180061_Submittal Register_v4.pdf

PDF 153 KB Posted

Attached to
TINKER AFB 2-STEP COMPETITIVE 8(a) WWYK180061 REPAIR HVAC SYSTEM, B3707
Solicitation number
FA813725R0015
Issued by

About this file

The document is a Submittal Register for a contract to Repair HVAC System at Building 3707, Tinker Air Force Base in Oklahoma. The register details 71 specific submittal requirements across various specification sections, including preconstruction submittals, certificates, product data, design data, test reports, operation and maintenance data, and closeout submittals. Key submittals include entry access lists, health and safety plans, construction schedules, quality control plans, environmental management documents, FAA forms, training plans, and monthly progress reports. The document is classified as a government review document with specific requirements for submission, approval, and documentation throughout the contract lifecycle, emphasizing rigorous documentation and compliance protocols for an HVAC repair project at a military installation.

View the file

Other files

File Type Posted
WWYK180061 Repair HVAC B3707 RFI 004 Clarification Request GK.pdf PDF
180061 - Pre-Bid RFIs - 15 Sep 25 - GK.pdf PDF
180061 - Pre-Bid RFIs - 28 Aug 25 - User response - Combined.pdf PDF
180061 - Pre-Bid RFIs - 28 Aug 25 signed.pdf PDF
WWYK180061 - Pre-Bid RFI 2nd Response COR.pdf PDF
Solicitation - FA813725R0029.pdf PDF
Wage Determination.txt TXT text file
Section M - Evaluation Factors for Award.pdf PDF
WWYK180061 - Pre-Bid RFI ResponseCOR GK.pdf PDF
Section L - Instructions to Bidders (2-Step).pdf PDF
B3707 High Bay East Wall.jpg JPG image
site visit sign in.pdf PDF
00 80 05.pdf PDF
32 01 17.62.docx DOCX document
23 08 00.pdf PDF
10 22 13.pdf PDF
32 17 23.pdf PDF
tinkerafb_INRMP.pdf PDF
USB-010874_TAFB TO3 B3707_HW_RevC_Redlines_04302018.pdf PDF
23 05 48.00 40.pdf PDF
07 53 23.pdf PDF
28 31 33.00 10.pdf PDF
23 05 15.pdf PDF
dafi21-101.pdf PDF
06 41 16.00 10.pdf PDF
23 65 00.docx DOCX document
07 52 00.pdf PDF
32 12 15.docx DOCX document
08 51 23.pdf PDF
32 13 73.pdf PDF
TAFB_SOP_outages_v2.pdf PDF
32 01 22.pdf PDF
TABLE OF CONTENTS_no Anno.docx DOCX document
32 16 13.pdf PDF
23 57 10.pdf PDF
05 12 00.pdf PDF
afman40-201.pdf PDF
10 14 00.10.pdf PDF
2023 TAFB FIRE PROTECTION STANDARD.pdf PDF
32 17 23.docx DOCX document
UMRL.pdf PDF
07 51 13.pdf PDF
07 42 13.pdf PDF
GEOWEB.pdf PDF
07 31 13.pdf PDF
07 24 00.pdf PDF
08 11 16.pdf PDF
afi91-202_afmcsup.pdf PDF
32 16 13.docx DOCX document
afman32-7003.pdf PDF
Show 40 more

Latest 50 of 309 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

Line

Acti vity

Transm ittal #

Specification Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

1 00 70 00 01 Preconstruction Submittals Entry Access List 1.6 G

2 00 70 00 01 Preconstruction Submittals Key Issue Receipt 1.3.12.1

3 00 70 00 06 Test Reports Pre-Construction Testing Record 1.3.11 G

4 00 70 00 07 Certificates Welding, Cutting and Brazing Permit 1.4 G

5 00 70 00 07 Certificates Framed Instructions 1.8

6 00 70 00 11 Closeout Submittals Key Return Receipt 1.3.12.1

7 00 71 00 01 Preconstruction Submittals Health and Safety Plan 1.3 G

8 00 71 00 01 Preconstruction Submittals Internal Combustion Engines Plan 1.3.5 G

9 00 71 00 01 Preconstruction Submittals Airfield Construction Waiver 1.5 G

Must be turned in by the 5th day of the month to make that month Waiver Package. Provide editable form to the CO to be forwarded to Community Planning. Allow 45 days for processing.

10 00 71 00 01 Preconstruction Submittals FAA Form 7460-1 1.5.3 G

11 00 71 00 07 Certificates Safety Meetings 1.3

12 00 71 00 07 Certificates FOD Awareness and Prevention Training 1.4

13 00 72 00 01 Preconstruction Submittals Restoration Plan 1.3.2 G

14 00 72 00 01 Preconstruction Submittals Storm Water Pollution Prevention Plan 1.3.3.2 G

15 00 72 00 01 Preconstruction Submittals Water System Construction Permit 1.3.3.6 G

16 00 72 00 01 Preconstruction Submittals AF Form 3952 Chemical/Hazardous Material Request/Authorization 1.4 G

17 00 72 00 01 Preconstruction Submittals Spray Painting Plan 1.9 G

18 00 72 00 01 Preconstruction Submittals Environmental Management System Awareness Training 1.1

19 00 72 00 03 Product Data New Boiler Information Form 1.3.8.2 G

20 00 72 00 03 Product Data Affirmative Procurement Documentation or Green Statement 1.3.10 G Provide only one. Reference specification for additional information

21 00 72 00 06 Test Reports AF Form 487 Generator Operating Log (Inspection and Testing) 1.3.8.1 G

22 00 72 00 07 Cerificates Fire Ant Federal Compliance Agreement or state phyto-sanitary certificate 1.3.4.1

