This document is a Pre-Bid Request for Information (RFI) response memorandum from the Department of the Air Force, Headquarters 72 Air Base Wing at Tinker Air Force Base, Oklahoma, for Project WWYK180061 – Repair HVAC System – B3707. The document contains detailed responses to 73 technical and procedural questions from potential contractors, covering aspects such as fire sprinkler system removal and replacement, electrical systems, lighting, door hardware, and project bidding process details.
The solicitation follows a two-step sealed bidding process, with Phase One requiring technical proposals without pricing, and Phase Two involving price submissions. Key project details include replacing HVAC systems, potential modifications to sprinkler systems, electrical upgrades, and clean room renovations. The government anticipates awarding the contract in November 2025, with funding already secured. Contractors must submit comprehensive technical proposals first, with only technically acceptable proposals advancing to the price bid stage. The project emphasizes detailed documentation, compliance with existing standards, and careful coordination of mechanical, electrical, and architectural modifications.
View the file
Other files
Show 40 more
Latest 50 of 309 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
HEADQUARTERS 72 AIR BASE WING (AFMC)
TINKER AIR FORCE BASE OKLAHOMA
28 Aug 2025
MEMORANDUM FOR AFSC/PZIOC (ATTN: Stephen Palmer)
THROUGH: 72 ABW/CENM
FROM: 72 ABW/CEED
Tepa Companies
SUBJECT: Pre-Bid RFI Responses Project: WWYK180061 – Repair HVAC System – B3707
Reference: Memo, 19 Aug 2025, Pre-Bid RFIs, WWYK180061 – Repair HVAC System – B3707
1. This office reviewed the referenced RFIs for the subject project and provided answers below. Please forward to the contractor(s) for their use in preparing proposals
RFIs ARE ONLY PERMITTED DURING PHASE ONE TECHNICAL PROPOSAL PROCESS.
NO RFIs ARE TO BE SUBMITTED DURING PHASE TWO PRICE BID PROCESS.
1. Drawing FD105 Demo Keynote #1 states to remove existing sprinklers, escutcheons, drops and plug branch line outlets. Drawing FX101 and Div-21 Specifications indicate a complete system is to be installed.
a. Are existing sprinklers and drops to be removed and replaced with new or are entire systems to be removed and replaced?
Government Response: Per the SOW, 4.7.2 –
4.7.2 Fire Sprinkler System
(1) To accommodate the renovation of the HVAC Systems remove:
(a) Existing sprinkler system heads
(b) Escutcheons
(c) Pipe drops back to branch line and provide temporary cap/plug as required to allow for removal of ceiling, HVAC units and the demolition of HVAC ducts.
(d) Document existing sprinkler head temperature rating, sprinkler head orientation (pendent, upright, side wall, etc.) sprinkler head orifice, sprinkler drop pipe sizes and drop length (including Fitting).
(e) Discard sprinkler heads, escutcheons, drop piping and fittings from branch lines.
(f) Removed materials will not be reused.
b. If only sprinklers and drops are being removed and replaced, will the project require the existing systems to be hydraulically calculated?
Government Response: Yes..
2. Drawing FX501 Detail 2:
a. Are automatic air vents to be added to existing systems if only sprinklers and drops are being replaced?
Government Response: Yes, as required to make system code compliant.
b. If so, please identify if any of the systems will require multiple air vents.
Government Response: Contractor’s QFPE shall evaluate to determine if multiple vents are required.
c. Specification 21 13 13 § 2.4.5 requires air vents to be piped to the building exterior. May drain piping be eliminated if a dual air vent is utilized?
Government Response: The referenced Specification is from the Tinker Guide Specification and sets the standards for design. Provide as specified.
3. Does reverting back to Step-One require offerors to resubmit their original technical proposals (Phase One submissions), or will the previously submitted technical proposals still be considered valid for evaluation purposes after the government addresses the current round of RFIs?
a. Government Response: After this set of RFI responses are provided to the offerors, a revised technical proposal (phase one submission) will be required to be submitted and received a full technical evaluation. After reverting back to phase one, the original proposals are no longer valid.
b. Ensure your phase one technical proposal also includes all previously provided RFI responses. These can be found on SAM.Gov.
