This is a Submittal Register for a construction contract at Tinker Air Force Base for the "Repair Roadways, Parking at Munitions Area" project. The document serves as a tracking tool for all required contractor submissions throughout the project lifecycle, from preconstruction through closeout phases.

The register identifies 54 line items of required submittals, organized by specification section and submission type. Preconstruction submittals include health and safety plans, equipment and material storage locations, environmental compliance documents (Storm Water Pollution Prevention Plan, Hazardous Material Request/Authorization), construction schedules, quality control plans, and design documentation. Material certificates and test reports are required for lime, separation fabric, ODOT Type A materials, prime coat, and asphalt mix designs. Certificates required throughout construction include safety meetings, FOD awareness training, fire ant compliance agreements, and monthly hazardous material usage and debris management reports. Closeout submittals include working as-built drawings, record drawings, and DD Form 1354. The register tracks submission dates, approval authority (Government or A/E Reviewer classification), material needed-by dates, action codes, and routing between the contractor, reviewing authorities, and approving authorities. Specific timing requirements are noted, such as baseline schedules due within 10 days of Notice to Proceed, airfield construction waivers due by the 5th of the month with 45-day processing time, and monthly reports due the first week of each month. Weekly contract progress reports utilizing AF Form 3065 are required throughout the contract duration.

View the file

Other files

File Type Posted
Att10_190230_SOW (REVISED).pdf PDF
RFI_s_Gov Response Updated Drawings_WWYK190230_21JULY2026_REV1.pdf PDF
Solicitation Amendment - FA813726R00270002.pdf PDF
Solicitation Amendment FA813726R00270002 SF 30.pdf PDF
WWYK109230 Repair Arnold Ave Between H Ave and M Ave RFI_s_Gov Response.pdf PDF
Solicitation Amendment - FA813726R00270001.pdf PDF
RFI Gov Response Updated Drawings_WWYK150185.pdf PDF
Solicitation Amendment FA813726R00270001 SF 30.pdf PDF
WWYK150185 Repair Roadways Parking at Munitions Area_RFI_s_Gov Response.pdf PDF
WWYK150185 - 190230 Site Visit Sign in Sheet.pdf PDF
Tinker AFB Visitor Map_.pdf PDF
SOW Att 01_Appointment of Security Representative Template 496.docx DOCX document
2026 TAFB Mechanical Standard_signed.pdf PDF
2026 TAFB Electrical Standard - Signed.pdf PDF
LightingFixtureSchedule.xlsx XLSX spreadsheet
2026 TAFB FIRE PROTECTION STANDARD.pdf PDF
2020 TAFB Facility Standard.pdf PDF
WWYK190230_Drawings.pdf PDF
Att10_150185_SOW.pdf PDF
Att10_190230_SOW.pdf PDF
Solicitation - FA813726R0027.pdf PDF
Wage Determination OK200260049.pdf PDF
WOSB Sec LM 22May26 Update (v3)_.pdf PDF
2 EAL List - BLANK to Contractors.xlsx XLSX spreadsheet
Att11_190230_Submittal Register_v4.pdf PDF
Att12_150185_Drawings.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

Line

Acti vity

Transm ittal #

Specification Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

1 00 71 00 01 Preconstruction Submittals Health and Safety Plan 1.3 G

2 00 71 00 01 Preconstruction Submittals Entry Authority List 1.5.2

3 00 71 00 01 Preconstruction Submittals Vehicle Entry Authority List 1.5.2 G

4 00 71 00 01 Preconstruction Submittals Equipment and Material Storage 1.5 G

5 00 71 00 01 Preconstruction Submittals Designated Waste and Disposal Areas 1.5 G

6 00 71 00 01 Preconstruction Submittals Airfield Construction Waiver 1.5 G

Must be turned in by the 5th day of the month to make that month Waiver Package. Provide editable form to the CO to be forwarded to Community Planning. Allow 45 days for processing.

7 00 71 00 01 Preconstruction Submittals FAA Form 7460-1 1.5.3 G

8 00 71 00 07 Certificates Safety Meetings 1.3

9 00 71 00 07 Certificates FOD Awareness and Prevention Training 1.4

10 00 72 00 01 Preconstruction Submittals Restoration Plan 1.3.2 G

11 00 72 00 01 Preconstruction Submittals Storm Water Pollution Prevention Plan 1.3.3.2 G

12 00 72 00 01 Preconstruction Submittals AF Form 3952 Chemical/Hazardous Material Request/Authorization 1.4 G

13 00 72 00 01 Preconstruction Submittals Spray Painting Plan 1.9 G

14 00 72 00 01 Preconstruction Submittals Environmental Management System Awareness Training 1.1