23 00 72 00 07 Cerificates Monthly Hazardous Material Usage Report 1.4 G Provide 1st week of each month during construction

24 00 72 00 07 Cerificates Refrigerant Technical Certifications 1.5 G

25 00 72 00 07 Cerificates Refrigerant Installation 1.5 G

26 00 72 00 08 Manufacturer's Instructions Safety Data Sheets/Material Safety Data Sheets 1.4

27 00 72 00 11 Closeout Submittals Notice of Termination (ODEQ Form 640-572) 1.3.3.2 G

28 00 72 00 - Attch 5 01 Preconstruction Submittals Construction Debris Analysis Plan 1.2.3 G

29 00 72 00 - Attch 5 07 Certificates Monthly Debris Management Report 2 G Provide 1st week of each month during construction

30 00 72 00 - Attch 11 01 Preconstruction Submittals Tree Protection Plan 2.1 G

31 01 32 16.00 20 01 Preconstruction Submittals Baseline Construction Schedule 1.2 G Provide within 10 days of NTP.

32 01 32 16.00 20 01 Preconstruction Submittals Baseline Design Schedule 1.2 G Provide within 10 days of NTP.

33 01 32 16.00 20 07 Certificates Monthly Updates 1.4 Provide 1st week of each month during construction, or as directed by CO

34 01 32 16.00 20 07 Certificates 3-Week Look Ahead Schedule 1.6 Provide weekly with the Contract Progress Report

TITLE: WWYK180061

SUBMITTAL REGISTER

JOB NAME: Repair HVAC System, B3707 LOCATION: Tinker Air Force Base, Oklahoma

CONTRACT NO: TBD

CONTRACTOR: TBD

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES APPROVING AUTHORITY

Submittal Register_v3_03/07/22

Acti vity

Transm ittal #

Specification Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES APPROVING AUTHORITY

35 01 33 00 01 Preconstruction Submittals Submittal Register 1.8 G

36 01 33 16.00 10 01 Preconstruction Submittals Design Quality Control Plan 1.5.1 G

37 01 33 16.00 10 01 Preconstruction Submittals Initial Design Conference 1.5.2.2

38 01 33 16.00 10 01 Preconstruction Submittals Preconstruction Conference 1.5.2.3

39 01 33 16.00 10 01 Preconstruction Submittals DCM Procedures 3.5.1 G

40 01 33 16.00 10 01 Preconstruction Submittals Submittal Register 3.8.4 G

41 01 33 16.00 10 05 Design Data Design and Code Checklists 1.7.1 C

42 01 33 16.00 10 05 Design Data Interim Design Submittals 3.2.1 R

43 01 33 16.00 10 05 Design Data Interior And Exterior Building Finishes Scheme 3.6.5.1.1 G

44 01 33 16.00 10 05 Design Data Conference Documentation 3.7.3

45 01 33 16.00 10 05 Design Data Final Design Submittals 3.8 R

46 01 33 16.00 10 05 Design Data Design Complete Documents 3.9 C

47 01 33 16.00 10 11 Closeout Submittals DD Form 1354 3.8.5 A

48 01 45 00.00 10 01 Preconstruction Submittals Quality Control (QC) Plan 3.2 G

49 01 45 00.00 10 01 Preconstruction Submittals Additional Requirements for Design Quality Control (DQC) Plan 3.2.2 G

50 01 45 00.00 10 05 Design Data Discipline-Specific Checklists 3.2.2

51 01 45 00.00 10 05 Design Data Design Quality Control 3.9.1

52 01 45 00.00 10 06 Test Reports QC Documentation 3.9 Provide weekly with the Contract Progress Report

53 01 50 00 01 Preconstruction Submittals Request for Contractor Staging Area 1.1 G

54 01 50 00 01 Preconstruction Submittals Photographic Record 1.3

55 01 78 00 03 Product Data Warranty Letter 1.7.1

56 01 78 00 03 Product Data Warranty Tags 1.7.3

57 01 78 00 03 Product Data Spare Parts Data 1.5

58 01 78 00 08 Manufacturer's Instructions Instructions 1.7.1

59 01 78 00 10 Operation and Maintenance Data Operation and Maintenance Manuals 3.4 G Provide (2) electronic sets (optical media) and

(1) hard copy

60 01 78 00 11 Closeout Submittals Working As-Built Drawings 3.1 G Provide (2) electronic sets (optical media) and

(2) hard copies

61 01 78 00 11 Closeout Submittals Record Drawings 3.3 G Provide (2) electronic sets (optical media) and

(1) hard copy

62 01 78 00 11 Closeout Submittals Certification of EPA Designated Items 2.3 G

63 01 78 00 11 Closeout Submittals Certification Of USDA Designated Items 2.4 G

64 01 78 23 10 Operation and Maintenance Data Operation and Maintenance Data 1.2 G Provide 30 days prior to scheduled Training

65 01 78 23 10 Operation and Maintenance Data O&M Database 1.3 G

66 01 78 23 10 Operation and Maintenance Data Training Plan 3.1.1 G Provide 30 days prior to scheduled Final Inspection

67 01 78 23 10 Operation and Maintenance Data Training Content 3.1.2 G Provide 14 days prior to scheduled Training

68 01 78 23 10 Operation and Maintenance Data Training Outline 3.1.3 G Provide 14 days prior to scheduled Training

69 01 78 23 11 Closeout Submittals Training Video Recording 3.1.4 G

70 01 78 23 11 Closeout Submittals Validation of Training Completion 3.1.6 G

71 SOW 07 Certificates Contract Progress Report(s) 2.4 G Provide weekly throughout life of contract.

Utilize AF Form 3065, Contract Progress Report (or equal)

Acti vity

Transm ittal #

Specification Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES APPROVING AUTHORITY

Submittal Register_General Requ