4. Confirm DOAU is not required based on Basis of Design Narrative Paragraph 7.2.6.
Government Response: Approval was received from the COR, in coordination with AFCEC/COSM, to deviate from the specific requirement on 6 February 2023 with the reasoning that this project is a one-for-one replacement of existing equipment, as such, there is no retro-active requirement to upgrade a previous design to include DOAS.
5. Existing design documents indicated that existing RM 158 PMEL requirements 100% Outside Air reused existing Exhaust fans. Typically, PMEL’s (Precision Measurement Equipment Labs) have very restrictive temperature and humidity requirements. Is RM 158 still used as a PMEL? Can Criteria for Rm 158 be provided?
Government Response: Pending User response
6. There are currently Mechanical Closets in Rms 138 and 155 that house Computer room units for Chilled water, to Refrigerant piping. Are these mechanical spaces to remain?
Government Response: The “FOR REFERENCE ONLY” drawings suggest to remove the water to refrigerant unit and associated piping. However, this is a concept design-build, and the DOR will be responsible for verifying these conditions in their final design.
7. Currently AHU-5 is a plenum return system. Will return air be required for the replacement system?
Government Response: Return air from the various space AHU-5 is serving will be required.
8. Air Handling Unit Schedule Note #8 ask for Redundant VFD’s for AHU-1, 2 &3 and MAU-1. Would a VFD per fan be sufficient since there is a Redundant Fan requested?
Government Response: For AHU’s of this size VFD’s for fans is acceptable.
9. Is roof insulation thickness known? Air Handling Schedule indicates 12” roof curb. Will a TAFB 18” Curb be required to meet TAFB Standard 8” Flashing at Roof Curbs?
Government Response: Roof insulation is shown as R-25 and R16.1 as shown on the As-Built drawings. Thickness is not provide in the As-Built drawings. Based on current tables and assuming Polyiso insulation this would suggest 4” to 4 ½” of insulation. Use the TAFB 18” curb.
10. What Refrigerant types are acceptable for new chillers?
Government Response: Provide equipment with approved refrigerants as listed in the 2025 Tinker AFB Mechanical Standard. If the proposed chiller uses a refrigerant not listed it will be considered for approval if approved by the EPA.
KTR is to design and specify magnetic lift chillers of the approved chiller manufacturers as listed in the Tinker AFB Mechanical Standard.
11. Please confirm if new sprinkler heads are to be moved to center of tile.
Government Response: Yes.
12. Shall CO Detectors be installed in mechanical rooms?
Government Response: Design shall provide required detectors IAW UFC 3-200-01 DOD Building Code and UFC 3-410-01 HVAC Systems.
13. The specifications require ceiling panels with CAC > 39, NRC 0.95, and Light Reflectance ≥ 0.75. For purposes of consistent and competitive pricing, please confirm whether these performance values are strict minimums, or if panels with slightly lower NRC (0.80–0.90) but CAC ≥ 40 would be acceptable, recognizing that this may provide meaningful cost savings with negligible performance difference.
Government Response: The Specification is the Tinker Guide Specification and sets the standards for design. Provide as specified.
14. In Room 139A (see snip below), do the highlighted green interior walls require full-height construction to the deck, including fire taping and sealing to the underside of the deck?
Government Response: Walls shall be designed and constructed to meet the requirements of the indicated Class Clean Room.
a.
b. Additionally, please confirm the following related conditions:
i. Should the exterior (North and East) perimeter walls, which include a parapet, also be sealed to the deck?
Government Response: Walls shall be designed and constructed to meet the requirements of the indicated Class Clean Room.
ii. There is existing roof insulation that has fallen onto the metal sloped ceiling along the North, East, and South walls—does this need to be removed or addressed as part of the scope?
Government Response: Any displaced insulation shall be removed and new insulation installed in its original location.
iii. Is any additional fire rating or sealing required for the new interior walls beyond standard construction?
