
· (Bldg. 503) NE= 72 ft2= 12 ft2
· (Bldg. 503) SW= 72 ft2= 12 ft2
· (Bldg. 503) SE= 72 ft2= 12 ft2

· Total Stair Area = 288 ft2 Total Tread Area = 48 ft2

All 22 topics above are approximate quantities for estimating purposes.

Contractor shall accommodate for an additional 10 % on items: 4, 6, 7, 8, 19, and 20. This is not accommodated in the file Materials Estimate.

Many of these products will require a minimum of one month lead time to order.