15 00 72 00 03 Product Data Affirmative Procurement Documentation or Green Statement 1.3.10 G Provide only one. Reference specification for additional information

16 00 72 00 07 Cerificates Fire Ant Federal Compliance Agreement or state phyto-sanitary certificate 1.3.4.1 G

17 00 72 00 07 Cerificates Monthly Hazardous Material Usage Report 1.4 G Provide 1st week of each month during construction

18 00 72 00 08 Manufacturer's Instructions Safety Data Sheets/Material Safety Data Sheets 1.4

19 00 72 00 11 Closeout Submittals Notice of Termination (ODEQ Form 640-572) 1.3.3.2 G

20 00 72 00 - Attch 5 01 Preconstruction Submittals Construction Debris Analysis Plan 1.2.3 G

21 00 72 00 - Attch 5 07 Certificates Monthly Debris Management Report 2 G Provide 1st week of each month during construction

22 01 32 16.00 20 01 Preconstruction Submittals Baseline Construction Schedule 1.2 G Provide within 10 days of NTP.

23 01 32 16.00 20 01 Preconstruction Submittals Baseline Design Schedule 1.2 G Provide within 10 days of NTP.

24 01 32 16.00 20 07 Certificates Monthly Updates 1.4 Provide 1st week of each month during construction, or as directed by CO

25 01 32 16.00 20 07 Certificates 3-Week Look Ahead Schedule 1.6 Provide weekly with the Contract Progress Report

26 01 33 00 01 Preconstruction Submittals Submittal Register 1.8 G

27 01 33 16.00 10 01 Preconstruction Submittals Design Quality Control Plan 1.5.1 G

28 01 33 16.00 10 01 Preconstruction Submittals Initial Design Conference 1.5.2.2

29 01 33 16.00 10 01 Preconstruction Submittals Preconstruction Conference 1.5.2.3

30 01 33 16.00 10 01 Preconstruction Submittals DCM Procedures 3.5.1 G

31 01 33 16.00 10 01 Preconstruction Submittals Submittal Register 3.8.4 G

32 01 33 16.00 10 05 Design Data Design and Code Checklists 1.7.1 C

33 01 33 16.00 10 05 Design Data Conference Documentation 3.7.3

34 01 33 16.00 10 05 Design Data Final Design Submittals 3.8 R

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES APPROVING AUTHORITY

TITLE: Tinker AFB General Requirements Specification (Div 00-01)

SUBMITTAL REGISTER

JOB NAME: Repair Roadways, Parking at Munitions Area

LOCATION:

CONTRACT NO:

CONTRACTOR:

Submittal Register_v3_03/07/22

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

Line

Acti vity

Transm ittal #

Specification Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES APPROVING AUTHORITY

35 01 33 16.00 10 05 Design Data Design Complete Documents 3.9 C

36 01 33 16.00 10 11 Closeout Submittals DD Form 1354 3.8.5 A

37 01 45 00.00 10 01 Preconstruction Submittals Quality Control (QC) Plan 3.2 G

38 01 45 00.00 10 01 Preconstruction Submittals Additional Requirements for Design Quality Control (DQC) Plan 3.2.2 G

39 01 45 00.00 10 05 Design Data Discipline-Specific Checklists 3.2.2

40 01 45 00.00 10 05 Design Data Design Quality Control 3.9.1

41 01 45 00.00 10 06 Test Reports QC Documentation 3.9 Provide weekly with the Contract Progress Report

42 01 50 00 01 Preconstruction Submittals Request for Contractor Staging Area 1.1 G

43 01 50 00 01 Preconstruction Submittals Photographic Record 1.3

44 01 78 00 03 Product Data Warranty Letter 1.7.1

45 01 78 00 11 Closeout Submittals Working As-Built Drawings 3.1 G Provide (2) electronic sets (optical media) and

(2) hard copies

46 01 78 00 11 Closeout Submittals Record Drawings 3.3 G Provide (2) electronic sets (optical media) and

(1) hard copy

47 01 78 00 11 Closeout Submittals DD FORM 1354 3.6 G

48 01 78 00 11 Closeout Submittals Checklist for DD FORM 1354 3.6 G

49 SOW 07 Certificates Contract Progress Report(s) 2.4 G Provide weekly throughout life of contract.

Utilize AF Form 3065, Contract Progress Report (or equal)

50 SOW Material Certificates Lime 2.6.2.1 (b) G

51 SOW Material Data Separation Fabric 2.6.2.1 (c) G

52 SOW Material Certificates ODOT Type A, field and lab reports 2.6.2.1 (d) G

53 SOW Material Certificates Prime Coat 2.6.2.1 (e) G

SOW Material Certificates

Asphalt, Mix Design, Lab Reports for each used 2.6.2.1 (a) G