Government Response: It is not the intent to add additional fire rated assemblies.
However, if the DOR determines the requirements of the project require additional fire rated assemblies, then those assemblies shall be provided and penetrations sealed.
iv. Should the floor trench at the new clean room wall also be sealed off as part of the fire or containment requirements?
Government Response: Trench sealing will be determined by the DOR if required to meet the indicated Class Clean Room specification.
v. Will there be a Blower Door Test required for the Clean Room?
Government Response: Yes.
15. It was brought to our attention that there is a current furniture and equipment plan in place for rooms 139 & 139A. Can you please confirm which existing furniture and equipment are intended to remain in place, and which items (if any) will be removed or replaced?
Government Response: Pending User response.
16. Please confirm temporary cooling is not required for the workspace.
Government Response: The occupants of the building will be relocated during construction; therefore temporary cooling will not be required.
17. Please confirm temporary heating is not required for the workspace.
Government Response: The occupants of the building will be relocated during construction; therefore temporary heating will not be required.
18. In lieu of HYDROMULCH, per SOW Issued 07 Jan 2025, para 4.2.1(5) would new sod be acceptable for areas disturbed during construction?
Government Response: Sod is acceptable provide the sod and installation is in accordance with Tinker Base Standards
19. SOW issued 07 2025, para 4.2.2(1) states to provide positive drainage away from B3707. Is grading limited to sheet C103 Detail 1 from the drawing set with issue date 6 March 2023?
Government Response: The “FOR REFERENCE ONLY” drawings suggest grading is limited to what is shown on C-103. However, this is a concept design-build, and the DOR will be responsible for verifying these conditions in their final design.
20. If grading area is not limited to sheet C103 Detail 1 please indicate limits of grading to be provided.
Government Response: See response to Pre-Bid RFI 19 above.
21. Drawing set dated 6 March 2023 with Revision 1 dated 4/1/2024 - Sheet AD101 keynote 2 states to remove furniture partition wall within room 106 LASBB. Confirm furniture partition wall shall be demolished and removed offsite.
Government Response: The “FOR REFERENCE ONLY” drawings suggest to remove the systems furniture wall. However, this is a concept design-build, and the DOR will be responsible for verifying these conditions in their final design.
22. Pre-Bid RFI responses dated 08 May 2025, #9 state that contractor is responsible for removing and reinstalling equipment and hoods as necessary to fulfill the requirements of the project scope.
a. Please provide:
i. Make & model of equipment.
Government Response: Pending User response
ii. Provide POC for who currently maintains this equipment.
Government Response: Pending User response
23. Damage to existing walls often occurs during the types of ceiling demolitions described in the drawings dated 06 March 2023 with Revision 1 dated 4/1/2024 – Sheets ACD101
– ACD104. Shall all contractors plan to patch & paint all existing & new walls within the project area?
a. Recommend Government to define scope extent to level bidders’ scope which will ensure Government intent is fulfilled.
Government Response: Refer SOW Issued 07 Jan 25 para 1.9 EXISTING
WORK.
“The Contractor shall repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the CO. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work star”
24. SOW Issued 07 Jan 2025, para 4.4.7 states existing wall covering to be repaired by re-gluing wall covering to wall. Please confirm Government intent is to have these areas repaired or shall contractor remove all wall covering, prep, tape, bed, & paint these areas to provide uniform finish.
Government Response: The Government intent is to repair these areas.
25. SOW issued 07 Jan 2025, para 4.4.7 states to paint all wall areas with new coat of paint.
Please confirm whether this requirement applies only to new or modified wall surfaces created by the project, or to all wall surfaces (including existing walls not otherwise impacted) within the project spaces.
Government Response: The Government intent is this requirement applies to new or modified walls.
26. If the intent is to repaint all existing and new walls within the project area, please confirm whether replacement of the existing cove base at those walls is also required to achieve a consistent finished appearance. We would recommend replacement in this case to avoid mismatched finishes.
Government Response: Replace the cove base.
