32 13 14.pdf

PDF 13 KB Posted

Attached to
WWYK260004 - REPAIR STRUCTURAL INTEGRITY, B1134, POST 34 & NORTH WALL
Solicitation number
FA813727R0001
Issued by

About this file

This is a technical specifications document for non-airfield pavement construction at Tinker Air Force Base in Oklahoma, effective April 2019.

The specification adopts the Oklahoma Department of Transportation (ODOT) Standard Specifications for Highway Construction as the baseline standard for all non-airfield paving projects, including grading, drainage, drainage structures, roads, streets, parking facilities, storage areas, sidewalks, driveways, bridges, and associated signage, markings, lighting, and signalization. The applicable ODOT edition is the one current on the Notice to Proceed (NTP) with design. Key amendments to ODOT standards include: concrete strength for roads, streets, and parking areas shall be specified as flexural with a minimum strength of 650 psi; pavements exceeding 8 inches in total thickness must include a drainage layer and separation layer (which may be fabric); all curbs and gutters shall be concrete and monolithic, placed separately from pavement; subgrade preparation requires removal of all plant materials and roots with select fill replacement; unsuitable subgrade material must be removed or modified until stable; and subgrades must be proof-rolled with visual checking for pumping even if compaction requirements are met. All materials must be sourced from the ODOT Approved Material Suppliers List and be ODOT-approved for their intended use. Contract-specific revisions to ODOT standards shall be included in the special conditions section. For IDIQ contracts, pay quantities and units are specified in line items; for non-IDIQ contracts, ODOT SSHC specifications apply. References include UFC 1-200-01 and UFC 3-201-01 from the Department of Defense.

View the file

Other files

File Type Posted
07 42 13.pdf PDF
32 01 16.pdf PDF
10 44 16.pdf PDF
32 01 17.pdf PDF
10 14 00.10.pdf PDF
07 41 13.pdf PDF
31 23 15.pdf PDF
31 00 00.pdf PDF
03 30 00.pdf PDF
06 10 00.pdf PDF
09 90 00.pdf PDF
02 41 00.pdf PDF
32 01 14.pdf PDF
COPY of Site Visit Sign-in Sheet_10.22.2026.pdf PDF
00 70 00.pdf PDF
00 80 05.pdf PDF
00 80 00.pdf PDF
01 42 00.pdf PDF
00 72 00.pdf PDF
01 33 16.00 10.pdf PDF
00 71 00.pdf PDF
01 78 23.pdf PDF
01 45 00.00 10.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
01 32 16.00 20.pdf PDF
01 78 00.pdf PDF
01 33 00.pdf PDF
01 50 00.pdf PDF
RFI QA RESPONSES - WWYK260004 - REPAIR STRUCTURAL INTEGRITY B1134 POST 34 NORTH WALL_COR.pdf PDF
Solicitation - FA813727R0001.pdf PDF
Wage Determinations.pdf PDF
Att.10_260004_Drawings.pdf PDF
Att.9_260004_Submittal Register.pdf PDF
Att.8_260004_MACB_SOW.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tinker AFB, OK TAFB Technical Specifications 2019

April 2019 Page 1 Section 32 13 14

SECTION 32 13 14

PAVEMENT; NON-AIRFIELD

Part 1 GENERAL

1.1 SCOPE

The Standard Specifications for Highway Construction, as published by the Oklahoma Department of Transportation (ODOT), are adopted as the Tinker Air Force Base Standard Specifications for all non-airfield paving. Non-airfield paving includes, but is not limited to, grading, drainage, drainage structures, roads, streets, parking facilities, storage areas, sidewalks, driveways, bridges and all associated signage, markings, lighting and signalization. The edition shall be the edition current on the date of the Notice to Proceed (NTP) with design.

1.2 DEFINITIONS

Certain terms included in the ODOT Standard Specifications shall incorporate the following substitutions in their use:

a. For Commission substitute Base Civil Engineer and Contracting

Officer

b. For Department substitute Tinker Air Force Base

c. For Director substitute Base Civil Engineer

d. For Resident Engineer substitute Contracting Officer

e. For Engineer substitute 72 ABW/CE

f. For Materials Division substitute 72 ABW/CE

These substitutions do not in any way alter the requirement that all project correspondence be channelled through the Contracting Officer.

1.3 REFERENCES

UNITED STATES DEPARTMENT OF DEFENSE; UNIFIED FACILITIES CRITERIA

UFC 1-200-01 General Building Requirements

UFC 3-201-01 Civil Engineering

OKLAHOMA DEPARTMENT OF TRANSPORTATION (ODOT)

ODOT SSHC Standard Specifications for Highway Construction

Tinker AFB, OK TAFB Technical Specifications 2019

April 2019 Page 2 Section 32 13 14

Part 2 PROCEDURE

2.1 REVISIONS, AMENDMENTS AND CLARIFICATIONS

2.1.1 Contract specific revisions, amendments and clarifications to the ODOT SSHC shall be included in the special conditions of the Contract.

2.1.2 General revisions, amendments and clarifications to the

ODOT SSHC are as follows:

2.1.2.1 Pay quantities and units shall be as specified in the line items of the IDIQ Contract. For non IDIQ contracts the pay quantities and units shall be as specified in the ODOT SSHC.

2.1.2.2 Concrete strength for roads, streets and parking areas shall be specified as flexural and shall have a minimum strength of 650 psi.

2.1.2.3 All pavements with a thickness (the cumulative total of all layers above the subgrade)of greater than 8 inches shall require a drainage layer and a separation layer. The separation layer may be fabric.

2.1.2.4 All curbs and gutters shall be concrete and monolithic. They shall be placed separate from pavement.

2.1.2.5 When preparing the subgrade, all plant materials and roots shall be removed and the excavation filled with select fill.

2.1.2.6 When working the subgrade, all soft, yielding or other unsuitable material shall be removed and replaced or modified in place until stable.

2.1.2.7 When preparing subgrades, the subgrade shall be proof rolled with a large roller or loaded scraper and visually checked for pumping even if it meets compaction requirements. Pumping subgrade material shall be removed or treated until it is stable.

2.2 MATERIALS

2.2.1 All materials shall be from a source listed on the ODOT

Approved Material Supppiers List.

2.2.2 All materials shall be ODOT approved for the use intended.

-- End of Section --