32 01 17.pdf

PDF 14 KB Posted

Attached to
WWYK260004 - REPAIR STRUCTURAL INTEGRITY, B1134, POST 34 & NORTH WALL
Solicitation number
FA813727R0001
Issued by

About this file

This document is a Technical Specification for crack sealing work in asphalt concrete pavements at Tinker Air Force Base, Oklahoma, dated April 2019.

The specification covers furnishing and installation of materials for crack sealing of asphalt concrete pavements, with products required to match existing materials or be directed by the Contracting Officer. Installation procedures must follow product manufacturer recommendations, and demolition and removal of materials shall be performed as necessary to support the work. Required products include Liquid Asphalt complying with ASTM D 2027, Grade MC-250; Emulsified Asphalt complying with ASTM D 977, Grade MS-2; Sealing Compound complying with Federal Specification SS-S-1401; and Fine Aggregate consisting of natural sand or crusher dust with a maximum size of 1/8 inch, free of clay and organic matter.

Execution requirements specify that all cracks must be cleaned of dirt and debris using portable air compressor equipment with hose and nozzles, followed by stiff bristle brooms. Heating equipment for liquid asphalt must be mobile with agitating devices, thermometers, regulating equipment for heat control, and gravity-type draw-off valves. Heating equipment for sealing compound shall consist of mobile, double boiler agitator-type kettles with oil medium for heat transfer and circulation capability. Installation procedures require sealing all cracks 1/8 inch wide and wider, with cracks 1/2 inch wide and wider first filled with a fine sand slurry and emulsified or liquid asphalt before final sealing. Temperature control is critical to ensure proper flow and complete crack filling without air entrapment. The contractor is responsible for all traffic control barricades and flagmen to prevent vehicle access to sealed cracks until sealer has cooled sufficiently.

View the file

Other files

File Type Posted
07 42 13.pdf PDF
32 01 16.pdf PDF
10 44 16.pdf PDF
10 14 00.10.pdf PDF
07 41 13.pdf PDF
31 23 15.pdf PDF
31 00 00.pdf PDF
03 30 00.pdf PDF
06 10 00.pdf PDF
09 90 00.pdf PDF
02 41 00.pdf PDF
32 13 14.pdf PDF
32 01 14.pdf PDF
COPY of Site Visit Sign-in Sheet_10.22.2026.pdf PDF
00 70 00.pdf PDF
00 80 05.pdf PDF
00 80 00.pdf PDF
01 42 00.pdf PDF
00 72 00.pdf PDF
01 33 16.00 10.pdf PDF
00 71 00.pdf PDF
01 78 23.pdf PDF
01 45 00.00 10.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
01 32 16.00 20.pdf PDF
01 78 00.pdf PDF
01 33 00.pdf PDF
01 50 00.pdf PDF
RFI QA RESPONSES - WWYK260004 - REPAIR STRUCTURAL INTEGRITY B1134 POST 34 NORTH WALL_COR.pdf PDF
Solicitation - FA813727R0001.pdf PDF
Wage Determinations.pdf PDF
Att.10_260004_Drawings.pdf PDF
Att.9_260004_Submittal Register.pdf PDF
Att.8_260004_MACB_SOW.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tinker AFB, OK TAFB Technical Specifications 2019

April 2019 Page 1 Section 32 01 17

SECTION 32 01 17

CRACK SEALING IN ASPHALT CONCRETE PAVEMENTS

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

This specification covers the furnishing and installation of materials for crack sealing of asphalt concrete pavements. Products shall match existing materials and/or shall be as directed by the Contracting Officer. Installation procedures shall be in accordance with the product manufacturer's recommendations. Demolition and removal of materials shall be as required to support the work.

PART 2 PRODUCTS

2.1 LIQUID ASPHALT

Liquid Asphalt shall comply with ASTM D 2027, Grade MC-250.

2.2 EMULSIFIED ASPHALT

Emulsified Asphalt shall comply with ASTM D 977, Grade MS-2.

2.3 SEALING COMPOUND

Sealing Compound shall comply with Fed. Spec. SS-S-1401.

2.4 FINE AGGREGATE

Fine Aggregate shall be natural sand or crusher dust and have a maximum size of not more than 1/8 inch and be free of clay and organic matter.

PART 3 EXECUTION

3.1 PREPARATION:

3.1.1 All Cracks to be sealed shall be cleaned of dirt and

debris.

3.1.2 Crack Cleaning Equipment shall consist of a portable air compressor with hose and nozzles for directing air directly into cracks and stiff bristle brooms.

3.1.3 Heating Equipment for Liquid Asphalt shall be mobile and shall be equipped with an agitating device for stirring material during heating, a thermometer, regulating

Tinker AFB, OK TAFB Technical Specifications 2019

April 2019 Page 2 Section 32 01 17 equipment for heat control, and a gravity type, draw off valve.

3.1.4 Heating Equipment for Sealing Compound: Unless otherwise required by the manufacturer's recommendations, the equipment shall be mobile and shall consist of double boiler, agitator type kettles with oil medium in the outer space for heat transfer. The applicator unit shall be so designed that the sealant will circulate through the delivery hose and return to the inner kettle when not sealing cracks.

3.1.5 Application Equipment shall have a spout or nozzle of such size that the sealing material will be placed in the cracks without entrapping air in cracks or spreading material on adjacent pavement surface.

3.2 INSTALLATION

3.2.1 Sealing Compound

All cracks one eighth of an inch wide and wider shall be sealed.

The application temperature for sealing compound shall comply with Fed. Spec. SS-S-1401. Cracks one half of an inch wide and wider shall be filled with a slurry of fine sand and an emulsified asphalt or liquid asphalt. After the slurry has cured, cracks shall be sealed with liquid asphalt or emulsified asphalt and lightly sanded.

3.2.2 Liquid and Emulsified Asphalt Sealer

The temperature shall be varied so that it flows freely into cracks and completely fills cracks without entrapping air. Cracks shall be free of moisture before filling and shall be filled slightly above the pavement surface. When excess sealer has been removed, the sealer shall be covered with fine sand.

3.2.3 Traffic Control

Traffic will not be permitted over sealed cracks until the sealer has cooled so that vehicle tires do not pick it up. The Contractor will be responsible for all barricades and flagmen necessary to control traffic.

- End of Section -

PART 1 GENERAL
PART 2 PRODUCTS
2.1 Liquid Asphalt
2.2 Emulsified Asphalt
2.3 Sealing Compound
2.4 Fine Aggregate
part 3 EXECUTION
3.1 Preparation:
3.1.1 All Cracks to be sealed shall be cleaned of dirt and debris.
3.1.2 Crack Cleaning Equipment shall consist of a portable air compressor with hose and nozzles for directing air directly into cracks and stiff bristle brooms.
3.1.3 Heating Equipment for Liquid Asphalt shall be mobile and shall be equipped with an agitating device for stirring material during heating, a thermometer, regulating equipment for heat control, and a gravity type, draw off valve.
3.1.4 Heating Equipment for Sealing Compound: Unless otherwise required by the manufacturer's recommendations, the equipment shall be mobile and shall consist of double boiler, agitator type kettles with oil medium in the outer space for heat transfer...
3.1.5 Application Equipment shall have a spout or nozzle of such size that the sealing material will be placed in the cracks without entrapping air in cracks or spreading material on adjacent pavement surface.
3.2 Installation
3.2.1 Sealing Compound
3.2.2 Liquid and Emulsified Asphalt Sealer
3.2.3 Traffic Control