27. Corridors 129 & 142 have existing multipart paint applied. Is it the intent to match the existing paint finish in the corridors or to repaint with a solid color to ease of facilitate maintenance?
Government Response: Repaint with a solid color.
28. If the intent to maintain the existing multipart paint in corridors 129 & 142. Please provide product information for paint finish.
Government Response: Repaint with a solid color.
29. Provide direction on which corner guard scope contractors shall price.
a. SOW issued 07 Jan 2025, para 4.4.7 states to provide 3” wide (wings) 6’ tall stainless steel corner guards at all outside corners of walls and columns.
i. Please confirm new corner guards shall be installed on all outside corners.
Government Response: Yes.
ii. Please confirm if new corner guards shall be 6’
Government Response: Yes.
b. Drawings dated 06 March 2023 with Revision 1 dated 4/1/2024, sheet A-100 keynote 2, states to provide 3” SS corners guards 8’ tall at all new gypsum wallboard outside corners, typ.
i. Please confirm if new corner guards shall be installed on new gypsum wallboard walls only.
Government Response: Per SOW Issued 07 Jan 25, para 4.4.7 – Corner Guards are to be installed on all corners of walls and columns.
ii. Please confirm new corner guards shall be 8’.
Government Response: Per SOW Issued 07 Jan 25, para 4.4.7 – Corner Guards are to be 6’ tall.
30. SOW issued 07 Jan 2025, para 4.4.7 states to provide translucent patterned window film to exterior windows.
a. Please provide basis of design for translucent patterned window film.
Government Response: Pending User response
31. The “Design Narrative – WWYK180061 – Repair HVAC System – B3707” para 2.2 states the floor finish within the cleanroom is to remain per conversations with the users.
a. Please confirm contractor is required to cover and protect existing floor covering from drywall ceiling finishing & paint damage within this space.
Government Response: Yes.
32. Drawings dated 06 March 2023 with Revision 1 dated 4/1/2024, Sheet AC102 indicates new suspended gypsum board ceiling system in room 139A.
a. Does the contractor need to provide new access panels for mechanical services?
Government Response: Yes. Also, include access panels for all electrical/low voltage control panels and plumbing valves, above the gypsum board ceiling system. If possible coordinate mechanical access panels in locations where access to panels or valves can be accessible via mechanical access panels or provide separate access panels for these items, if not practical use Mech access panels. Ensure that access to any of the MEP items is not impeded by other trades which is installing their distribution system: for example, plumbing lines, electrical conduits, as a minimum.
33. Drawings dated 06 March 2023 with Revision 1 dated 4/1/2024, Sheet AC102 indicates new suspended gypsum board ceiling system in room 139A. Sheet E102 keynote 2 states to clean, reinstall, and reconnect all existing light fixtures.
a. Are the existing light fixtures scheduled for re-use compatible with a new suspended gypsum ceiling within room 139A?
Government Response: See Lighting Fixture Schedule on Sheet E-501. The light fixtures for Rooms 139A, 154A, 154B, 154C & 154B are recommended. The existing light fixtures are owned by Honeywell. They shall be removed, location cataloged, cleaned, protected, and turned over to the government.
34. Please clarify SOW paragraph 4.14.1.4(b) and reference design narrative paragraph 8.5.
Is it the intent to perform an arc flash study for any new electrical distribution equipment, but then install “generic” arc flash labels?
Government Response: Perform a flash study and install the “generic arc flash labels.
Flash study shall be turned over to Base Civil Engineering.
35. New metallic screen walls are mentioned in structural portion of the SOW. Is it necessary to incorporate these screen walls into the LPS?
Government Response: Lighting Protection System (LPS). Comply with UFC 3-575-01 (Lighting and Static Electricity Protection Systems) and Air Force Manual 32-1065 (Grounding and Electrical Systems.)
36. Does SOW paragraph 4.14.1.3(b) require a UL Master Label for the facility?
Government Response: The UL Master Label is a certification that indicates that the LPS has been installed in accordance with the relevant acceptable standards.
37. If deficiencies in the existing LPS are found during the UL LPS inspection required by SOW paragraph 4.14.1.3(b), will the Gov’t have the deficiencies repaired “by others?”
Government Response: The contractor is responsible for providing a complete and certified LPS: all system repairs shall be the contractors’ responsibility.
38. Since the SOW does not require a complete new LPS would a UL letter of findings be sufficient in lieu of a UL inspection certificate?
Government Response: Provide UL LPS inspection Certificate.
39. In SOW paragraphs 4.15 and 4.15(2), are components of the contract and components of the solicitation listed in descending precedence?
Government Response: Yes. Follow Contract of Precedence as outlined in Statement of Work (dated 07 Jan 2025), paragraph 4.15.
40. In SOW paragraph 4.14.1.2, does circuit breaker “breaking capacity” refer to short circuit interrupting rating?
Government Response: Yes. Circuit Breaker “breaking capacity” refers to short circuit interrupting rating.
41. SOW paragraphs 4.13.1.1 and 4.14.1.1 require LED light fixtures and other ceiling mounted devices in areas affected by HVAC modifications to be removed, protected, and reinstalled. Would it be acceptable for these items to be tied up, out of the way, and protected from damage during demolition and returned to the ceiling after all the HVAC work is completed?
Government Response: Follow requirements as outlined in reference paragraphs above.
42. Reference drawings E-101 through E-104 include a general note that requires fire alarm conduit fittings to be threaded or compression type and prohibits set screw connectors.
Is this requirement limited to fire alarm conduits or do the same requirements and restrictions apply to conduits of other systems?
Government Response: General notes on reference drawing only applies to fire Alarm conduits.
43. Detail 1, sheet E-501 includes a note “all components shall be stainless steel.” This note implies that all modular channel is to be stainless steel. Would it be acceptable for modular channel and related hardware to be protected from corrosion in some other fashion?
Government Response: Provide details of proposed recommendations and provided benefits. If not available comply with note that all components shall be stainless steel.
44. SOW includes no mention of lighting controls. Are existing lighting controls to be retained and remain in use?
Government Response: See Sheet E-501: provide new occupancy sensors. Any existing occupancy sensors shall be removed and transferred to the government. Also, see Sheet ED102 Keyed Note Five (5).
45. Reference drawings E-105 and E-501 show new occupancy sensors. SOW does not include any mention of occupancy sensors. Are new occupancy sensors required? If so, where?
Government Response: Reference Sheet E-105 for conceptual locations of occupancy sensors. The following rooms 139A, 154, 154A, 154B, 154C, and 154D are to receive occupancy sensors. Conceptual lighting control details, see E-502.
46. SOW does not mention new clean room lighting in Room 139A. Is new clean room lighting for this room required?
Government Response: Clean room lighting is required, See Sheet E-105 and E-501 Lighting Fixture Schedule.
47. SOW paragraph 4.13.1.1 states to remove LED fixtures within the HVAC modified space. Reference drawing ED-101 keynote 2 states to remove all fixtures. Please confirm that SOW paragraph 4.13.1.1 prevails.
Government Response: Reference response it RFI No. 41, above.
48. Reference drawing ED-101 keynote 2 states to remove all conductors associated with removed lighting. The SOW does not include this requirement but does require testing of the existing circuits. Please confirm that existing lighting circuits can be retained and reused, after successful testing.
Government Response: Existing light circuits can be reused after successful testing.
49. Will the Government be issuing a standardized bid schedule to ensure consistent pricing submissions across all offerors?
a. Government Response: A standardized bid schedule will not be provided.
Offerors will provide bid pricing during phase two similar to what they have submitted for any other MACB project.
50. Please confirm the Government’s preferred format for submission of price proposals (e.g., electronic form, hard copy, system upload).
a. Government Response: No preferred format. Offerors will provide bid pricing during phase two similar to what they have submitted for any other MACB project.
51. Should offerors structure price proposals as lump sum submissions, or will an alternative format be required?
a. Government Response: Prices will not be provided until phase two. No pricing is to be submitted during phase one since it is only a technical proposal. However, material and quantities are to be provided. But no unit price nor total prices are to be included. During phase two price bid submissions, you will now include the unit prices and total prices for review.
b. A cover sheet is to be used that will identify the contractor company name along with the individual CLIN prices and Total price. This cover page will be all that will be reviewed during the bid opening process.
52. Does the Government require that price proposals include a detailed cost breakdown (e.g., labor, materials, equipment, subcontractor costs), or will a single consolidated value suffice?
a. Government Response: A full and complete price bid with a detailed cost breakdown as mentioned in the RFI question is to be included.
b. A cover sheet is to be used that will identify the contractor company name along with the individual CLIN prices and Total price. This cover page will be all that will be reviewed during the bid opening process.
53. Will the Government’s evaluation process confirm that all proposed solutions fully meet the minimum performance and design criteria before price proposals are compared?
a. Government Response: During phase one, a full and complete technical proposal is to be submitted for technical evaluation. Offerors are to ensure that it provides enough information to meet the minimum performance and design criteria. Only the proposals found to be technically acceptable will be allowed to move to phase two and provide price bid proposals. Price bid proposals will not be opened or reviewed until the day of bid opening, date to be determined.
b. A cover sheet is to be used that will identify the contractor company name along with the individual CLIN prices and Total price. This cover page will be all that will be reviewed during the bid opening process.
54. Will the Government require offerors to clearly delineate assumptions, exclusions, and deviations from the solicitation requirements in order to validate scope coverage and ensure accurate evaluation across proposals?
Government Response: Any and all assumptions exclusions, and deviations related to this project are to be submitted with the phase one technical proposal for technical evaluation determination. None are to be submitted during phase two price bid process.
55. Can the government please confirm whether certified funding has been secured for this project?
Government Response: Funding for the project is secured.
56. What is the anticipated timeline for award of this contract? If a specific date is not yet determined, could an estimated timeframe for when the award decision will be made be provided?
Government Response: Anticipated estimated award timeframe is during the month of November.
57. Is all new steam piping required to be welded 304 stainless steel?
Government Response: No.
58. Is existing steam piping allowed to remain if it is not 304 stainless steel?
Government Response: Yes.
59. What are the DOAS unit component requirements?
Government Response: Refer RFI 04 above.
60. Where are the additional DOAS units being relocated?
Government Response: Refer RFI 04 above.
61. Where is the new DOAS supply air and exhaust ductwork terminating?
Government Response: Refer RFI 04 above.
62. There is no schedule for the inline preheat pumps. What AHU’s receive them and what is their size?
Government Response: Reference drawings indicate two preheat pumps AHU-8 & MAU-1 and new HWP-1 & HWP-2 pumps. DOR to determine if tertiary pumps are required in addition to replacing the heating water pumps to be located in the mechanical room.
63. Will the crane use be restricted to Saturday’s and Sunday’s, or can we get permission during the week?
Government Response: An Airfield Construction Waiver will be required for crane use even though this project is not located on the Airfield. Crane use will not be restricted as the areas of construction will not be occupied.
64. Regarding the existing boilers, it would be in the best interest of Tinker to replace the bank of boilers with a new set of high-efficiency boilers. The existing boiler controls are on the verge of becoming obsolete and parts will become hard to find.
Government Response: Provide additional boiler(s) as required to meet the load for all AHU’s.
65. Can we get detailed utility plans to help us determine if the natural gas line can be isolated to conduct the underground work?
Government Response: If available contact 72 ABW/CE – Engineering Support, located in B400.
66. Will there be any requirements for temporary heating and cooling?
Government Response: Refer RFI 16 and 17 above.
67. Section 4.9.1 says all existing steam piping to remain shall be cleaned or replaced if required. Please specify what will determine if the pipe replacement is required.
Government Response: Upon completion of steam piping construction and connection to existing piping pressure testing shall determine if any repairs or replacement is required.
68. Section 4.10.2 requires All AHU’s will be provided with external pipe chases sized to fit all piping and accessories interior with a hinged access door. The referenced plans show the three largest AHU-1,2,3 with no pipe chases. Please verify if pipe chases are required for AHU-1,2 and 3.
Government Response: Pipe chases within the AHU insulated envelope are required.
69. On Sheet A-504 the Door Schedule indicates the Hardware Set required for each Door location, however the Specification Section 08 71 00 Door Hardware does not include any hardware sets. Please provide Hardware Sets for each door location on the indicated.
Government Response: The “FOR REFERENCE ONLY” drawings and specification do not identify the hardware sets. However, this is a concept design-build, and the DOR will be responsible for this information in their final design.
70. Division 08 - Openings do not indicate what type of Door & Frame is required (other than Hollow Metal). There are specifications for Steel, Aluminum, Forced Entry, Sectional Overhead Doors, Aluminum Framed Entrances & Storefronts, Aluminum Windows, Steel
Windows, Wood Windows, Blast resistant tempered glass windows, etc. however, none are shown or indicated on the plans. Please clarify?
Government Response: The “FOR REFERENCE ONLY” drawings , Sheet A-504, indicates the intent of the door and frame material. The specification referenced is from the Tinker Guide Specifications and will be edited by the DOR for the final design
71. Spec. Section 13 34 19 - Metal Building Systems - Please clarify if this is a requirement?
Government Response: There is no requirement. The referenced Section is from the Tinker Technical Guide Specifications. Not all Sections are required. The DOR will select the required sections for the final design documents.
72. Are any of the new doors and frames to be STC Rated? Fire-Rated?
Government Response: The “FOR REFERENCE ONLY” drawings , Sheet A-504, indicates the doors intent of which doors are fire-rated and which doors have a STC rating. However, this is a concept design-build, and the DOR will be responsible for verifying these conditions in their final design.
73. As a reminder to the offeror, 2-Step Sealed Bidding process is as follows:
a. Step-One – conduct the initial site visit with prime contractors (offerors) and their subcontractors. After the initial site visit the offeror(s) are to submit RFIs for a government response. RFI government responses will be provided to the offeror(s), any questions or concerns of the responses should be addressed as a follow on RFI. Once the RFIs have been provided to the offeror(s), a request for technical proposal (RFTP) will be sent to the offeror(s) to submit the technical proposal to the government contracting office. Technical proposals are not to have any pricing, unit nor total, but do need to have all material and quantities as required for any proposal. At this time, no additional RFIs are to be submitted. A technical evaluation of the technical proposal will be conducted and only the offeror(s) found to be technically acceptable will proceed to Step-Two.
b. Step-Two – a request for price bid (RFPB) will be sent to all offerors that had Step-One found to be technically acceptable. And a date / time for submission of price bid will be stated. In Step-Two, a cover page of the total price and follow-on pages of full pricing break down to include material unit/total prices. During this step no additional RFIs are to be submitted, and no additional site visits are anticipated but can be requested to assist in developing pricing. After submission of price bids, a bid opening date will be advertised. During the bid opening, only the total submitted bid price from price bid cover page of each offeror will be verbalized. And an apparent low bid offeror will be announced at the bid opening.
A more in-depth price evaluation will be conducted on the apparent low bid offeror’s proposal to determine full acceptability. If low bid offeror’s price bid is found to be unacceptable, the next lowest offeror’s price bid will be evaluated for acceptability.
2. The points of contact for this project are:
a. Glen Kay, Project Manager. PH:734-6917
b. Adam Gibson, Construction Inspector. PH: 736-5028
c. Joshua Wheeler, CSAG Program Manager. PH: 582-4826
d. Billy Deal, Contracting Officer Representative (COR). PH: 739-4975
Glen Kay Arnaud Kouemo Project Manager Contracting Officer Representative 72d Civil Engineering Directorate (Tepa) 72d Civil Engineering Directorate
No Attachment(s):
cc:
Project folder
| 2025-09-03T08:01:56-0500 | |
| KOUEMO.ARNAUD.NGASSEU.1269207600 |
| 2025-09-03T08:04:37-0500 | |
| KAY.GLEN.AMOS.1612399464 |
File details come from the government source that posted it. Updated .